Why Conduct the Study?
•The Taft Speedway Study, completed in Year
2012 discovered issues with drainage from north
of Idyllwild.
•To evaluate the existing drainage system and
see if deficiencies exist, where they are and the
extent of the problem.
Project Purpose
•Determine impact of runoff draining through the
Idyllwild area.
•Review the history of drainage problems.
•Determine extent of drainage issues and
problems.
Project Goals
•Identify drainage deficiencies in the existing
storm drainage system.
•Identify conveyance improvements that will
provide stormwater bypass during high flow
periods.
•Maintain low flow conveyance to the existing
ponds for pond management.
What Goes into a Study Process?
•Infrastructure Information
What Goes into a Study Process?
•Land Use
What Goes into a Study Process?
•Precipitation
•Public Input
What Goes into a Study Process?
•Modeling Process
▫Actual combination of pipe flow rates and
overland conveyance conditions.
▫Looks at various rainfall events
▫Models present day land-use and future land-use.
•Defining the Problem
▫Drainage impacts- How much, how often and
where problems are located.
What Goes into a Study Process?
Mapping
Problem
Areas to review.
Interact with
the public
to make sure
problems are
correctly identified
QUESTIONS?
Mike Ryan, PE
HR Green, Inc.
mryan@hrgreen.com