HomeMy WebLinkAboutParking Garage RFP 2020-2023 Final Request for Proposals (RFP) Engineering Services for the City of Iowa City Parking Garage Structures (January 19, 2021 and June 30, 2023) November 20, 2020 RFP – Parking Garage Eng. Services 2 City of Iowa City SUMMARY The City of Iowa City, Iowa (City) is soliciting proposals from interested consulting firms, licensed in the State of Iowa, to provide professional engineering services for the six parking garage structures owned and operated by the City of Iowa City. The selected firm (Consultant), will assist the City in engineering services between January 19, 2021 and June 30, 2023 with a potential extension. CONTENTS Summary ......................................................................................................................................... 2 Submittal Instructions and Deadline ............................................................................................... 3 Timeline for RFP Process ............................................................................................................... 3 Minimum Qualifications ................................................................................................................. 3 Costs for Developing the RFP ........................................................................................................ 3 Consultant Selection Process .......................................................................................................... 4 Submittal Contents .......................................................................................................................... 4 Contract Documents........................................................................................................................ 6 Reservations .................................................................................................................................... 6 Inquires ........................................................................................................................................... 6 Project Background ......................................................................................................................... 6 Capitol Street Ramp .................................................................................................................... 7 Dubuque Street Ramp ................................................................................................................. 7 Tower Place Ramp ...................................................................................................................... 8 Chauncey Swan Ramp ................................................................................................................ 9 Court Street Transportation Center ........................................................................................... 10 Harrison Street Ramp ................................................................................................................ 10 Scope of Services .......................................................................................................................... 11 Schedule for Completion of Services ........................................................................................... 12 Appendix A – Master Plan .............................................................................................................. 1 Appendix B – Consultant Agreement ............................................................................................. 1 Appendix C – City of Iowa City Wage Theft Policy ...................................................................... 1 RFP – Parking Garage Eng. Services 3 City of Iowa City SUBMITTAL INSTRUCTIONS AND DEADLINE Submittals may be mailed or submitted electronically. If the submittal is mailed, it should be sent to: City Clerk City of Iowa City City Hall 410 East Washington Street Iowa City, Iowa 52245 Mailed submittals must be received by the City Clerk’s office before 4:00 p.m. (CST) on Wednesday, December 23, 2020. Mailed submittals should include three (3) hard copies of the submittal and a USB thumb drive, CD or DVD containing one electronic (PDF) copy of the submittal. Mailed submittals must be sealed and clearly marked as: “Engineering Services for the City of Iowa City Parking Garage Structures (January 19, 2021 and June 30, 2023).” If the submittal is delivered electronically, it should be delivered to the City’s website at www.icgov.org/parkingRFP. Submittals delivered electronically must be complete and uploaded to the website in their entirety before 4:00 p.m. (CST) on Wednesday, December 23, 2020. Submittals delivered electronically should include one (1) electronic (PDF) copy of the submittal. No hard copies will be required if submitted electronically. Faxed submittals will not be accepted. Late submittals will not be evaluated. The City may reject any or all submittals in its sole discretion. TIMELINE FOR RFP PROCESS Tentative consultant selection timeline is as follows: ▪ Submittals are due 4:00 PM CST, Wednesday December 23, 2020 ▪ All inquiries must be made no later than December 11, 2020 ▪ Selection of consultant will occur on approximately January 4, 2021 ▪ Consultant agreements will be finalized approximately by January 19, 2021 MINIMUM QUALIFICATIONS To be considered, consultants must document the knowledge, skills, and abilities of the firm and team members proposed for this project. COSTS FOR DEVELOPING THE RFP Firms participating in the consultant selection process will be responsible for all costs incurred to respond to this RFP. RFP – Parking Garage Eng. Services 4 City of Iowa City CONSULTANT SELECTION PROCESS The Selection Committee consists of several members of the Engineering Division, Transportation Services, and other departments or divisions as needed. Submittals will be reviewed based on the submittal contents described below and evaluated based on the following criteria: consultant qualifications and experience, project approach, consultant fees and project costs, and project scheduling. The firm deemed best qualified by the Selection Committee will be selected for negotiations related to final project scope and fee. Should the City and Consultant not be able to reach an agreement regarding project scope and fee, the City reserves the right to negotiate with the firm determined by the City to be the next most qualified. The intent of the selection process is to select the most qualified firm based on the identified needs of the City. The skills, areas of expertise, and capabilities that the City believes are necessary for successful completion of the project work will be evaluated and factored in the selection process. In all cases, the City reserves the right to select a consultant firm and award a contract that is in the best interests of the City. Interviews may be conducted as part of the selection process. SUBMITTAL CONTENTS To standardize responses and simplify the comparison and evaluation of responses, all statements must be organized in the manner set forth below, separated into sections, and appropriately labeled. However, specific requirements for each section have been minimized in order to allow for flexibility for each firm to provide information they feel best conveys their qualifications. All information and materials requested shall be provided in the response under a single cover. The submittal length shall be limited to a maximum of 20 single-sided (or 10 double-sided) pages, not including dividers and covers. The cover letter attached to the response counts towards the page limit. Minimum font size shall be ten (10) point. Interested Consultants shall submit proposals to make sure a proper evaluation of the firm’s capabilities. Three hard copies and an electronic copy of the response are requested. The Proposals shall contain the following response items arranged in order in the manner specified below. Cover Letter – The letter should state the firm’s interest in being considered for selection as well as pertinent information for the firm’s contact person. General Firm Profile – A general description of the firm is required. Describe the general nature of services provided by the firm, the location of main and branch offices, and the number of years the firm has provided services similar to those anticipated on the project included in the RFP. Any sub-consultants who are expected to be a part of the design team should be identified. Key Personnel – Provide information indicating anticipated key personnel, relationship to the desired project, and their positions within the firm. Include in the descriptions past experience with the City, technical abilities, and identified project responsibilities. It is a requirement of the City that the key personnel identified during the consultant selection process will participate in and execute the project. Substitution of key personnel after selection will require approval by the RFP – Parking Garage Eng. Services 5 City of Iowa City City as project lead professionals are considered essential. Please indicate the persons possessing the licenses and certifications necessary to perform the type of work being requested. Reference Projects – A listing of reference projects shall be provided. Reference projects should be of similar size and scope as those for which the consultant would like to be considered. Particular emphasis should be placed on innovative, sustainable, and cost-effective solutions. Indicate which key personnel were involved in the reference projects and their role in the reference projects. Provide contact information for the project owners, the nature of the firm’s scope of work on the project, and the date the contract started and ended. The Project Team should demonstrate current experience in working with federal, state, and local agencies involved in the operations and compliance at the Facility. Project Approach (Each Fiscal Year) – A description of the anticipated project approach, including technical and management factors that will lead to a quality project. Respondents are encouraged to use this section of the submittal to address unique understanding, knowledge and/or abilities of the firm as they apply to the project included in this RFP. Competitive advantages or special capabilities of project teams should be highlighted in this section. This section should describe the firm’s understanding of the maintenance and upkeep of the City’s Parking Garages including, but not limited to, their structure; operations and maintenance; environmental compliance and permitting; and future operations and compliance issues. The proposed maintenance and repair activities for the six garages is described in the City of Iowa City Parking Garages, Condition Review and Proposed Repair and Maintenance Master Plan, THP Limited, Inc., June 19, 2020 (Master Plan). The Master Plan is included in Appendix A. This section should describe how the activities within the Master Plan will be implemented across the different locations, years, and types of work (electrical, mechanical, structural, waterproofing, etc.). Of particular concern is how the project approach will organize the design packages to meet the budget included in the Master Plan, while minimizing the disruptions to regular operations and usage of the garages. The response should identify the basis for the specifications. Possibilities include American Institute of Architects (AIA), Engineers Joint Contract Documents Committee (EJCDC), and Statewide Urban Design and Specifications (SUDAS). This section will describe the project management approach as well as provisions that will be utilized to accommodate working during the Coronavirus Pandemic (COVID-19). Estimate of Resources (Each Fiscal Year) – Based on the firm’s understanding of the scope of work required, provide an estimate of the firm’s resources that should be dedicated to the project. This can be in a form of the firm’s choosing but should clearly convey a sense of the amount of effort, resources and an estimated price the firm believes will be required for the project. The estimated price does not need to be a quote to complete the project, and may include an estimated cost range, but should accurately reflect the anticipated effort to complete the project. A detailed breakdown by task, as included in the Scope of Service Section, would be beneficial. Project Schedule (Each Fiscal Year) – Provide a preliminary project schedule that includes projected durations for anticipated project phases, including project milestones and deliverables. A detailed breakdown by task, as included in the Scope of Services and Schedule for Completion of Service Sections, would be beneficial. RFP – Parking Garage Eng. Services 6 City of Iowa City Billing Rates – Provide current billing rates for firm personnel, including rates of staff included in the proposal, at a minimum. CONTRACT DOCUMENTS The City anticipates entering into a contract for professional services with the selected firm for three fiscal years, Fiscal Years 2021 through 2023 (the period from January 19, 2021 to June 30, 2023). Consultants selected to provide services will be required to enter into a written consultant agreement with the City of Iowa City. A sample consultant agreement is included in Appendix A of this RFP. Any objections to agreement language shall be documented in the submitted proposal. In addition, selected consultants will be required to submit a completed copy of the City of Iowa City Wage Theft Policy, included in Appendix B of this RFP. Any objections to agreement language shall be documented in the submitted proposal. RESERVATIONS The City reserves the right to reject any and all submittals; waive formalities, technical requirements and/or deficiencies; or to solicit for new or additional proposals it deemed to be in the best interests of the City. In addition, the City reserves the right to further negotiat e with one or more firms of its choice, if such negotiations better serve the City’s interest. The City reserves the right to negotiate a contract that covers all or selected parts of the proposal, key project team members and sub-consultants. INQUIRES Inquiries to clarify the requirements of this RFP can be directed to Joe Welter at (319) 356-5144 or emailed to joe-welter@iowa-city.org. All inquiries must be made no later than December 11, 2020. Specific project scope and fees will be negotiated at a later time. PROJECT BACKGROUND The City owns and operates six parking garages. The recommended maintenance and repair activities for these locations are described within the Five-Year Master Plan for Calendar Years 2020 – 2024. The locations and their associated activities for the five years is summarized below. Locations of the six (6) parking garages: No. Garage Address 1 Capitol Street Ramp 220 South Capitol Street, Iowa City, Iowa 52240 2 Dubuque Street Ramp 220 South Dubuque Street, Iowa City, Iowa 52240 3 Chauncey Swan Ramp 415 East Washington Street, Iowa City, Iowa 52240 4 Tower Place Ramp 335 Iowa Avenue, Iowa City, Iowa 52240 5 Court Street Transportation Center 150 East Court Street, Iowa City, Iowa 52240 6 Harrison Street Ramp 175 East Harrison Street, Iowa City, Iowa 52240 RFP – Parking Garage Eng. Services 7 City of Iowa City Capitol Street Ramp The Capitol Street Ramp has approximately 875 parking spaces and in excess of 280,000 square feet of supported floor structure. This structure has six levels with five being supported. Each level consists of three adjacent bays with two bays that act as ramps between adjacent floor levels. The planned efforts for this ramp are as follows: Capitol Street Ramp Summary Year Structural/Waterproofing Mechanical, Electrical, and Plumbing (MEP) 2020 New sealant, traffic membrane strip installations Repair stair tower ventilation and replace stand pipe cap, complete IR scan and maintenance of electrical equipment. 2021 Expansion joint repairs and replacement, Interior level sealant replacement, concrete soffit repairs, Isolated stair towers repairs and waterproofing No efforts planned 2022 Concrete floor repairs and traffic membrane recoating, interior level sealant replacement, concrete soffit repairs, isolated stair towers repairs and waterproofing No efforts planned 2023 No efforts planned Replace top deck lighting and poles, replace common area lighting fixtures 2024 Interior level sealant replacement No efforts planned Dubuque Street Ramp The Dubuque Street Ramp has approximately 625 parking spaces, and in excess of 200,000 square feet of supported floor structure. This ramp is a double helix with two adjacent bays sloped in opposing directions with crossover at the common intersection. The planned efforts for this ramp are as follows: RFP – Parking Garage Eng. Services 8 City of Iowa City Dubuque Street Ramp Summary Year Structural/Waterproofing Mechanical, Electrical, and Plumbing (MEP) 2020 Concrete floor repairs and membrane patching, concrete soffit repairs, expansion joint repairs, stair tower roof replacements Repair stair tower ventilation, install CO/NOx control and repair ductwork, electrical room ventilation, complete IR scan 2021 Traffic membrane recoating at crossovers, new sealants at roof level topping slab, north facade joint sealant replacements, stair towers repairs and water proofing No efforts planned 2022 Concrete floor repairs and traffic membrane recoating, interior level sealant replacement, concrete soffit repairs, isolated stair towers repairs and waterproofing No efforts planned 2023 No efforts planned Replace top deck lighting and poles, replace common area lighting fixtures 2024 Concrete floor repairs and membrane patching No efforts planned Tower Place Ramp The Tower Place Ramp has approximately 510 parking spaces and approximately 180,000 square feet of supported parking structure. This parking ramp has multiple levels of retail and businesses as well as the City Parking Office. Each level has two bays, configured in a double helix with a traffic crossover between each bay. The planned efforts for this ramp are as follows: Tower Place Ramp Summary Year Structural/Waterproofing Mechanical, Electrical, and Plumbing (MEP) 2020 Stair tower vestibule leaking and membrane at adjacent floor areas Repair stair tower ventilation, relocate boiler flue, complete IR scan and maintenance of electrical equipment RFP – Parking Garage Eng. Services 9 City of Iowa City Tower Place Ramp Summary Year Structural/Waterproofing Mechanical, Electrical, and Plumbing (MEP) 2021 Concrete floor repairs and membrane patching, expansion joint replacements and membrane strip recoating, stair tower waterproofing, handrail embedment repairs No efforts planned 2022 No efforts planned Replace chilled water pumps, replace 200MHB boiler, replace snowmelt piping, replace common area lighting fixtures 2023 Facade expansion joint and control joint, sealant replacement and miscellaneous repairs No efforts planned 2024 Facade expansion joint and control joint sealant replacement, lower level traffic membrane partial recoating No efforts planned Chauncey Swan Ramp The Chauncey Swan Ramp has approximately 475 parking space with two and one half supported levels. It has just less than 100,000 square feet of support structure. The parking ramp has two adjacent bays with one bay sloped to provide traffic between levels. The upper levels are not connected to the ground level but are all accessible by a stair tower. The planned efforts for this ramp are as follows: Chauncey Swan Ramp Summary Year Structural/Waterproofing Mechanical, Electrical, and Plumbing (MEP) 2020 No efforts planned Repair stair tower ventilation and complete IR scan and maintenance of electrical equipment 2021 Isolated garage, spandrel, and stair tower repairs No efforts planned 2022 Concrete floor repairs, epoxy injection of stem/flange cracks in precast, entrance ramp soffit and floor repairs and waterproofing No efforts planned RFP – Parking Garage Eng. Services 10 City of Iowa City 2023 No efforts planned Replace top deck lighting and poles, replace common area lighting fixtures, repair storm drain insulation 2024 Sealant replacement and membrane strip installations at exposed top level No efforts planned Court Street Transportation Center The Court Street Transportation Center has approximately 600 parking spaces with over 180,000 square feet of supported parking structure. The parking ramp has two adjacent bays with one bay sloped to provide traffic between levels. The planned efforts for this ramp are as follows: Court Street Transportation Center Summary Year Structural/Waterproofing Mechanical, Electrical, and Plumbing (MEP) 2020 Repair of deteriorated spandrel panel Repair stair tower ventilation, repair AH-2 and tenant space combustion air, complete IR scan and maintenance of electrical equipment 2021 Clean and coat miscellaneous facade elements No efforts planned 2022 Construction joint sealant replacement and membrane strips, isolated stair tower repairs and water proofing, clean and coat miscellaneous facade elements No efforts planned 2023 No efforts planned Replace top deck lighting and poles, replace common area lighting fixtures, repair storm drain insulation 2024 Clean and coat miscellaneous facade elements No efforts planned Harrison Street Ramp The Harrison Street Parking Ramp has approximately 600 parking spaces and is approximately 160,000 square feet of supported parking structure. The parking ramp has two bays, with both RFP – Parking Garage Eng. Services 11 City of Iowa City being sloped to provide continuous traffic between levels. The planned efforts for this ramp are as follows: Harrison Street Ramp Summary Year Structural/Waterproofing Mechanical, Electrical, and Plumbing (MEP) 2020 No efforts planned Clean and seal common area light fixtures, complete IR scan and maintenance of electrical equipment 2021 Route and seal floor cracks and minor, miscellaneous efforts No efforts planned 2022 Route and seal floor cracks and minor, miscellaneous efforts No efforts planned 2023 Contingency funds for annual garage maintenance No efforts planned 2024 Contingency funds for annual garage maintenance No efforts planned SCOPE OF SERVICES