HomeMy WebLinkAboutConstruction site runoff permitBuilding Division, 410 E. Washington St. Iowa City, IA 52240 319/356-5120 www.icgov.org
Construction Site Runoff (CSR) Permit Application
Permit Fee $150.00
Site Address or Lot and Subdivision
Applicant Applicant’s E-Mail
Address City, State, ZIP
Telephone (office) (cell)
Applicant’s Designated Agent E-Mail
Address City, State, ZIP
Telephone (office) (cell)
Project Description
Is the Applicant responsible for Iowa Department of Natural Resources (IDNR) National Pollutant Discharge
Elimination System (NPDES) General Permit #2 (GP2)? Yes No
REQUIRED CERTIFICATION
I certify under penalty of law that I understand the terms and conditions of the NPDES GP2 that authorizes the stormwater discharges
associated with industrial activity from the construction site as part of this certification. Further, by my signature, I understand that I am
becoming the permittee or a co-permittee, along with the owner(s) and other contractors and subcontractors signing such certifications, to
the IDNR NPDES GP2 for “Stormwater Discharge Associated with Industrial Activity for Construction Activities” at the identified site.
As a permittee or co-permittee, I understand that I, and my company, am legally required under the Clean Water Act and the Code of
Iowa, to ensure compliance with the terms and conditions of the stormwater pollution prevention plan (SWPPP) developed under this
CSR/NPDES permit and the terms of this CSR/NPDES permit.
Applicant’s/Agent’s Signature Title Date:
The CSR permit will not be issued until an initial inspection of the site is conducted & required controls are
properly installed.
City Staff Use Only
NPDES Permit Authorization from IDNR Yes No
Notice of Intent to IDNR Yes No
Proof of Publication to IDNR Yes No
Permittee SWPPP Yes No
Co-Permittee/Transferee SWPPP Yes No
CSR Permit # City Approval by Date
Building Division, 410 E. Washington St. Iowa City, IA 52240 319/356-5120 www.icgov.org
Construction Site Runoff Permit (CSR) Required Information
Project Address or Lot and Subdivision
Subcontractors Company Name Contact Name and Telephone
Excavation
Geothermal
Foundation
Flatwork
Framing
Plumbing
Electric
Mechanical
Siding
Painting
Landscaping
Drywall
Mason
Pollution Prevention
Miscellaneous
Construction Schedule Dates (estimated) Pollution Prevention Schedule Dates (estimated)
Excavation Perimeter Controls
Geothermal Silt fence Rolled Other
Foundation Site Entry & Exit (2” clean rock)
Groundwork Inlet Protection
Backfilling Concrete Wash-Out
Flatwork Pit Above-ground enclosure
Framing Solid Waste Removal
Plumbing Portable Toilet
Electrical Temporary Stabilization
Mechanical After 14 days of inactivity on the site
Insulation & Sheetrock Other
Roofing Other
Siding & Masonry Ongoing Maintenance
Drives & Walks
Paint & Interior Finish
Landscaping Stabilization of all Disturbed Areas
The CSR permit will not be issued until an initial inspection of the site is conducted & required controls are
properly installed.
Building Division, 410 E. Washington St. Iowa City, Iowa 52240 319/356-5120 www.icgov.org
Construction Site Runoff Permit Review Checklist
Address Reviewed by Date
Received Comments Action Required Application Information
Name & contact information (24-hour contact)
Signed certification
IDNR NPDES permit, proof of publication, & Notice Of Intent
Sub-contractors & contact information
Estimated sequence of construction activity
Estimated sequence of pollution prevention measures
Form for weekly & post-rain inspections (required after ½” rain)
Stormwater Pollution Prevention Plan (SWPPP) Information
Size of lot
Area of site to be disturbed
Local waterway potentially impacted by pollutants
Site drainage patterns, shown by arrows
Slope stabilization methods or limits of construction
Perimeter controls
Stormwater inlets
Stabilized exit (2” clean rock or existing pavement)
Soil stockpile(s) with perimeter controls or temporary stabilization
Concrete washout (note if on another lot)
Equipment & material storage (hazardous material kept under cover)
Construction waste disposal
Portable toilet
Location of SWPPP documents & inspection reports
The CSR permit will not be issued until an initial inspection of the site is conducted & required controls are properly installed.