HomeMy WebLinkAboutImplementationIOWA CITY DOWNTOWN AND PEDESTRIAN MALL STREETSCAPE PLAN UPDATE . DRAFT P | 146 If you can dream it, you can do it. – Walt Disney FEBRUARY 2014 147 I m p l e m e n t a t i o n SECTION 8 Implementation IOWA CITY DOWNTOWN AND PEDESTRIAN MALL STREETSCAPE PLAN UPDATE . DRAFT P | 148 IMPLEMENTATION | INTRODUCTION Studies These projects are intended to provide additional detail that can be incorporated into subsequent design and im- plementation phases. As an example, it is recommended that an urban arborist be retained to provide a profession- al recommendation on the health and care of existing mature trees within the downtown core and pedestrian mall. These recommendations will have a great deal of influence on the next phase of design work. Design + Engineering To move larger recommendations forward, additional de- sign work is required to resolve details, provide accurate implementation budgets and to eventually construct the physical improvements. PRIORITIZATION A significant amount of public and stakeholder input was utilized to form the recommendations and guide decision- making throughout the master planning process and this plan update. As in most projects that involve stakeholders with varied interests, its fair to say that full consensus of recommendations was not always achieved. The same can be said regarding how to prioritize improvements. The following pages outline recommendations for how to approach short term [ 1-2 year ], as well as mid-range [ 3-15 year ] planning and implementation objectives. Gen- erally speaking, the highest priority projects are those that address safety and infrastructure needs, such as universally accessible public space and aging underground utilities. Second priority is given to elements that enhance and contribute to a cohesive and unique identity throughout Downtown, while maintaining focus on maximizing value for the City. In most cases, priority was given to projects located in the core of Downtown, largely driven by the philosophy that the core offers the highest return on invest- ment, focuses improvements where the highest numbers of pedestrians exist, and offers a logical way of sequenc- ing phased improvements. Selection and approach towards implementation of the first phases are particularly important as they will establish the physical character, public perception and interest in subsequent phases. Prioritizing improvements based on the design concepts is only the first step, as the City must identify resources and strategies for on-going funding, as well as efficient and effective maintenance practices. The following section presents preliminary ideas on how to implement the overall vision with meaningful projects of varying levels of cost and impact. IMPLEMENTATION The achievement of the Iowa City Downtown Street- scape and Pedestrian Mall Plan Update will require public sector involvement of the City of Iowa City, private sector involvement in terms of development plans and requirements of private land owners and public / private partnerships where the City and land- owners will need to work jointly to achieve common goals. A variety of planning and financial tools will be required to implement the vision. It should be noted that implementation recommendations and cost summaries are prepared to guide planning decisions and in all cases additional design, engineering and stakeholder input will be necessary. As with any planning effort, there becomes a point where information and recommendations may no longer be considered relevant or appropriate. Fac- tors such as traffic volumes, evolution of private de- velopment, rapidly changing demographics within the community and the University of Iowa’s desire to be ‘fresh’ are key drivers in determining whether or not the recommendations within this plan continue to hold merit. Recommendations should be reviewed and updated towards the end of this documents life span, which is anticipated to be 10-15 years. PHASING Implementation of the projects will require a num- ber of phases over several years. The phasing plans presented on the following pages identify a clear path for immediate decision-making within the