The selected firm (Consultant), will assist the City in engineering services for Fiscal Years 2021 through 2023 (the period from January 19, 2021 to June 30, 2023). The Consultant shall perform the following services, including but not limited to, the tasks listed below: The information provided in this section is not intended to comprise a detailed scope of services that will be required in a final consultant contract, but is intended to provide general information to firms wishing to submit proposals. The City will negotiate the detailed scope of servi ces with the successful firm for each project. Each contract for engineering and design services will be a full-service design contract that includes, but is not limited to, the following: ▪ Conduct a kick-off meeting with City Staff. ▪ Review available information provided by the City. ▪ Survey and field verify the project area (using the Iowa State Plane South Coordinate System). ▪ Survey boundary work and preparation of acquisition plats, as needed. RFP – Parking Garage Eng. Services 12 City of Iowa City ▪ Create a base map for use during design and project document development. ▪ Project team meetings (City and Consultant staff) and field visits as necessary. ▪ Provide project plans, including estimate of construction costs, for review at approximately 30%, 60%, 90% and 100% completion. ▪ Coordinate with private utility companies, as needed, for required relocations. ▪ Meet with City Staff to discuss and review comments. ▪ Individual property owner meetings and public meetings. ▪ Provide final bid documents, including a final estimate of construction costs. ▪ Bid phase services, as necessary, including but not limited to, assisting the City in responding to bidder inquiries on technical matters and preparing the appropriate clarifications and addenda. ▪ Limited construction period services. ▪ Construction period services, including but not limited to, attending construction meetings and issuing meeting notes, shop drawing review, responding to Requests for Information (RFIs), issuing Instructions to Contractors (ITCs), preparing punch lists, assisting with closeout and providing as-built record drawings based on contractor mark-ups. Following selection of a preferred consultant for each project, City staff will meet with consultant staff to negotiate final project design scope and fee. The detailed schedule for development of draft documents should be included in the response as described in Submittal Contents – Project Schedule Section of this RFP. Following selection of a preferred consultant for each project, the City will meet with the selected consultant to negotiate final project design scope and fee. SCHEDULE FOR COMPLETION OF SERVICES The Consultant will complete the deliverables for the intended project approach in a manner to meet the schedule within the Master Plan. As needed, activities within Calendar Year 2020 will be moved into Calendar Year 2021. RFP – Parking Garage Eng. Services A-1 City of Iowa City APPENDIX A – MASTER PLAN City of Iowa City Parking Garages Condition Review and Proposed Repair and Maintenance Master Plan THP #19040.00 Table of Contents Page I. Executive Summary .............................................................................................1 II. Introduction ..........................................................................................................3 III. Capitol Street Ramp Description Structural and Waterproofing .......................................................................5 MEP Systems ..............................................................................................6 Recent Repair and Maintenance Efforts ......................................................7 Review and Findings Precast and Cast-in-Place Concrete ...........................................................8 Chloride Testing of Concrete Powder Samples ...........................................9 Membrane Conditions..................................................................................9 Membrane Bond Testing ...........................................................................10 Sealants and Shear Connectors ................................................................10 Expansion Joint Conditions .......................................................................11 Stair and Elevator Towers .........................................................................11 Mechanical/Electrical/Plumbing .................................................................11 Photos........................................................................................................13 Recommendations Structural and Waterproofing .....................................................................16 Mechanical/Electrical/Plumbing .................................................................17 Repair and Maintenance Master Plan .............................................................19 IV. Dubuque Street Ramp Description Structural and Waterproofing .....................................................................23 MEP Systems ............................................................................................24 Recent Repair and Maintenance Efforts ....................................................26 Review and Findings Concrete Floor and Soffit Deterioration .....................................................27 Chloride Testing of Concrete Powder Samples .........................................27 Membrane Conditions................................................................................28 Membrane Bond Testing ...........................................................................28 Expansion Joint Conditions .......................................................................29 Sealants in the Precast Levels ..................................................................29 Façade Panels and Sealants .....................................................................29 Stair and Elevator Towers .........................................................................29 Mechanical/Electrical/Plumbing .................................................................30 Photos........................................................................................................32 Recommendations Structural and Waterproofing .....................................................................35 Mechanical/Electrical/Plumbing .................................................................36 Repair and Maintenance Master Plan .............................................................38 Table of Contents (continued) Page V. Tower Place Ramp Description Structural and Waterproofing .....................................................................42 MEP Systems ............................................................................................43 Recent Repair and Maintenance Efforts ....................................................45 Review and Findings Concrete Floor and Soffit Deterioration .....................................................46 Chloride Testing of Concrete Powder Samples .........................................46 Expansion Joints, Membrane and Sealant Conditions ..............................47 Membrane Bond Testing ...........................................................................47 Stair Towers...............................................................................................48 Handrails....................................................................................................48 Garage Façade ..........................................................................................48 Mechanical/Electrical/Plumbing .................................................................49 Photos........................................................................................................51 Recommendations Structural and Waterproofing .....................................................................54 Mechanical/Electrical/Plumbing .................................................................55 Repair and Maintenance Master Plan .............................................................57 VI. Chauncey Swan Ramp Description Structural and Waterproofing .....................................................................61 MEP Systems ............................................................................................62 Recent Repair and Maintenance Efforts ....................................................62 Review and Findings Precast Concrete Double Tees..................................................................63 Chloride Testing of Concrete Powder Samples .........................................63 Sealants and Membrane Systems .............................................................64 Connector Bridge to Street Level...............................................................64 Spandrel Panels ........................................................................................64 Stair and Elevator Towers .........................................................................64 Mechanical/Electrical/Plumbing .................................................................65 Photos........................................................................................................66 Recommendations Structural and Waterproofing .....................................................................68 Mechanical/Electrical/Plumbing .................................................................69 Repair and Maintenance Master Plan .............................................................70 Table of Contents (continued) Page VII. Court Street Transportation Center Description Structural and Waterproofing .....................................................................74 MEP Systems ............................................................................................75 Review and Findings Concrete Floor Slabs .................................................................................77 Sealants .....................................................................................................77 Garage Façade ..........................................................................................77 Stair and Elevator Towers .........................................................................77 Mechanical/Electrical/Plumbing .................................................................78 Photos........................................................................................................79 Recommendations Structural and Waterproofing .....................................................................81 Mechanical/Electrical/Plumbing .................................................................81 Repair and Maintenance Master Plan .............................................................83 VIII. Harrison Avenue Ramp Description Structural and Waterproofing .....................................................................87 MEP Systems ............................................................................................88 Review and Findings Garage Structural and Waterproofing ........................................................90 Garage Façade ..........................................................................................90 Stair and Elevator Towers .........................................................................90 Mechanical/Electrical/Plumbing .................................................................91 Photos........................................................................................................92 Recommendations Structural and Waterproofing .....................................................................94 Mechanical/Electrical/Plumbing .................................................................95 Repair and Maintenance Master Plan .............................................................96 APPENDICES Appendix A – Parking Facility Chloride Testing Data Appendix B – Parking Facility Membrane Bond Testing Data Appendix C – Discussion of Typical Parking Garage Issues I. Salt-Induced Corrosion in Reinforced Parking Decks..................................1 II. Slab Tendons in Post-Tensioned Concrete Structures................................5 III. Lateral Stability and Movement in Parking Garages....................................6 Appendix D – NFPA Recommended Systems Testing Frequencies City of Iowa City Parking Garages 1 of 99 Executive Summary Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 I. EXECUTIVE SUMMARY The City of Iowa City parking facilities range significantly in their recommended maintenance of structural, waterproofing, and mechanical/electrical/plumbing (MEP) items. The two oldest structures (Capitol Street and Dubuque Street Ramps) require the most significant structural and waterproofing needs over the next 5 years, with a focus on concrete floor repairs and traffic membrane patching in the post-tensioned Dubuque Street facility, and isolated tee joint repairs and traffic membrane strip installations in the precast Capitol Street facility. Isolated recommendations for structural and waterproofing efforts exist in the other four facilities. Similarly, varying MEP efforts are recommended for all six facilities, with the most significant efforts outlined for the Tower Place Ramp, where several systems are recommended for replacement in the coming years. Comprehensive summaries and outlines of the recommended Master Plan scope of work for each facility are included at the end of their corresponding report section. The recommended scope for each facility is broken down into two categories: Structural and Waterproofing efforts, and MEP work. The six parking facilities, taken as a whole, contain over 3,600 total spaces and in excess of 1,050,000 square feet of structurally maintainable floor areas. While the unit costs of the individual structural and waterproofing repair needs are typically not high, the extension of large volume items (such as expansion joint and sealant replacements, concrete floor repairs, and traffic membrane renewal) over this great amount of floor area results in significant total costs. The total opinion of probable cost for the recommended 2020 through 2024 scope of in the six facilities is $2,300,000, including $1,565,000 in Structural and Waterproofing efforts and $735,000 in MEP efforts. Anticipated costs include varying allowances for future repairs, contingency and architectural/engineering (A/E) fees. A summary of the annual opinion of probable costs is included on the following page. City of Iowa City Parking Garages 2 of 99 Executive Summary Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 City of Iowa City Parking Garages Proposed Repair and Maintenance Master Plan, 2020-2024 Annual Summary of All Garages (Structural, Waterproofing, and MEP) Opinion of Probable Costs(1)(2) Year Parking Garage Structural/Waterproofing MEP Totals 2020 Capitol $120,000 $35,000 $155,000 Dubuque $185,000 $45,000 $230,000 Tower Place $45,000 $60,000 $105,000 Chauncey Swan no efforts planned $40,000 $40,000 Court Street $5,000 $40,000 $45,000 Harrison no efforts planned $25,000 $25,000 Totals $355,000 $245,000 $600,000 2021 Capitol $115,000 no efforts planned $115,000 Dubuque $270,000 no efforts planned $270,000 Tower Place $135,000 no efforts planned $135,000 Chauncey Swan $10,000 no efforts planned $10,000 Court Street $15,000 no efforts planned $15,000 Harrison $5,000 no efforts planned $5,000 Totals $550,000 -$550,000 2022 Capitol $140,000 no efforts planned $140,000 Dubuque $15,000 no efforts planned $15,000 Tower Place no efforts planned $250,000 $250,000 Chauncey Swan $75,000 no efforts planned $75,000 Court Street $65,000 no efforts planned $65,000 Harrison $5,000 no efforts planned $5,000 Totals $300,000 $250,000 $550,000 2023 Capitol no efforts planned $45,000 $45,000 Dubuque no efforts planned $55,000 $55,000 Tower Place $55,000 no efforts planned $55,000 Chauncey Swan no efforts planned $75,000 $75,000 Court Street no efforts planned $65,000 $65,000 Harrison $5,000 no efforts planned $5,000 Totals $60,000 $240,000 $300,000 2024 Capitol $45,000 no efforts planned $45,000 Dubuque $40,000 no efforts planned $40,000 Tower Place $55,000 no efforts planned $55,000 Chauncey Swan $145,000 no efforts planned $145,000 Court Street $10,000 no efforts planned $10,000 Harrison $5,000 no efforts planned $5,000 Totals $300,000 - $300,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .................................$2,300,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include Contractor general conditions and A/E fees. (2)Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 3 of 99 Introduction Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 II. INTRODUCTION THP was retained by the City of Iowa City to provide a condition assessment of six separate parking garages. The review included the Capitol Street Ramp, the Dubuque Street Ramp, the Chauncey Swan Ramp, the Tower Place Ramp, the Transportation Center Parking Facility, and the Harrison Street Ramp. THP conducted a structural and waterproofing survey of these garages during a site visit in June, 2019. Heapy Engineering conducted a survey of MEP equipment at each facility during a separate site visit in June, 2019. The primary efforts of the survey consisted of the following: Review of original construction drawings, recent THP-coordinated restoration projects, and previous Master Plan reports, as available, and interviews with relevant City personnel about recent and ongoing maintenance concerns with each facility. A complete visual survey of all facilities to note conditions, including (where applicable) but not limited to floor membrane conditions, expansion joint conditions, floor and soffit deterioration, beam and column deterioration, stairwell structures, integral façade panels or similar elements, and miscellaneous features impacting potential restoration efforts. A representative chain drag survey of supported floors to quantify concrete delaminations and deterioration, along with representative sounding of spalled or deteriorated concrete soffit areas, to quantify delaminations. In the Dubuque Street, Capitol Street, Tower Place and Chauncey Swan Ramps, select concrete powder sampling and laboratory testing for acid soluble chloride ion content of exposed concrete floor structures not currently under membrane. In the Dubuque Street and Capitol Street Ramps, testing of the existing traffic membranes to verify the bond strength of the existing system, to help determine the City of Iowa City Parking Garages 4 of 99 Introduction Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 feasibility of recoating the existing traffic membranes in lieu of complete removal and replacement. Systems inspection services, including review of MEP systems and lighting, performed by Heapy Engineering. MEP survey work included review of major equipment in the garages and parking offices, where accessible. THP analyzed the field survey and laboratory data to prioritize short-term repair needs and more long-term repair and maintenance recommendations. Using this information, THP developed an outline of recommended repair efforts with an opinion of probable costs, and prepared individual 5-Year Master Plans for each facility. All findings and recommendations are based on conditions existing as of the date of the survey and assume the original design and construction of the garages met appropriate standards. Review of conditions hidden or indeterminable from visual assessment were excluded from THP’s scope of work. City of Iowa City Parking Garages 5 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 III. CAPITOL STREET RAMP DESCRIPTION Structural and Waterproofing The Capitol Street Ramp was designed by Carl Walker and Associates, Inc. and constructed around 1980. The garage is located north of Burlington Street, between Capitol Street and Clinton Street, and is directly adjacent to the Old Capitol Town Center. The structure consists of six total levels, with five supported levels. Each level includes three adjacent bays, oriented in the east-west direction. The two southern-most bays act as ramps between adjacent floor levels, while the north bay is predominantly flat. Vehicular access to the garage is available from both Capitol and Clinton Street. The Capitol Street Ramp has approximately 875 parking spaces, and in excess of 280,000 square feet of supported floor structure. The supported levels of the garage are predominately formed by 8-foot-wide, precast, prestressed concrete double tees. The double tees are predominately pretopped, with cast–in–place concrete installed at pour strips over precast support beams, vehicular crossovers between adjacent bays, and along perimeter washes. North-south oriented expansion joints subdivide each supported level into structurally independent segments. These joints are located at approximate third points along the east-west direction of the structure. Joints are located between adjacent precast double tees, at vehicular crossovers over precast support beams, and at intersections with cast-in-place concrete. Joints are typically sealed with urethane sealant. In total, there is in approximately 10 miles of joint sealant in the Capitol Street Ramp. Urethane-based traffic membrane installations are located throughout the three lowest supported floor levels, plus a portion of Level 5. The garage includes two stand-alone stair towers located along the south façade, as well as an integrated central stair tower, located between the middle and north bays. Another stair and elevator tower is located in the northern-most bay, and is directly connected to the adjacent Town Center facility on multiple levels. Stair construction is typically comprised of steel framing with concrete-filled metal pan treads, except for the central stair, which is a precast concrete framed structure. City of Iowa City Parking Garages 6 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 MEP Systems The parking area is naturally ventilated. Stair towers are ventilated and heated only, utilizing