HomeMy WebLinkAbout2020 American Legion Road Fact SheetPUBLIC INFORMATION MEETING
AMERICAN LEGION ROAD IMPROVEMENTS
SCOTT BOULEVARD TO TAFT AVENUE
PROJECT OVERVIEW
Iowa City is planning to reconstruct American Legion Road from Scott
Boulevard to Taft Avenue. Planned improvements include:
• New pavement with curb and gutter
• Roundabout at Scott Boulevard
• On-street bike lanes
• Pedestrian facilities
• Underground utilities
The new roadway corridor will have one travel lane in each direction, on-street
bikes lanes on both sides of the roadway, a shared-use path, sidewalks, and a
pedestrian underpass near Hoover Elementary School.
The project will also support the projected growth within the southeast quadrant
of the City by upgrading the roadway infrastructure to current arterial design
standards.
PROJECT WEBSITE
https://www.icgov.org/project/american-legion-road-improvements-project
CONTACT INFORMATION
For project questions, please contact the project team.
Scott Sovers, P.E., Assistant City Engineer
City of Iowa City – Engineering Division
319-356-5142
scott-sovers@iowa-city.org
Aaron Moniza, P.E., Project Manager
Foth Infrastructure and Environment, LLC
319-297-2073
aaron.moniza@foth.com
PROJECT SCHEDULE
The following is the
anticipated schedule for the
project
FIELD SURVEYS
Spring / Summer 2019
PRELIMINARY DESIGN
January - June 2019
FINAL DESIGN
June 2019 - February 2020
RIGHT-OF-WAY
ACQUISTION
Winter / Spring 2020
UTILITY RELOCATIONS
Winter / Spring 2020
PROJECT LETTING
May 19, 2020
PROJECT CONSTRUCTION
Summer 2020 - 2021
PROJECT
DETAILS
Right-of-way will need to be acquired
for project and Iowa City has started
that process.
Segments of American Legion Road
will be closed during construction
but access will be maintained.
• 10’ Travel Lanes
• 7’ Bike Lanes (includes buffer)
• 10’ Shared Use Path
• 5’ Sidewalk
• Intersection Treatments
• Pedestrian Underpass
• Drainage Box Culvert
• Storm Sewer
• Sanitary Sewer
• Water Main
• Lighting (only at roundabout