first two years. Short term projects are identified as one of three categories: quick starts, studies and design/ engineering. Quick Start Projects Projects in this category have been identified by the Consultant, City Staff and Stakeholders as small scale projects that require minimal planning or de- sign efforts to implement. As funding allows, these projects could be completed in a 3-6 month time frame, while more elaborate projects may require anywhere from 9-24 months of additional design, engineering and construction time before enhance- ments are realized. FEBRUARY 2014 149 WALKABILITY / PEDESTRIAN FRIENDLY POLICY + PLANNING MAINTENANCE ENVIRONMENTAL BRANDING + BEAUTIFICATION ARTS + CULTURE • E/W Pedestrian Mall alley lighting - install grapevine spheres • Large format banner or art on building along Burlington • Ramp facade improvements on Burington • NSMP building lighting [ North Linn +Market ] • Lighting mock-ups in Ped Mall • Planting rail + annual plantings in Ped Mall - pilot • Infill tree planting on streets that are +2 years out or streets not impacted by improvements • Purchase and install recycling stations in Ped Mall • Bioretention planting area - pilot installation • Establish a Green Alley program • Electric vehicle charging station pilot • Play surface at existing play area in Ped Mall • Electrical upgrades to Iowa Avenue - for events • Urban arborist - study Ped Mall / Clinton / Washington Tree pruning in Ped Mall [ following arborist review ] • Brass plaques in Iowa Avenue - repair or relocate • Miscellaneous repair and miscellaneous painting • Traffic modeling study • Establish fundraising committee • Policy recommendations - cafe / signage / purple meters / waste receptacles committee to discuss and make recommendations on the suggested areas for improvement • Repair of limestone planters not anticipated to be impacted by the redesign • Sidewalk repairs throughout Downtown • Update tree grates at Iowa Avenue • Purchase and install one sheltered bike parking with photovoltaics • Install new benches along South Linn [ Sr. Center - ICPL ] • North Linn and Bloominton painted crosswalks SAFETY IMPLEMENTATION | QUICK START PROJECTS IOWA CITY DOWNTOWN AND PEDESTRIAN MALL STREETSCAPE PLAN UPDATE . DRAFT P | 150 IMPLEMENTATION | PRIORITIZATION PRIORITY PRIORITIZATION CHART BASE PROJECT COST KEY ELEMENTSPROJECT / STREET Market Street 1 Dubuque Street Pedestrian Mall $880,500 - 1,365,000 $830,000 - 1,285,000 Extend the Pedestrian Mall character. Es- tablish a gateway feel with multiple layers of overhead lighting. Improve sidewalk pavement and storm sewer upgrades. Upgraded fiber duct bank and electrical distribution for enhanced lighting through- out NSMP. Conversion to two way traffic. PRIORITIZATION TEXT HERE. IMPLEMENTATION TEXT HERE. Washington Street +/- $2,500,000 phase 1 +/- $2,000,000 phase 2 Improve sidewalk pavement, address criti- cal update to water main, replace & relo- cate storm sewer between Linn & Gilbert, enhance retail environment with streets- cape components. $2,430,000 - 3,766,000 Renovate Black Hawk Mini Park. Update lighting throughout, enhance plantings, site furnishings and add way-finding kiosks. Consider development of programmed spaces and improved performance area and stage. FEBRUARY 2014 151 PRIORITY PRIORITIZATION CHART CONTINUED Burlington Street Iowa Avenue Iowa / Gilbert Gilbert Street 2 $3,600,000 - 5,557,000 $728,000 - 1,130,000 $418,000 - 648,000 $1,915,000 - 2,968,000 Introduce pedestrian scale elements. Up- grade water main. Pedestrian crossing improvements, plantings and large scale building facade treatments to improve visu- al interest. Address maintenance related items such as lit- erary walk bronze emblems, heaving tree grates and spalling limestone light pole bases. Enhance electrical service for events and add appropri- ately scaled light columns with banners. Enhanced crosswalks to meet ADA requirements & improve walkability. Focus on adding pedestri- an scale, burying of overhead utilities & neces- sary water main upgrades. Reduction in travel lanes. Enhanced bicycle accommodations. IMPLEMENTATION | PRIORITIZATION BASE PROJECT COST KEY ELEMENTSPROJECT / STREET PRIORITY Linn