exhaust fans at the top of the stair tower with make–up air louvers near the bottom. These systems were not functioning at the time of the surveys. Heating is provided via electric unit heaters. The elevator machine room is served by two (2) mini- split system AC units and heated by an electric unit. A portable dehumidifier is also present in the elevator machine room. The stair towers are equipped with manual standpipes, while the parking decks are not suppressed. Existing drainage for the parking decks appears to be piped to the City or municipality storm sewer system. The Capitol Street Ramp is served from a utility company pad mount transformer and has a main electric service room towards the west end of the garage. The garage has a 400 amp, 480Y277 volt, 3-phase, 4-wire main fusible switchboard. A majority of the electrical distribution equipment is still from the original installation of the facility. The parking area is lit by LED fixtures, each fixture equipped with a combination photocell and motion sensor for control. The space is well lit in all areas. The top deck is outfitted with what appears to be the original metal-halide poles and fixtures that show signs of aging. The location of the poles appears adequate for sufficient light at night. Additionally, there is grounding of the poles to what appears to be the lightning protection system. A control panel, mounted in the Guard Shack provides control for the lighting fixtures. Current settings allow the outer edge and the top deck to be automatic operation through a photocell, with the rest of the lighting kept in the ON position. The majority of the support spaces in the garage still have the original light fixtures with T8 and T12 fluorescent lamps in them. The stairwell well lighting appears to have been changed recently to newer LED based fixtures on both the interior and exterior. Exit signage are a mixed system with some incandescent, some compact fluorescent, and some LED based in the stairwells. City of Iowa City Parking Garages 7 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 The garage has a Simplex 4010 fire alarm system installed that was inspected and approved on 6/9/2019. There are smoke detectors located in the elevator lobbies. There were no fire alarm audio visual devices in the stairwells or elevator lobbies. This would be in keeping with the Building Codes of the original design and build in 1978. Recent Repair and Maintenance Efforts THP has designed and coordinated several structural and waterproofing repair efforts in recent years as part of annual maintenance efforts. These efforts included replacement of most expansion joints in the parking deck, new sealants throughout the exposed level with traffic membrane strips on over joints on the north bay, isolated sealant replacements on the interior levels of the garage, and isolated structural repairs to damaged or deteriorated precast stems and soffits. THP also designed and coordinated repairs to the stair towers, including structural repairs and new sealants on the exposed facades, replacement of select deteriorated metal tread-riser units, and application of a new waterproofing pedestrian traffic membrane system on exposed treads and landings. City of Iowa City Parking Garages 8 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REVIEW AND FINDINGS Precast and Cast-in-Place Concrete No significant issues were noted with either the cast-in-place or precast concrete floor structure in the Capitol Street Ramp. Minor cracking, spalls, or other deterioration were noted throughout the garage, though typically concentrated at the cast-in-place pour strips at vehicular crossovers between adjacent bays (refer to Photo 01, included at the end of this section). Minor scaling, cracking and deterioration were also noted in the cast-in-place concrete washes at the ends of the precast double tees, especially on the exposed top level of the parking deck (Photo 02). THP performed a chain drag survey of all cast-in-place crossovers throughout the garage, and estimates approximately 100 square feet of delaminated or deteriorated concrete. Precast concrete bearings throughout the garage, where visible, were noted to be in good condition, with no significant deterioration and only minor rotation of bearing pads at tee stem bearings on ledge beams. The majority of the bearings in the garage have a manufactured cover installed between adjacent tee stems to deter bird nesting, and as such were not visible for review. Isolated issues were noted with the exposed flange soffits and stems of the precast double tee elements. Corrosion-induced spalling at shear connectors was noted at the underside of several leaking joints throughout the facility (Photo 03). One of the most significant concentrations of this deterioration is below the expansion joint on the south bay of Level 2. Isolated tee stem deterioration was noted below two locations on the south bay of Level 3 (Photo 04). The floor area below both of these locations had been blocked by the City at the time of THP’s survey. No significant issues were noted with spandrel panels and connections. Spalling and cracking were noted at isolated locations, including at the exposed top face of one spandrel panel on the west façade (Photo 05). City of Iowa City Parking Garages 9 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Chloride Testing of Concrete Powder Samples A test program was performed to determine the extent of chloride contamination throughout the exposed Levels 4 through 6 of the Capitol Street Ramp. A total of 6 samples were taken from 3 different locations. Each sample was taken in 1” depth increments. Floor locations were selected with a mix between drive lane and parking areas. Concentrations of between 1.3 to 1.9 lbs. of acid soluble chloride ions per cubic yard of concrete are normally considered the threshold level above which corrosion of embedded reinforcing steel will occur, given sufficient exposure to moisture and oxygen. Samples in the top 1” depth of slabs typically indicate higher chloride content, since this depth is directly exposed to all road salt trafficked in by vehicles. In precast double tees, examination of the overall chloride build-up through the 1”-2” is more critical. If build-up increases to the point where the chlorides start to migrate into the heavily removed tee flanges, restoration measures can become excessive. Average chloride content in the Capitol Street Ramp was 0.80 lbs./cubic yard (CY) for the 0-1” depth, and 0.51 lbs/CY for the 1” to 2” depth. These values are similar to the results from the previous 2012 testing. Refer to Appendix A for a breakdown of the chloride data and a copy of the chloride sampling laboratory report from CTL Group. Membrane Conditions Typical heavy wear and debonding were noted at the traffic membrane installations throughout the lower levels of the garage. The most significant wear was located at vehicular crossovers between adjacent ramp bays (Photo 06). Isolated cracking and splits were also noted in the membrane systems over adjacent tee joints, as well as premature wear of the systems at high edges along the tee joint. Urethane based-traffic membrane strips are installed over tee joints on the north bay of the exposed level of the parking garage. These strips were designed and coordinated by THP as part of the 2018 annual garage repairs project. No issue was noted with these strips. The strips do not extend to the washes at the north and south sides of the bay, or to the crossovers with the middle bay of the garage on either the east or west sides. City of Iowa City Parking Garages 10 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Membrane Bond Testing As part of the review of the membrane system installations at the Capitol Street Ramp, THP performed a series of bond tests at representative locations throughout the structure. A total of 6 bond tests were performed on Levels 2 through 4. One of the tests failed the epoxy adhesive to the disc, at a value of 166 pounds-per-square-inch (psi), and can be disregarded. The remaining five tests carried an average bond strength of 209 psi, with no result less than 166 psi. All tests were recorded as adhesive failures of the existing coating to the concrete substrate. Refer to Appendix B for a more comprehensive breakdown of the membrane bond testing data. While no industry standards exist for pass/fail results of bond tests, THP mandates all new membrane installations or existing membrane substrates scheduled for recoating have a warranted value of 200 pounds per square inch (psi) average, with no single test result of less than 150 psi. All testing is performed per ASTM D4541 specifications. Membrane bond strengths below these values typically carry recommendations for removal to an acceptable substrate, in lieu of simply recoating the system. These criterion values were originally established during testing of older membrane systems in the early 1990’s, where typical minimum values of between 150 to 200 psi were recommended to ensure proper bond strength for the individual layers of the system (top coats to base coats, etc.), as well as for the overall system to the base substrate. A well-prepared substrate and quality installation of a typical modern membrane system will often achieve bond values of 300 psi or greater. Sealants and Shear Connectors Sealant in the lower levels of the garage were found to be in varying states of serviceability, with isolated leaking over several joints. This leaking was particularly heavy below the lowest supported level, where ongoing water infiltration though the joint had caused corrosion of the steel and corresponding spalls of the concrete floor edges and soffit adjacent to the embedded shear connections (Photo 07). However, few joints in the garage appeared to deflect differentially under vehicular traffic, indicating the shear connections are still predominantly intact. City of Iowa City Parking Garages 11 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Expansion Joint Conditions Expansion joints throughout the garage are typically standard wing compression seal systems. No significant issues were noted with these joints, though over 200 linear feet of isolated deteriorated nosing material were noted throughout the garage (Photo 08). The expansion joint seal on Level 5 in the north bay, at the east side, is split and failed from support wing for some length. Stair and Elevator Towers The two southern stair towers in the Capitol Street Ramp have isolated areas of corroding metal tread/riser units, though steel replacements and traffic membrane installations in recent years appears to have predominantly slowed the rate of deterioration. The majority of this deterioration was noted in the southeast stair tower, where an estimated 12 units are deteriorating to the point of replacement (Photo 09), mostly at the Level 3 interface. The joint between the stair tower and elevator tower is a combination of a compressible foam seals, premold seals, and wide isolation joints. Signs of Isolated leaking were noted at several levels adjacent to the stair tower