HomeMy WebLinkAboutJanuary 21, 2014 presentation to CouncilCity Council Work Session
January 21, 2014
Tonight’s Objective:
Establish the Primary Design Parameters for the Project
•Work Session
Review City Council Process to Date
Review Recent Activities for NEPA Process
Review the Process as we Move Forward with Design
Review Staff Recommendations
Outline the Resolution and Options
Answer Additional Questions from Council
•Formal Meeting
Outline Staff Recommendations
Public Input
Consider Resolution Establishing Primary Design Parameters
September 17, 2013 Work Session
•Reviewed the project and Environmental Assessment Process
•Identified three primary design parameters that will need to be decided to move into the design phase
•Answered Questions
October 1, 2013
•Work Session: Reviewed the three primary design parameters and staff’s recommendations. Answered questions.
•Formal Meeting: Held Public Hearing for input on the project. No action item on the agenda.
January 21, 2014
•Work Session: Review the process, parameters and recommendations. Answer questions.
•Formal Meeting: Additional public input. Consider resolution establishing the three primary design parameters.
Led by Office of State Archaeologist and Tallgrass Historians
Coordinated with:
•Iowa City Historic Preservation Commission
•Iowa DOT Cultural Resource staff
•State Historic Preservation Officer
Received finding of Conditional No Effect summer 2012
Affirmed by independent evaluation summer 2013
Iowa City Historic Preservation Commission confirmed support, fall 2013
Received FHWA Finding of No Significant Impact December 2013
Started April 2010
Two public meetings: 250+ attendees
Drop-in center + online public meeting
Public hearing/drop-in center
Multiple paid ads
Multiple media stories
Local media press releases
City and project specific Web site*
Mailing list of nearly 2,000*
Neighborhood and civic group meetings*
Multiple one-on-one meetings and calls*
*Will continue in the design process
Completed:
Data collection
Flood model data updated
Initial alternatives screening
Purpose and Need approved
Two public meetings
Refine alternatives
Screen alternatives
Recommend preferred alternative
Prepare NEPA document
Resource Agency coordination
Release NEPA document for
review
Hosted Public Hearing
Received Federal approval
Level of protection for Dubuque Street
•2008 event + 1’
Backwater reduction goals (Elevation of Park Road
Bridge):
•Low Steel at 200 year event +1’
Structural type of the bridge
•Deck Girder or Through Arch
Level of Protection Estimated # of days closed
in the past 20 years due to
Iowa River flooding
Relative Comparison: Inches
above/below the 2008 + 1’
protection level
Existing 150 NA
100 year + 1’ 7* -39”
200 year + 1’ 5* -11”
2008 flood + 1’ (Recommended) 0 0”
500 year + 1’ (EA Preferred Alt) 0 +19”
*Including one day for cleanup, inspection and repair after inundation
Bridge Type Low Steel
Elevation
Backwater
Reduction
at Idyllwild
Incremental
Improvement
in Backwater
Reduction
Deck
Elevation
Incremental
Height of
Bridge Deck
Constructi
on Cost
Estimate
with
Dubuque
at
100yr + 1’
Constructi
on Cost
Estimate
with
Dubuque
at
200yr + 1’
Construction
Cost
Estimate
with
Dubuque at
2008 + 1’
Construction
Cost
Estimate
with
Dubuque at
500yr + 1’
Deck Girder 100yr + 1’ 3.4” 660.20 $32.67 M $34.26 M
Deck Girder 200yr + 1’ 6.1” 2.7” 662.52 27.8” $34.63 M $35.01 M
Deck Girder 2008 + 1’ 6.6” 0.5” 663.45 11.2” $33.41 $35.17 M
Deck Girder 500yr + 1’ 7.0” 0.4” 665.03 19.0” $34.20 M $35.01 M $35.34 M $36.65 M
EA Preferred
Alternative
Deck Arch 100yr + 1’ 3.6” 659.20 $36.01 M $37.59 M
Deck Arch 200yr + 1’ 4.7” 1.1” 661.52 27.8” $37.96 M $38.34 M
Deck Arch 2008 + 1’ 5.2” 0.5” 662.45 11.1” $36.71 M $38.48 M
Deck Arch 500yr + 1’ 5.6” 0.4” 664.03 19.0” $36.94 M $38.33 M $38.66 M $39.98 M
Through
Arch
100yr + 1’ 3.4” 656.87 $35.99 M $37.58 M
Through
Arch
200yr + 1’ 4.9” 1.5” 659.02 25.8” $37.93 M $38.31 M
Through
Arch
2008 + 1’ 5.2” 0.3” 659.95 11.1” $36.70 M $38.47 M
Through
Arch
500yr + 1’ 5.8” 0.6” 661.53 19.0” $36.90 M $38.30 M $38.63 M $39.60 M
Option Bridge Type Low Steel
Elevation
Elevation at
the Dubuque
St/Park Rd
Intersection
Backwater
reduction at
Idyllwild and
Taft
Speedway
Dubuque
Street
Protection
Level
Construction
Cost Estimate
of Bridge and
Road
Max. protection
and backwater
reduction
(EA Preferred Alt)
Deck Girder 500yr + 1’ 665.03 7” 500yr + 1’ $36.65M
Recommended
Arch
Through Arch 200yr + 1’ 659.02 4.9” 2008 + 1’ $38.31M
Recommended
Girder
Deck Girder 200yr + 1’ 662.52 6.1” 2008 + 1’ $35.01M
Questions?
Bridge Type Low Steel
Elevation
Backwater
Reduction
at Idyllwild
Incremental
Improvement
in Backwater
Reduction
Deck
Elevation
Incremental
Height of
Bridge Deck
Constructi
on Cost
Estimate
with
Dubuque
at
100yr + 1’
Constructi
on Cost
Estimate
with
Dubuque
at
200yr + 1’
Construction
Cost
Estimate
with
Dubuque at
2008 + 1’
Construction
Cost
Estimate
with
Dubuque at
500yr + 1’
Deck Girder 100yr + 1’ 3.4” 660.20 $32.67 M $34.26 M
Deck Girder 200yr + 1’ 6.1” 2.7” 662.52 27.8” $34.63 M $35.01 M
Deck Girder 2008 + 1’ 6.6” 0.5” 663.45 11.2” $33.41 $35.17 M
Deck Girder 500yr + 1’ 7.0” 0.4” 665.03 19.0” $34.20 M $35.01 M $35.34 M $36.65 M
EA Preferred
Alternative
Deck Arch 100yr + 1’ 3.6” 659.20 $36.01 M $37.59 M
Deck Arch 200yr + 1’ 4.7” 1.1” 661.52 27.8” $37.96 M $38.34 M
Deck Arch 2008 + 1’ 5.2” 0.5” 662.45 11.1” $36.71 M $38.48 M
Deck Arch 500yr + 1’ 5.6” 0.4” 664.03 19.0” $36.94 M $38.33 M $38.66 M $39.98 M
Through
Arch
100yr + 1’ 3.4” 656.87 $35.99 M $37.58 M
Through
Arch
200yr + 1’ 4.9” 1.5” 659.02 25.8” $37.93 M $38.31 M
Through
Arch
2008 + 1’ 5.2” 0.3” 659.95 11.1” $36.70 M $38.47 M
Through
Arch
500yr + 1’ 5.8” 0.6” 661.53 19.0” $36.90 M $38.30 M $38.63 M $39.60 M