Street3 North Linn $1,250,000 - 1,935,000 $640,000 - 990,000 Improved lighting to unify corridor and improve energy efficiency. Updated water main, sanitary, and fiber optic duct. Addition of much needed street furniture and wayfinding elements. Upgrades to sanitary, water main and significant storm sewer enhancements. As an alternate, consider burying of overhead utility lines. Com- pliment recent streetscape improvements with added plantings and improved seating areas. BASE PROJECT COST KEY ELEMENTSPROJECT / STREET Clinton Street $1,844,000 - 2,855,000 Enhanced crosswalk environment and curb bumpouts to improve pedestrian safety and walkability, Updated water main and fiber optic. Enhanced electrical capacity. Wider East sidewalks. College Street $601,000 - 932,000 Updated street and sidewalks, addition of a healthy landscape and tree canopy, improved crosswalks to meet ADA requirements and rein- force connectivity. Water main and fiber optic upgrades. Bloomington Street $277,000 - 440,000 Implementation of small scale improvements, in- cluding pedestrian scale lighting to match core NSMP and street furniture. Bury a small section of overhead electric and make necessary up- grades to water main and fiber optic duct. IOWA CITY DOWNTOWN AND PEDESTRIAN MALL STREETSCAPE PLAN UPDATE . DRAFT P | 152 CALENDAR YEAR 2014 - QUICK START PROJECTS 1. Ped Mall Playground Resurfacing $ 85,000 2. Sheltered Bike Parking Pilot w/ PV $ 30,000 3. Large Format Banner/Art on Building at Burlington Street $ 50,000 4. Lighting Mock-up in Ped Mall $ 50,000 5. Planting Rail Mock-up in Ped Mall $ 15,000 6. Purchase and Install Recycling Containers in Ped Mall $ 20,000 7. Infill Trees on College Street and Burlington Street $ 25,000 8. Lighting at N.Linn and Market Street [ match ICDD funding ] $ 30,000 9. Sidewalk Repair $100,000 10. Iowa Avenue Tree Grates [ and other streets as needed ] $ 85,000 11. Misc. Repair [ trash receptacles, bench, etc. ] $ 25,000 12. Misc. Painting $ 25,000 13. LED Conversions of Select Existing Lights $ 70,000 14. Linn Street Benches $ 10,000 15. North Linn and Bloomington Painted Crosswalk $ 500 16. Design of Ramp Facade Improvements on Bulington $150,000 17. Electric Vehicle Charging Stations Pilot $ 44,000 $814,500 Contingency [ 10% ] $ 81,450 $895,950 STUDIES 1. Urban Arborist to Evaluate Plantings in Ped Mall, Washington + Clinton $ 25,000 2. Traffic Modeling for Downtown Iowa City $ 85,000 3. Survey [ Washington Street | Ped Mall | Dubuque Street ] $ 28,000 Contingency [ 10% ] $ 81,450 $219,450 DESIGN + ENGINEERING PROJECTS 1. Pedestrian Mall - Schematic Design thru Construction Documents $215,000 2. Washington Street - Schematic Design [ Clinton to Linn ] $ 55,000 4. Dubuque Street - Schematic Design $ 45,000 Contingency [ 10% ] $ 31,500 $346,500 CALENDAR YEAR 2015 - QUICK START PROJECTS 1. Projects TBD $ 75,000 DESIGN + ENGINEERING PROJECTS 1. Pedestrian Mall Bidding and Construction [ Phase One ] $ 3,000,000 2. Dubuque Street Design Development thru Construction Documents $ 100,000 Contingency [ 10% ] $ 317,500 $3,492,500 IMPLEMENTATION | PHASING STRATEGY FEBRUARY 2014 153 0’800’400’200’ IMPLEMENTATION | PROJECT IMPROVEMENT FRAMEWORK PED MALL BLOOMINGTON MARKET JEFFERSON IOWA AVE WASHINGTON COLLEGE BURLINGTON CALENDAR YEAR 2014 CL I N T O N DU B U Q U E LI N N S T R E E T GI L B E R T VA N B U R E N 15 8 9 9 9 4 54 6 1 2 10 14 9 7 73 #Quick Start Project Studies Design and Engineering Projects LEGEND IOWA CITY DOWNTOWN AND PEDESTRIAN MALL STREETSCAPE PLAN UPDATE . DRAFT P | 154 COST OPINIONSAccuracy The level of detail and accuracy of pricing in this opinion of probable cost are consistent with the degree of com- pleteness of the documents used for estimating purposes. The documents used to prepare estimates include master plan level design, shown throughout this document and information provided by the Planning team members. Ad- ditional information was obtained through discussion with the Client, Stakeholders and industry contacts. No site survey information was available to verify utilities, site ele- ments or quantities. Bid Conditions The planning recommendations have been estimated as large scale projects to achieve