threshold (Photo 10). Minor concrete cracking exists in the enclosed northern stair tower, though no significant signs of corrosion were noted. Isolated, though minor, spalling and cracking was also noted at the central concrete stair, between the north and center bays of the garage. Mechanical/Electrical/Plumbing No significant issues were noted with the manual standpipe system. A cap was missing on one of the standpipes on the top level. Storm drainage piping appear to be adequate and in acceptable condition within the limits of visual observation. Horizontal piping from all the drains to the vertical pipes was recently replace with PVC piping. The stair tower summer ventilation system did not appear to be operational and the temperature was elevated well above ambient at the time of the site visit. The existing electric unit heaters appeared to be functional and in acceptable condition. City of Iowa City Parking Garages 12 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 No significant issues were noted with the electrical distribution equipment, though minor surface rusting was visible at several older components. No issues were noted with the parking area LED fixtures. While adequate, the exposed level lighting is older and less efficient, and visible surface corrosion and deterioration was noted with the older poles and fixtures. Support spaces throughout the garage have aging fixtures with discolored or missing lenses and guards. City of Iowa City Parking Garages 13 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Capitol Street Photo 01 Typical pour strip cracking and deterioration. Capitol Street Photo 02 Visible scaling in exposed concrete washes on top level. Capitol Street Photo 03 Visible corrosion and spalling at shear connector. Capitol Street Photo 04 Tee stem deterioration. City of Iowa City Parking Garages 14 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Capitol Street Photo 05 Spalled spandrel panel corner. Capitol Street Photo 06 Heavily worn traffic coating at vehicle crossover between bays. Capitol Street Photo 07 Spalled edge at precast shear connector. Capitol Street Photo 08 Damaged wing compression expansion joint seal. City of Iowa City Parking Garages 15 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Capitol Street Photo 09 Corroding and deteriorating tread/riser plate. Capitol Street Photo 10 Visible leaking below stair tower door threshold. City of Iowa City Parking Garages 16 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 RECOMMENDATIONS Structural and Waterproofing The deteriorated tee stems and precast soffit at currently blocked areas of parking, along with the associated joint leaking causing these issues should be prioritized and addressed as soon as possible. The recently installed membrane strips on the north bay of the exposed level appear to be mitigating the isolated leaking that has been an issue in recent years. As a result, full membrane strip installations for the remaining top-level joints, washes, and crossovers are recommended. While the traffic membrane throughout the lower levels of the garage is predominantly worn and debonded, full replacement is not recommended at this time. Repair of deteriorated crossover concrete pour strips should be performed, and then these elements recoated to provide better durability. Leaking interior level joints should be removed and replaced, with an allowance for isolated traffic membrane strip installations similar to the top level. In conjunction with these efforts, deteriorated soffit concrete and failed shear connections should be repaired, as well as any deterioration to spandrel panels and connections. This select traffic membrane recoating throughout the lower garage will also alleviate the widespread need to potentially remove and replace poorly bonded existing coatings. While the bond test data indicates the exiting coating may be acceptable for recoating, the close proximity of the overall average for the tests (209 psi) to THP’s recommended threshold (200 psi) means these systems should be investigated more in the future prior to scheduled recoating or replacement. The deteriorated expansion joint nosing throughout the garage should be repaired, along with replacement of the failed wing seal at the exposed level. Several additional seals will likely require repair or replacement as part of future annual maintenance efforts. City of Iowa City Parking Garages 17 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Annual maintenance work should also typically include an allowance for additional isolated sealant and waterproofing repairs, along with knock down of loose concrete and epoxy coating of exposed reinforcement at corroding shear connectors. Repair and localized replacement of isolated stair tower elements, primarily corroding steel landings and tread and risers, should be scheduled within the next several years. Isolated repair of associated waterproofing elements, including sealants and traffic membrane as well as the threshold expansion joint, should also be performed. For additional discussion on the structural and waterproofing recommendations outlined above, refer to the applicable sections of Appendix C. Mechanical/Electrical/Plumbing The stair tower ventilation system should be returned to working order to provide summer ventilation based on temperature at the top of the stair tower. The electrical distribution system is still functional, but reaching the end of its life expectancy according to industry standards. There is no visible eminent danger of equipment failure. It is recommended that the City coordinate a complete maintenance action per the manufacturer’s recommendation on all equipment, including an IR scan to insure proper connections. While outside the scope of this Master Plan, the city should be budgeting money to replace the equipment in the next 10 years. The missing standpipe cap on the top level should be replaced. The top deck exterior light poles are showing signs of age. These poles and fixtures should be replaced with new more energy efficient LED fixtures. The remaining primary fixtures for the parking area are in good condition. All of the existing fluorescent lights in the support spaces should be replaced with new LED light fixtures with vacancy sensing where applicable. Finally, it is recommended the City evaluate installating audio/visual fire alarm devices in the elevator lobbies, stairwells and other employee or public spaces. Other garages managed by the City have devices in these areas. City of Iowa City Parking Garages 18 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Additional information on recommended testing frequencies in accordance with the National Fire Protection Association is included in Appendix D. City of Iowa City Parking Garages 19 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REPAIR AND MAINTENANCE MASTER PLAN THP has developed a 5-year (2020 through 2024) Repair and Maintenance Master Plan for structural, waterproofing, and MEP issues in the Capitol Street Parking Ramp. The total opinion of probable cost for the full 5-year period is $500,000. A complete annual breakdown for the recommended scope of work for both Structural/Waterproofing and MEP efforts is included at the end of this report section. The Master Plan and its associated opinion of probable costs include an allowance for contractor overhead and profit, and all associated consulting fees. Opinion of probable costs reflect recently noted general increases for raw materials, shipping, etc. for similar THP administered efforts in the region. Opinion of probable costs have not been adjusted for inflation beyond 2020. Minor inflation over the life of the Master Plan should be accounted for within the available contingency funds. The conclusions and recommendations in this report are provided for repair/maintenance planning and budgeting purposes. This report is not intended to be used as a construction document. All findings and recommendations are based on conditions existing as of the date of the survey. It is important that the recommended repairs and maintenance are implemented in a timely manner. City of Iowa City Parking Garages 20 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Capitol Street Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Annual Summary (Structural, Waterproofing, and MEP) Year Effort Opinion of Probable Cost(1)(2) 2020 Recommended Structural and Waterproofing Repairs .............................$120,000 Recommended MEP Efforts .......................................................................$35,000 2020 Subtotal ..........$155,000 2021 Recommended Structural and Waterproofing Repairs .............................$115,000 Recommended MEP Efforts........................................................no efforts planned 2021 Subtotal ..........$115,000 2022 Recommended Structural and Waterproofing Repairs .............................$140,000 Recommended MEP Efforts........................................................no efforts planned 2022 Subtotal ..........$140,000 2023 Recommended Structural and Waterproofing Repairs ...............no efforts planned Recommended MEP Efforts .......................................................................$45,000 2023 Subtotal ............$45,000 2024 Recommended Structural and Waterproofing Repairs ...............................$45,000 Recommended MEP Efforts........................................................no efforts planned 2024 Subtotal ............$45,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$500,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2)Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 21 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Capitol Street Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Structural and Waterproofing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 (a) New sealants at roof level sloped bays and washes .....................$40,000 (b) Traffic membrane strip installations at roof level joints ..................$70,000 (c) Contingency funds for annual garage maintenance (3)....................$10,000 2020 Subtotal ..........$120,000 2021 (a) Expansion joint repairs and replacement.......................................$25,000 (b) Interior level sealant replacement at leaking joints, including joint edge and shear connector repairs ..........................$45,000 (c) Concrete soffit repairs....................................................................$25,000 (d) Isolated stair towers repairs and waterproofing .............................$10,000 (e) Contingency funds for annual garage maintenance (3)....................$10,000 2021 Subtotal ..........$115,000 2022 (a) Concrete floor repairs and traffic membrane recoating at vehicular crossovers ..................................................................$50,000 (b) Interior level sealant replacement at leaking joints, including joint edge and shear connector repairs ..........................$45,000 (c) Concrete soffit repairs....................................................................