HomeMy WebLinkAboutWashington Street Phasing(030116)2016 Washington Street Streetscape Project Construction Phasing – Overall 2016 Washington Street Streetscape Project Construction Phasing – Phase 1A Phase 1A Phase 1A . Utilities and Street Paving April 11 . Early Start Date 2016 Washington Street Streetscape Project Construction Phasing – Phase 1B Phase 1B . Clinton St. Intersection May 2 . Early Start Date June 30 – July 6 . Fully functional for vehicle and pedestrian traffic One northbound lane and one southbound lane will remain open on Clinton St. at all times Three crosswalks to remain open at all times Phase 1A Ongoing 2016 Washington Street Streetscape Project Construction Phasing – Phase 1C Phase 1C Phase 1C . Dubuque St. Intersection April 11 . Early Start Date June 2 – June 5 & June 30 – July 6 . Fully functional for vehicle and pedestrian traffic Clinton St. intersection to be open and operational when Dubuque St. lane closures are in effect At least one lane of one-way will remain open at all times Two crosswalks to remain open at all times Phase 1A Ongoing 2016 Washington Street Streetscape Project Construction Phasing – Phase 1D Phase 1D Phase 1D . Jefferson Vault and Pedestrian Mall April 4 . Early Start Date Pedestrian Mall Section and Washington Street section will not be done at the same time. East-West Pedestrian Access to be Maintained on Washington Street Phase 1A Ongoing 2016 Washington Street Streetscape Project Construction Phasing – Phase 1E Phase 1E . Sidewalk Phase 1A Complete. Early Start Date East – West pedestrian access on both sides of Washington St. to be maintained at all times. 2016 Washington Street Streetscape Project Construction Phasing – Phase 2A Phase 2A . Utilities and Street Paving Phase 1 Complete . Early Start Date Phase 2A 2016 Washington Street Streetscape Project Construction Phasing – Phase 2B and 2C Phase 2B . South Side Sidewalk 2A Complete . Early Start Date East – West pedestrian access on both sides of Washington St. to be maintained at all times Phase 2C . North Side Sidewalk 2B Complete . Early Start Date East – West pedestrian access on both sides of Washington St. to be maintained at all times. Phase 2B Phase 2C 2016 Washington Street Streetscape Project Construction Phasing – Phase 2D Phase 2D . Linn Street Phase 2C Complete . Early Start Date At least one lane of one-way will remain open at all times Three crosswalks to remain open at all times Phase 2D