economy of scale. If the project is broken down and approached in small phases, the total estimated costs will likely be higher. Items Affecting Costs Items which may change the probable costs include, but are not limited to: Restrictive or specialized technical or material specifica- tions and accelerated project schedules. Escalation Costs are reflective of current costs with no escalation in- cluded. A labor and material escalation factor will need to be added once a construction period has been deter- mined. Probable Cost Opinion Objective This cost framework is intended to be used as a tool for decision making and managing phasing strategies during the next phase of the project. It is prepared using indus- try contacts, experience, and the best judgment of the professional consultants. This estimate is intended to re- flect an amount close to what would be the low bid of the project with respect to the present level of design and documentation. The consultant has no control over mar- ket conditions, wage rates, or any contractor’s method of determining prices or quantities. Therefore, the consultant cannot and does not guarantee this cost opinion will not vary from actual costs. COST SUMMARIES The following summaries provide a synopsis of recommen- dations and associated costs for each street, the pedestri- an mall and Blackhawk Mini Park. In each case the costs are rounded to reflect an order of magnitude cost for el- ements that are considered to be part of the base proj- ect. Additionally, projects involve ‘alternates’. These al- ternates are intended to capture recommendations that were important to stakeholders, but either not supported by the majority, warranted additional study to test valid- ity or maintenance requirements, or required additional funding beyond what may be available from traditional City sources. Below the costs identified for specific categories of work are costs that cover expenses often referred to as ‘soft costs’: General Requirements This category addresses items such as contractor mark- ups, bonding, permits, temporary power and water, as well as NPDS permits. The complexity of the project, scale and contractor selection are all important factors in deter- mining the appropriate percentage to carry forward. Contingency This line item addresses the unknowns that go hand-in- hand with design and constructing urban infrastructure projects. Given that these are planning level cost opinions and design work is not based on actual site survey or con- ditions, a sizable contingency (25% of construction value) is recommended. As projects move forward utilizing actu- al site surveys and design development the contingency amount is typically reduced to align with the level of de- sign and engineering. Design, Engineering and Survey To move larger recommendations forward, additional de- sign work is required to resolve details, provide accurate implementation budgets and to eventually construct the physical improvements. It is anticipated that the majority of these projects will require professional design and engi- neering consultants to advance the design and produce bid documents. Traditional costs for basic services [ sche- matic design thru construction administration ] are intend- ed to be included within the 15% allowance. Additionally, costs associated with site surveys is included within. While many of the projects will require multiple professional dis-ciplines [ landscape architecture, civil, electrical, structur-al engineering, lighting designer,etc.] the actual cost of services will fluctuate based on project scale, complexity, market conditions and scope of work. IMPLEMENTATION | COST SUMMARY FEBRUARY 2014 155 IMPLEMENTATION | PROJECT AREA COST SUMMARY PEDESTRIAN MALL [ +/- 95,000 Square Feet ] New Pedestrian Lighting Atmospheric Lighting at Planting Areas Playground Surface Enhancement Landscape Plantings + Irrigation Wayfinding Kiosks See page 106 for more detail. Site Preparation $ 275,000 Utilities $ 220,000 Paving $ 475,000 Planter Walls $ 100,000 Landscape + Irrigation $ 605,000 Site Furnishings + Amenities $ 380,000 Electrical and Lighting $ 375,000 General Requirements [15% ] $ 364,500 Contingency [ 25% ] $ 607,500 Design, Engineering, Survey [15%] $ 364,500 Alternates Eco Lab $ 300,000 Sound Garden $ 250,000 Media Room + Table $ 175,000 Story Walls + Lighting $ 215,000 Covered Bike Parking [2] $ 60,000 WDF Stage and Canopy $ 400,000 WDF Stage Lighting $ 40,000 WDF Stage A/V Upgrades $ 50,000 WDF Lighting Enhancements $ 50,000 WDF Art Modifications in Seating Area $ 40,000 $ 2,430,000 $ 3,766,500 IOWA CITY DOWNTOWN AND PEDESTRIAN MALL STREETSCAPE PLAN UPDATE . DRAFT P | 156 IMPLEMENTATION | PROJECT AREA COST SUMMARY Site Preparation $ 55,000 Utilities $ 35,000 Paving $ 155,000 Planter Walls $ 65,000 Landscape + Irrigation $ 75,000 Site Furnishings + Amenities $ 165,000 Electrical and Lighting $ 65,000 General Requirements [15% ] $ 92,250 Contingency [ 25% ] $ 154,000 Design, Engineering, Survey [15%] $ 92,250 Alternates Feature Area / Public Art $ 750,000 - 1,500,000 $ 615,000 BLACK HAWK MINI PARK [ +/- 9,500 Square Feet ] New Public Space Public Art Variety of Seating See page 108 for more detail. $ 953,500 FEBRUARY 2014 157 Site Preparation $ 102,000 Utilities General $ 50,000 Storm/Sanitary Separation $ 20,000 Fiber Optic Duct $ 25,000 Paving $ 110,000 Landscape $ 90,000 Site Furnishings $ 40,000 Electrical and Lighting $ 385,000 General Requirements [ 15% ] $ 125,000 Contingency [ 25% ] $ 205,000 Design, Engineering, Survey [ 15% ] $ 140,000 Alternate Bioretention $ 150,000 Festive Lighting $ 80,000 IMPLEMENTATION | PROJECT AREA COST SUMMARY MARKET STREET [ 2 blocks ] Festive Lighting New Pedestrian + Street Lighting Gateway Elements Enhanced Plantings See page 98 for more detail. NORTH LINN STREET [ 2.5 blocks ] Underground Utility Updates Updated Pedestrian Lighting Gateway Element Public Art See page 96 for more detail. $ 830,000 Site Preparation $ 70,000 Utilities General $ 85,000 Sanitary $ 4,500 Water Main $ 22,000 Storm Sewer $ 127,000 Fiber $ 22,000 Paving $ 36,000 Landscape $ 92,000 Site Furnishings $ 30,000 Electrical and Lighting $ 151,500 General Requirements [15% ] $ 95,000 Contingency [ 25% ] $ 160,000 Design, Engineering, Survey [15%] $ 95,000 Alternate Bury Overhead Electric $ 525,000 $ 1,285,000 $ 640,000 $ 990,000 IOWA CITY DOWNTOWN AND PEDESTRIAN MALL STREETSCAPE PLAN UPDATE . DRAFT P | 158 BLOOMINGTON STREET [ 1 block ] Updated Utility Duct Bank Pedestrian Crossing Updates Landscape Enhancements Pedestrian Lighting Historical Markers See page 102 for more detail. Site Preparation $ 40,000 Utilities General $ 28,000 Water Main $ 25,000 Fiber Duct $ 12,000 Paving $ 15,000 Landscape $ 23,000 Site Furnishings $ 38,000 Electrical and Lighting $ 96,000 General Requirements [15% ] $ 43,000 Contingency [ 25% ] $ 72,000 Design, Engineering, Survey [15%] $ 43,000 Alternate Bury Overhead Electric $ 10,000 $ 277,000 $ 440,000 BURLINGTON STREET [ 3 blocks ] Gateway Elements New Pedestrian + Street Lighting Water Main Upgrade Enhanced Plantings Building Art / Mural See page 90 for more detail. Site Preparation $ 350,000 Utilities General $ 90,000 Water Main $ 150,000 Fiber Duct $ 40,000 Traffic Signals $ 700,000 Paving $ 1,410,000 Landscape $ 160,000 Site Furnishings $ 67,000 Electrical and Lighting $ 638,000 General Requirements [ 15% ] $ 540,000 Contingency [ 25% ] $ 900,000 Design, Engineering, Survey [ 15% ] $ 540,000 Alternates Bioretention $ 315,000 Building Mural / Art $ 50,000 [ Each ] $ 3,600,000 $ 5,557,000 IMPLEMENTATION | PROJECT AREA COST SUMMARY FEBRUARY 2014 159 IMPLEMENTATION | PROJECT AREA COST SUMMARY CLINTON STREET [ 3 blocks ] Monument Lights New Pedestrian + Street Lighting Wayfinding Kiosk Enhanced Plantings Water Main Upgrade See page 84 for more detail. COLLEGE STREET [ 1 block ] Enhanced Plantings Water Main Upgrade Accent Unit Pavers New Traffic Signals at Gilbert See page xx for more detail. Site Preparation $ 164,000 Utilities General $ 85,000 Water Main $ 26,000 Fiber Duct $ 36,000 Paving $ 612,000 Landscape $ 141,000 Site Furnishings $ 190,000 Electrical and Lighting $ 590,000 General Requirements [15% ] $ 274,000 Contingency [ 25% ] $ 461,000 Design, Engineering, Survey [15%] $ 276,000 Alternates College Intersection - brick $ 70,000 East Side Curb Work $ 31,000 Expand east sidewalk to 