$25,000 (d) Isolated stair towers repairs and waterproofing .............................$10,000 (e) Contingency funds for annual garage maintenance (3)....................$10,000 2022 Subtotal ..........$140,000 2023 no efforts planned 2024 (a) Allowance for interior level sealant replacement at leaking joints, including joint edge and shear connector repairs ..........................$20,000 (b) Contingency funds for annual garage maintenance (3)....................$25,000 2024 Subtotal ............$45,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$420,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. (3) Contingency funds for annual inspections and unidentified scope or efforts associated with structural and waterproofing maintenance. City of Iowa City Parking Garages 22 of 99 Capitol Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Capitol Street Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Mechanical/Electrical/Plumbing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 (a) Repair stair tower ventilation and replace standpipe cap ..............$20,000 (b) Complete IR Scan and maintenance of electrical equipment ........$15,000 2020 Subtotal ............$35,000 2021 no efforts planned 2022 no efforts planned 2023 (a) Replace top deck lighting and poles ..............................................$30,000 (b) Replace common area lighting fixtures..........................................$15,000 2023 Subtotal ............$45,000 2024 no efforts planned TOTAL OPINION OF PROBABLE COSTS (2020-2024) .........................$80,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 23 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 IV. DUBUQUE STREET RAMP DESCRIPTION Structural and Waterproofing The Dubuque Street Ramp was designed by Carl Walker and Associates, Inc. The garage is located north of Burlington Street, between Dubuque Street and Linn Street. The garage serves several businesses that border the north side of the structure, including the Graduate Hotel and Plaza Towers. The structure consists of seven total levels, with six supported levels. The structure has approximately 625 parking spaces, and in excess of 200,000 square feet of supported floor structure. The garage was built in two phases, with the lower four supported levels constructed in around 1981, and the upper levels constructed around 1985. Each level includes two adjacent bays, oriented in the east-west direction. The geometry of the garage is a double helix configuration, with the two adjacent bays sloped in opposing directions to provide crossover traffic flow to adjacent bays at the top and bottom of each level, plus an additional crossover at the common intersection between the two bays in the middle of each level. Vehicular access to the garage is available from both Dubuque Street and Linn Street. The original lower supported levels of the garage are a post-tensioned concrete structure. The original construction drawings indicate the typical slab is nominally 5” thick, and reinforced with ½” diameter, 270k strand tendons. The location and profile of the tendons varies within the slab depth, from approximately 1” from the bottom of the slab at midspan to approximately 1-1/4” from the top of the slab over support beams. This designed tendon drape within the slab allows the structure to maximize the beneficial compressive stresses imparted by the tendons – upward forces from tendons at mid- span regions, and downward forces from tendons over support beams. Based on the early 1980’s construction of the facility, the tendons are believed to be greased and encapsulated in extruded plastic sheathing. Slabs span to post-tensioned support beams located at 24 feet on center, which are in turn supported from a mix of cast-in-place and precast columns. A single north-south oriented expansion joints divides City of Iowa City Parking Garages 24 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 each level along the west side of the center crossover. A 4-foot wide, cast-in-place concrete pour strip is located adjacent to the expansion joint at each level, to provide stressing pockets for the post tensioning tendons that reinforce the slabs west of the expansion joint. The two newer upper garage levels are comprised of 8-foot-wide, precast, prestressed concrete double tees with a cast-in-place topping slab. 6” thick precast concrete panels form the façade of the garage. Construction joints are located in the slab that mirror the joints between adjacent precast double tees below, with additional construction joints installed over precast support beams, and continuously at the middle of each bay. Joints are typically sealed with urethane sealant. There are approximately 13,000 linear feet of construction joints in the two precast levels of the Dubuque Street Ramp, with most joints sealed with urethane. Expansion joints exist in the precast levels which mirror the location and orientation of the joints in the post-tensioned levels below. Urethane-based traffic membrane installations are located throughout the post-tensioned floor levels. The garage includes two stand-alone stair and elevator towers in the northeast and northwest corners of the facility. Stair construction is typically comprised of steel framing with concrete-filled metal pan treads. The Parking Department Maintenance Office is located below street level, in the southwest quadrant of the facility. A retrofit pedestrian walkway bridge connects the north side of the garage to the newer Plaza Towers on the Red Level (second floor). MEP Systems The parking area is naturally ventilated except for the lower level which is mechanically ventilated via a large, inline fan system. Stair towers are ventilated and heated utilizing exhaust fans at the top of the stair tower with makeup air louvers near the bottom; these systems were not functioning at the time of our review. Heating is provided via electric unit heaters. The elevator machine room is equipped with a small packaged AC unit to maintain appropriate conditions for the elevator controller. The Parking Department City of Iowa City Parking Garages 25 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Maintenance Office is heated and air conditioned utilizing a residential type natural gas furnace and air-cooled AC system. The stair towers are equipped with manual standpipes. The majority of the parking decks are not suppressed, except for the lowest level and the Parking Department Maintenance Office. Existing drainage for the parking decks appears to be piped to a municipality storm system. Lower level appears to drain to a sanitary sewage ejector located with the Parking Department Maintenance Office. It appears this ejector also serves the toilet room fixtures within the office area. The Dubuque Street Ramp is served from a utility company pad mount transformer and has a main electric service room towards the west end of the garage. The garage has a 600 amp, 480Y277 volt, 3-phase, 4-wire main fusible switchboard. A majority of the electrical distribution equipment is still from the original installation of the facility. The parking area is lit by LED fixtures. Each fixture is equipped with a combination photocell and motion sensor for control. The space is well lit in all areas. The top deck is outfitted with what appears to be the original metal-halide poles and fixtures. The location of the poles appears minimal to provide sufficient light at night, but this may be due to the close proximity of the parking deck to a hotel and residential high-rise. There does not appear to be grounding of the poles to a lightning protection system. A control panel, mounted in the Electrical Room, provides control for the lighting fixtures. Current settings are for all lights to be in automatic operation from photocell or motion sensor. The majority of the support spaces in the garage still have the original light fixtures with T8 and T12 fluorescent lamps in them. The stairwell lighting appears to have been changed recently to newer LED based fixtures on both the interior and exterior. Exit signage throughout the garage are a mixed system with some incandescent, some compact fluorescent, and some LED based in the stairwells. City of Iowa City Parking Garages 26 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 The garage has a Simplex 4010 fire alarm system that was inspected and approved on 6/9/2019. There are smoke detectors located in the elevator lobbies. Fire alarm audio visual devices are located in the stairwells or elevator lobbies. Recent Repair and Maintenance Efforts THP has designed and coordinated several structural and waterproofing repair efforts in recent years as part of annual maintenance efforts. These efforts included widespread concrete floor repairs, with repair of several failed post-tensioning tendons, recoat traffic membrane applications to the lower supported levels, and recoat or replacement traffic membrane applications to upper post-tension level crossovers. Isolated construction joint sealant replacement has been performed on the upper precast levels, in addition to expansion joint repairs or replacements throughout the garage. Isolated concrete soffit and beam repairs have been completed in the post-tension structure. Stair towers have had several tread-riser repairs and replacements, with isolated waterproofing and flashing of the stair tower exterior. City of Iowa City Parking Garages 27 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REVIEW AND FINDINGS Concrete Floor and Soffit Deterioration Throughout the post-tensioned slabs of the Dubuque Street Ramp, THP performed a representative chain drag survey of remaining floor areas, with a focus on slab areas located over beam lines, where slab reinforcement would be typically be highest. THP estimates a total of approximately 1,000 square feet of deterioration exists in the post- tensioned floor structure throughout the garage. This deterioration was typically noted over beam lines, and often adjacent to previous floor repairs (refer to Photos 01, included at the end of this section). The majority of previous floor repairs from the last several years appear to be intact, with no significant issues. No significant issues were noted with the post-tensioned floor slabs, with minimal spalls or other deterioration, and no visible grease spotting or tendon-induced cracking or significant deflection. Isolated cracking and minor deterioration were noted at isolated beams throughout the post-tensioned garage structure (Photo 02). Chloride Testing of Concrete Powder Samples A test program was performed to determine the extent of chloride contamination throughout the exposed precast levels of the Dubuque Street Ramp. A total of 6 samples were taken from 3 different locations. Each sample was taken in 1” depth increments. Floor locations were selected with a mix between drive lane and parking areas. Concentrations of between 1.3 to 1.9 lbs. of acid soluble chloride ions per cubic yard of concrete are normally considered the threshold level above which corrosion of embedded reinforcing steel will occur, given sufficient exposure to moisture and