HomeMy WebLinkAboutPIN Grant Review Process July 2015-June 2016
PROGRAM FOR IMPROVING
NEIGHBORHOODS
APPLICATION, EVALUATION, PAYMENT,
AND MONITORING PROCESS
************************************************************
TIME SCHEDULE
March 27, 2015 (Friday) - 5:00 PM - Grant applications due to Office of
Neighborhood Services (electronic or hard copies accepted.)
April 8, 2015 (Wednesday) Tentative - 5:30 PM - Neighborhoods present
their PIN applications to the City Staff.
April 22, 2015 (Wednesday) – Results of City Staff recommendation for
funding is forwarded to applicants.
May 8, 2015 (Friday) – Applicant deadline to request an appeal of decision.
May 13, 2015 (Wednesday) - 5:30 PM – Neighborhood Council reviews
appeal request and decides if changes will be requested to the staff
recommendation.
May 22, 2015 (Friday) – 5:00 PM – Staff response forwarded to all grant
applicants.
Week of June 10, 2015 – Memo developed from Neighborhood Council to
the City Council regarding funding appropriation for PIN grants.
July 1, 2015- Funds available for projects.
INSTRUCTIONS FOR COMPLETING APPLICATION
Complete one application form for each project proposal. Please print clearly in ink or type. Each block
should be responded to as completely as possible. If a block is not applicable, indicate "NA". If additional
pages are necessary to respond to a question, please number the additional pages and label with the
corresponding block question found on the application. EXAMPLE: "What are the goals of this program
and why is it needed?"
Instructions for Blocks within Application Form
A. Briefly describe the activities (meetings, newsletters, events, participation in the
Neighborhood Council etc,) of your neighborhood association over the past 12 months.
This information can include social events, board meetings, steering committee meetings,
etc. This information provides some indication of past history of the neighborhood.
B. Describe the project briefly and how this project will meet a need of the neighborhood
that has been determined by the neighborhood association. Include problems that
currently exist and will be addressed by the project. Present information from studies,
reports, etc. to show the need for the project. Demonstrate why the neighborhood
association should be the group to implement this project
C. Indicate the steps that will occur during the project implementation and approximately
when they are expected to occur. Detail if the project will be or could be phased over a
number of years. Also indicate if this project is a continuation of previously funded PIN
grants.
D. Detail the organizations, individuals, or other resources that have been contacted and
expressed a financial or volunteer commitment to the project. It is important to have
researched all available resources to assist in this project prior to application. Please
indicate, if available, the time commitment or financial resources that have been offered.
City Staff time cannot be considered a volunteer or cash resource but should be
documented to detail that all necessary staff have been contacted.
E. Detail the process involved in soliciting neighborhood input into this PIN grant request.
Be explicit about who was involved, how many responded, how the process occurred and
describe the results.
F. If applicable, describe how this project will benefit low income, elderly, youth or
disadvantaged youth. Describe how low income benefit has been determined and why
these groups have been selected as the focus of the project.
G. If you were not to receive PIN funding this year, will you still receive other proposed
funding listed in Block C? How would these funds be utilized?
H. There may be the need to allocate less funding than requested. Please describe how
the scale of the project can be reduced or the project phased over a number of years. It is
important to keep in mind that annual PIN funding is not guaranteed and a phased project
may not be completed. Each phase should attempt to complete an entire goal.
It is important to document that the project has been thoroughly thought through, what activities will
occur, and that the project is feasible. It is not necessary to receive written bids for any materials or
equipment involved in the grant application but a reasonable estimate should be determined. It is
necessary to determine what other forms of assistance (financial, volunteer or consultant) are available
from other sources prior to grant submission.
EVALUATION PROCESS
A staff member from each of the following departments will make up a PIN Grant Review Committee:
Parks and Recreation, Neighborhood and Development Services, Public Works, and City Manager’s Office.
Staff will be provided with copies of all submitted applications and reviewed according to the Ranking
Criteria. Staff will also recommend a funding level for each application based on the outcome of the
ranking. These results will be sent to all PIN grant applicants as well as all other Neighborhood Council
representatives for their review and approval.
If there is the interest by an applicant to appeal the decision of the staff committee, a Neighborhood
Council meeting can be scheduled to discuss that appeal if the majority of neighborhood representatives
involved in the review process support that appeal request. The staff recommendation can be adjusted
upon majority support by those neighborhoods involved in the appeal discussion. The staff review
committee will be notified of any change to their initial recommendation.
When a final appropriate of grant funding has been approved by both staff and neighborhood association
representatives, a memo to the City Council will be drafted by the Neighborhood Council explaining the
process and final funding appropriation before the end of June of each funding year.
PAYMENT PROCESS
Funds will be available from July 1, 2015 to June 30, 2016. The work must be verified as complete by the
Office of Neighborhood Services to receive payment.
To obtain funds for work that has been completed, an invoice must be submitted to the Neighborhood
Outreach Coordinator from the contractor/supplier. The invoice must be made out to the City of Iowa
City. It is possible to make payment for partially completed work or provided materials although it would
be helpful to limit the number of such payments if possible.
At the time that the invoice is submitted, please arrange a time with the Neighborhood Outreach
Coordinator to inspect and verify that the work is completed. It may be necessary to have the work
inspected by various staff people dependent upon the project.
Invoices submitted by any Thursday will be paid on the Friday of the following week. The checks will
normally be mailed out unless otherwise indicated.
Materials can be paid for only if they have been utilized or installed as detailed in the grant application.
The completed work must be acceptable to the neighborhood and City for payment to be made.
GRANT MONITORING AND CLOSEOUT
The Neighborhood Council will act as a monitoring body for the PIN projects throughout the year by asking
for periodic updates on the progress by the responsible neighborhood association. The Neighborhood
Council may wish to visit the project site (if applicable).
In order to confirm that all PIN funding will be expended within the funding year, neighborhoods must
present written verification of intentions to expend all funds by January 2016. At that time, if it is apparent
that all funds will not be expended during the funding year, the Neighborhood Council may choose to
reallocate funds to unfunded PIN grant requests based on original ranking. If a neighborhood association
chooses not to utilize the funds, the next ranked grant applications will be offered the opportunity until all
funds are committed. The City Council will be requested to approve any reallocation of funds.
Substantial changes or amendments that are seen as necessary during the grant implementation period
must receive the approval of the Neighborhood Council and relayed to the City Council. Neighborhood
Associations should allow for the time necessary for the Neighborhood Council to review any
amendments.