6’ $ 30,000 Bioretention Areas $ 192,000 $ 1,844,000 $ 2,855,000 Site Preparation $ 127,500 Utilities General $ 28,000 Storm Sewer $ 15,000 Fiber Duct $ 12,000 Water Main $ 57,500 Paving $ 151,000 Landscape $ 77,500 Site Furnishings $ 31,000 Electrical and Lighting $ 101,500 General Requirements [15% ] $ 90,000 Contingency [ 25% ] $ 150,000 Design, Engineering, Survey [15%] $ 90,000 Alternates Monument Lights $ 40,000 Unit Pavers $ 105,000 $ 601,000 $ 932,000 IOWA CITY DOWNTOWN AND PEDESTRIAN MALL STREETSCAPE PLAN UPDATE . DRAFT P | 160 IMPLEMENTATION | PROJECT AREA COST SUMMARY DUBUQUE STREET [ 1.5 blocks ] Festive Lighting Gateway Elements Landscape Enhancements Street Pavers Sidewalk Pavers See page 80 for more detail. GILBERT STREET [ 3 blocks ] Water Main Upgrade New Sidewalk Landscape Enhancements Traffic Signals Pedestrian Lighting & Banners See page 92 for more detail. Site Preparation $ 189,000 Utilities General $ 60,000 Water $ 18,000 Storm Sewer $ 25,000 Fiber Duct $ 15,000 Paving $ 207,000 Landscape $ 86,500 Site Furnishings $ 122,000 Electrical and Lighting $ 158,000 General Requirements [ 15% ] $ 132,000 Contingency [ 25% ] $ 220,000 Design, Engineering, Survey [ 15% ] $ 132,000 Alternate Bioretention Areas $ 144,000 Unit Pavers in Street $ 510,000 Festive Lighting $ 400,000 $ 880,500 $ 1,364,500 Site Preparation $ 275,000 Utilities General $ 84,000 Water Main $ 211,000 Sanitary $ 5,000 Traffic Signals $ 875,000 Fiber Duct Bank $ 36,000 Paving $ 84,500 Landscape $ 28,000 Site Furnishings $ 25,000 Electrical and Lighting $ 292,000 General Requirements [ 15% ] $ 287,000 Contingency [ 25% ] $ 479,000 Design, Engineering, Survey [ 15% ] $ 287,000 Alternate Bury Overhead Utility $ 425,000 $ 1,915,000 $ 2,968,000 FEBRUARY 2014 161 IMPLEMENTATION | PROJECT AREA COST SUMMARY IOWA AT GILBERT [ 1 Intersection ] Enhanced Pedestrian Crossing New Civic Monument Traffic Signals Update See page 94 for more detail. Site Preparation $ 56,000 Utilities General $ 28,000 Fiber Duct $ 3,500 Paving $ 128,500 Landscape $ 7,000 Site Furnishings $ 10,000 Electrical and Lighting $ 10,000 Monument / Obelisk $ 175,000 General Requirements [ 15% ] $ 62,500 Contingency [ 25% ] $ 104,500 Design, Engineering, Survey [ 15% ] $ 63,000 Alternate Bioretention $ 25,000 $ 418,000 $ 648,000 IOWA AVENUE [ 3 blocks ] Monument Lights Enhanced Landscape + Irrigation Enhance Literary Walk Traffic Signals See page 82 for more detail. Site Preparation $ 140,000 Utilities General $ 90,000 Fiber Duct $ 31,000 Paving $ 43,000 Landscape + Irrigation $ 195,000 Site Furnishings $ 13,000 Sheltered Bike Parking with PV $ 30,000 Electrical and Lighting $ 216,000 General Requirements [ 15% ] $ 114,500 Contingency [ 25% ] $ 190,000 Design, Engineering, Survey [ 15% ] $ 114,500 Alternate Monument Lighting with banners $ 315,000 $ 760,000 $ 1,179,000 IOWA CITY DOWNTOWN AND PEDESTRIAN MALL STREETSCAPE PLAN UPDATE . DRAFT P | 162 LINN STREET [ 3 blocks ] Paver Sidewalks Enhanced Landscape + Irrigation Site Furniture Water Main Update See page 86 for more detail. WASHINGTON STREET [ 4 blocks ] Gateway Elements Enhanced Paving New Sidewalks Water Main Upgrade Pedestrian Lighting See page 78 for more detail. Site Preparation $ 104,000 Utilities General $ 85,000 Water Main $ 110,000 Storm Sewer $ 30,000 Sanitary $ 8,000 Fiber Duct $ 31,000 Paving $ 360,000 Landscape $ 82,000 Site Furnishings $ 120,000 Electrical and Lighting $ 320,000 General Requirements [15% ] $ 187,000 Contingency [ 25% ] $ 311,000 Design, Engineering, Survey [15%] $ 187,000 Alternate Pavers at Intersection $ 190,000 $ 1,250,000 $ 1,935,000 Site Preparation $ 489,000 Utilities General $ 115,000 Utility Vaults $ 150,000 Water Main $ 240,000 Storm Water $ 57,000 Fiber Duct $ 45,000 Traffic Signals $ 72,000 Paving $ 1,155,000 Landscape $ 180,000 Site Furnishings $ 196,000 Electrical and Lighting $ 711,000 General Requirements [15% ] $ 511,000 Contingency [ 25% ] $ 850,000 Design, Engineering, Survey [15%] $ 511,000 Alternates Permeable Street Paving $ 700,000 Bioretention Planting Area $ 375,000 Dubuque Intersection - Unit Pavers $ 64,000 $ 3,410,000 $ 5,282,000 IMPLEMENTATION | PROJECT AREA COST SUMMARY FEBRUARY 2014 163 IMPLEMENTATION | FUNDING SOURCES FUNDING SOURCES While the majority of project funding is anticipated to come from the Capital Improvements Program [ CIP ] as appropriated by City leadership, additional resources may be necessary to realize specific plan components such as programmed spaces within the Pedestrian Mall, architec- tural lighting for private businesses and public art. Tradi- tional sources for additional funding may come from two primary sources: GRANTS A number of grant opportunities exist for urban projects that encompass the arts, sustainability and infrastructure. Because many grants require a significant lead time to se- cure funding, this master plan update will serve as a valu- able guide to identifying future phasing with enough lead time to pursue relevant grants or loans. Although not all inclusive, information on environmental, infrastructure and transportation grants in Iowa is presented on the following pages. PRIVATE FUNDRAISING The potential for private fundraising in Iowa City is signifi- cant. The first step in this process is the formation of a di- verse private stakeholder group that can work in partner- ship with the City. Given there are multiple improvements proposed that affect areas offering a high level of visibili- ty, sentimental attachment or historical significance – the formation of a private stakeholder group is a reasonable approach to add detail and richness in public space that may otherwise be delayed or overlooked. STATE REVOLVING LOAN FUND [ SRF ] The State Revolving Fund program is administered by the Iowa Department of Natural Resources and provides low interest loans for projects that provide water quality ben- efits. There are several funding programs under the SRF umbrella that would be appropriate for the Iowa City Streetscape project. There was money added to the SRF program under the Federal Stimulus program for 2014 and the City is already involved with the development of their new wastewater treatment facility. The State Revolving Fund and the Sponsored Project option may be a great source of funding since Iowa City is upgrading the waste water / sanitary sewer system and would utilize an SRF loan for such upgrades. Money that would be sent back to the SRF as interest payments can be kept and invested locally in stormwater projects that improve water quality. Typical- ly, you would be able to plan on $100,000 for water quality per $1 million borrowed. For more information: www.iowasrf.com. CLEAN WATER LOAN PROGRAM Iowa’s Clean Water State Revolving Fund [ CWSRF ] is the best choice to finance publicly owned wastewater treat- ment, sewer rehabilitation, replacement, and construc- tion, and storm water quality improvements. The Clean Water SRF Water Resource Restoration Sponsored Project program funds are still available. As part of an application for a wastewater infrastructure Intended Use Plan appli- cation, a municipality can request up to 10% additional funds under the Sponsored Project program to pay for oth- er projects that will improve the watershed in which the wastewater plant is located. It appears that projects that are already included in the IUP but are only in the planning stages may also be eligible. I have attached a copy of the Sponsored project application. Applications for the Clean Water Loan Program and the Sponsored are due March 3. PLANNING AND DESIGN LOANS SRF Planning and Design Loans cover costs incurred in the planning and design phase of a water infrastructure proj- ect. These loans have 0 percent interest for up to three years and require no initiation or servicing fees. In addition, there is no minimum or maximum loan amount. Eligible costs include engineering fees, archaeological surveys, environmental or geological studies, and costs related to project plan preparation. The loans may be rolled into a State Revolving Fund [ SRF ] construction loan or can be repaid when permanent financing is committed. The proj- ect planning and design costs must be directly related to the proposed wastewater, storm water or drinking water projects. The 2014 deadline for Planning and Design Loan applications is April 3rd. For more information on the SRF Program: Patti Cale-Finnegan DNR State Revolving Fund Coordinator P 515-725-0498 WIRB GRANT PROGRAM The Watershed Improvement Fund Program was initiated in 2005 by the Iowa Legislature and is administered through the Iowa Department of Agriculture’s Land Stewardship program. The funds are administered by a self-govern- ing, independent Watershed Improvement Review Board [ WIRB ]. The WIRB Board focuses on watershed projects and the streetscape project, due to its direct influence on Ralston Creek, would likely qualify as an appropriate proj- ect. The current funding limit is $300,000. Tying the streets- cape improvements into a Ralston Creek watershed scale initiative would be the strongest approach to funding thru WIRB. 2014 WIRB grant applications are due by February 28th. Program Contact: Amy Bouska Urban Conservationist / IDALS amy.bouska@ia.nacdnet.net IOWA CITY DOWNTOWN AND PEDESTRIAN MALL STREETSCAPE PLAN UPDATE . DRAFT P | 164 IMPLEMENTATION | FUNDING SOURCES USEPA SECTION 319 NON-POINT SOURCE WATER POLLUTION CONTROL GRANT PROGRAM Section 319 grants have long been a source of support for cutting-edge green infrastructure projects in many states throughout the US. In Iowa the program has been admin-istered historically by the IDNR, and the focus has always been on rural, agricultural water quality initiatives of a rather traditional NRCS manner. The program is still func-tional under the IDNR Watershed Implementation Grant Program. Again this program has not been traditionally a source of funding for urban green infrastructure initiatives, but it may still be worth exploring. Applications are gener-ally due in October with funds available the following cal-endar year. More information about the program can be obtained through the program coordinator listed below. DNR Contact: Steve Hopkins DNR Watershed Improvement Program Grants Coordinator 515-281-6402 Stephen.Hopkins@dnr.iowa.gov TRANSPORTATION ALTERNATIVES PROGRAM [ TAP ] Funding may be available under the U.S. Department of Transportation, Federal Highway Administration Transpor-tation Alternatives Program (TAP). The Transportation Al-ternatives Program (TAP) was authorized under Section 1122 of Moving Ahead for Progress in the 21st Century Act (MAP-21). TAP provides funding for programs and projects defined as transportation alternatives, including on- and off-road pedestrian and bicycle facilities, infrastructure projects for improving non-driver access to public trans-portation and enhanced mobility, landscape and sce-nic enhancement, community improvement activities, and environmental mitigation; recreational trail program projects; safe routes to school projects; and projects for planning, designing, or constructing boulevards and oth-er roadways largely in the right-of-way of former Interstate System routes or other divided highways. For more information: http://www.iowadot.gov/systems_planning/trans_enhance.htm IOWA CLEAN AIR ATTAINMENT PROGRAM (ICAAP) This program funds highway/street, transit, bicycle/pedes-trian, or freight projects or programs which help maintain Iowa’s clean air quality by reducing transportation-related emissions. Eligible highway/street projects must be on the federal-aid system, which includes all federal functional class routes except local and rural minor collectors. For more information: http://www.iowadot.gov/systems_planning/icaap.htm SURFACE TRANSPORTATION PROGRAM (STP) The Surface Transportation Program (STP) is one of the main sources of flexible funding available for transit or highway purposes. STP provides the greatest flexibility in the use of funds. These funds may be used for public transportation capital improvements, car and vanpool projects, fringe and corridor parking facilities, bicycle and pedestrian facilities, and intercity or intracity bus terminals and bus facilities. As funding for planning, these funds can be used for surface transportation planning activities, wet- land mitigation, transit research and development, and environmental analysis. Other eligible projects under STP include transit safety improvements and most transporta- tion control measures. For more information: http://www.fhwa.dot.gov/map21/ guidance/guidestp.cfm