oxygen. Samples in the top 1” depth of slabs typically indicate higher chloride content, since this depth is directly exposed to all road salt trafficked in by vehicles. In precast double tees, examination of the overall chloride build-up through the 1”-2” depth is more critical. If build-up increases to the point where the chlorides start to migrate into the heavily removed tee flanges, restoration measures can become excessive. City of Iowa City Parking Garages 28 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Average chloride content in the Dubuque Street Ramp was 7.49 lbs./CY for the 0-1” depth, and 2.49 lbs/CY for the 1” to 2” depth, with only one value recorded below the minimum corrosive threshold. These values are similar to the results from the previous 2012 testing. Refer to Appendix A for a breakdown of the chloride data and a copy of the chloride sampling laboratory report from CTL Group. Membrane Conditions No significant issues were noted with the traffic bearing membrane throughout the lower levels of the garage which has been recoated since the last assessment report in 2012. Much of this coating is still under warranty. One end-bay crossover, on Level 4, has not been replaced or recoated since 2012. The coating at this area was noted to have typical heavy wear and debonding (Photo 03), with much of the coating worn to bare concrete. Membrane Bond Testing As part of the review of the membrane system installations at the Dubuque Street Ramp, THP performed a series of bond tests at representative locations throughout the structure. A total of 7 bond tests were performed on the lower post-tensioned levels of the garage, including a mixture of recently recoated and older installations. One of the tests failed the epoxy adhesive to the disc, at a value of 134 psi, and can be disregarded. The remaining six tests carried an average bond strength of 250 psi, with no result less than 166 psi. All tests were recorded as adhesive failures of the existing coating to the concrete substrate. Refer to Appendix B for a more comprehensive breakdown of the membrane bond testing data. While no industry standards exist for pass/fail results of bond tests, THP mandates all new membrane installations or existing membrane substrates scheduled for recoating have a warranted value of 200 psi average, with no single test result of less than 150 psi. All testing is performed per ASTM D4541 specifications. Membrane bond strengths below these values typically carry recommendations for removal to an acceptable substrate, in lieu of simply recoating the system. These criterion values were originally established during testing of older membrane systems in the early 1990’s, where typical minimum values of between 150 to 200 psi were City of Iowa City Parking Garages 29 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 recommended to ensure proper bond strength for the individual layers of the system (top coats to base coats, etc.), as well as for the overall system to the base substrate. A well-prepared substrate and quality installation of a typical modern membrane system will often achieve bond values of 300 psi or greater. Expansion Joint Conditions Expansion joints throughout the garage are a mixture of premold and wing compression seal systems, with most locations replaced since the last assessment in 2012. No significant issues were noted with the expansion joint seals, with minimal nosing deterioration observed at a few locations (Photo 04). Expansion joints seals and isolation joints at the stair tower interfaces were split and deteriorated at several locations (Photo 05), with apparent leaking visible below. Sealants in the Precast Levels Sealant throughout the upper precast levels are in various states of serviceability. Isolated construction joint and cove sealants have been replaced in recent years, but significant lengths of older sealants were noted to be crazing and deteriorating from UV exposure (Photo 06). Isolated leaking was noted below adjacent tee joints throughout the top level (Photo 07), with occasional visible staining from corroding shear connectors (Photo 08). However, no joints in the garage were noted to deflect differentially under vehicular traffic, and no significant floor spalls or other deterioration were visible in the precast topping slab, indicating the shear connections are still predominantly intact and functioning as designed. Façade Panels and Sealants No significant issues were noted with the façade panels or their connections to the garage structure. However, the joints at the south façade where the panels interface with the garage structure are open (Photo 09), allowing water infiltration from wind- driven rain and other inclement weather. Stair and Elevator Towers Stair towers in the Dubuque Street Ramp are in varying states of deterioration. Several steps in both towers have been replaced in recent years, mostly in the northwest tower. Several tread/risers and landing plates were noted to have corrosion and deterioration (Photo 10) with visible exposed aggregate from scaling and freeze/thaw induced City of Iowa City Parking Garages 30 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 deterioration in the lower steps and landings (Photo 11), in particular in the lower levels of the northwest tower. While some of this deterioration is due to water infiltration from the adjacent garage slabs, there are also signs of leaking from the roofs of the stair towers (Photo 12). Mechanical/Electrical/Plumbing No significant issues, such as leaks or significant corrosion, were noted with the standpipe and sprinkler system. The fire service backflow preventer also appeared to be functioning with no visible issues. The existing drainage system piping had visible corrosion on the storm drainage risers. The existing sewage ejector seals appeared to be in place and no issues were noted with the discharge piping. No issues were noted with the plumbing fixtures within the Parking Department Office Area and flush valves and faucets were in working order. The lower level parking deck mechanical ventilation fan was disconnected from the exhaust ductwork and not running at the time of the site visit. There were no apparent CO/NOx (carbon monoxide/nitrous oxides) controls for that fan. Generally, without CO/NOx controls, the fan is expected to operate continuously to provide code required ventilation. The stair tower ventilation fans were not in operation and the thermostatic controls originally specified for the control of the fan appeared to have been removed and replaced with blank cover plates. Additionally, there was no apparent source of make-up air for these tower ventilation fans. The stair towers are heated with electric unit heaters, which appeared to be in working order. No issues were noted with the Parking Department Office Area HVAC system. Based on a limited review, it appears the system is providing outdoor air to the space that it is positive relative to the garage. The main electric room is equipped with a unit heater but no source of ventilation. A significant storm water leak appeared to be occurring at a construction joint in the structure, with the main switchboard displaying a significant amount of rust on the City of Iowa City Parking Garages 31 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 exterior enclosure due to chloride-contaminated water dripping onto the equipment. A 15 kVA transformer serving the exit and egress lights was very hot and is humming very loudly at the time of the surveys. No issues were noted with the parking area LED fixtures. While adequate, the exposed level lighting is older and less efficient, and visible surface corrosion and deterioration was noted with the older poles and fixtures. Support spaces throughout the garage have aging fixtures with discolored or missing lenses and guards. Non-LED exit signage fixtures are showing signs aging with yellowing lenses that are hard to read. City of Iowa City Parking Garages 32 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Dubuque Street Photo 01 Locations of noted floor deterioration in post-tensioned slab. Dubuque Street Photo 02 Typical minor cracking and deterioration of beam bottom. Dubuque Street Photo 03 Worn older traffic coating on Level 4. Dubuque Street Photo 04 Typical cracking in expansion joint nosing. City of Iowa City Parking Garages 33 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Dubuque Street Photo 05 Split seal at stair tower interface. Dubuque Street Photo 06 UV-deteriorated sealant on exposed level. Dubuque Street Photo 07 Visible leaking below exposed level. Dubuque Street Photo 08 Corroding and deteriorated shear connector. City of Iowa City Parking Garages 34 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Dubuque Street Photo 09 Open façade joints on south elevation. Dubuque Street Photo 10 Corroded riser plate Dubuque Street Photo 11 Scaling and deterioration of lower level concrete-filled steps and landing. Dubuque Street Photo 12 Visible leaking through stair tower roof. City of Iowa City Parking Garages 35 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 RECOMMENDATIONS Structural and Waterproofing Concrete floor repairs with traffic membrane patching are the highest priority Dubuque Street issue to address over the next few years. While no definitive locations requiring tendon repairs were noted during the survey, an allowance for a limited number of tendon repairs should be included. In conjunction with these efforts, repairs to isolated deteriorated soffit areas and prestressed support beams should also be performed. The recoating or replacement of the older remaining worn crossover membrane should also be performed in conjunction with other floor repairs and membrane patching, to provide beneficial waterproofing protection of these high-traffic areas. Based on the overall bond test data, the existing crossover area membrane is anticipated to be recoated, in lieu of complete removal to bare concrete and installation of a new membrane system. However, past THP-coordinated projects required isolated removal of existing traffic membrane areas following additional review and testing with the selected coating manufacturer. As a result, it is recommended this effort include an allowance for isolated removal and replacement. In the precast structure, the chloride levels at the critical depths in the topping slab were found to be well above the threshold levels for potential corrosion of reinforcing steel, reconfirming the test data from the 2012 assessment. However, no visible or wide spread deterioration was noted during this survey. While no immediate remediation of the chloride levels is recommended as part of this Master Plan, these topping slabs should continue to be monitored. It is likely that within the next 5 to 10 years, applications of at least a water repellent will likely be required to the topping slabs, with consideration for application of a migrating corrosion inhibitor. The minor expansion joint nosing deterioration noted at isolated seals should be repaired as part of annual maintenance to mitigate water infiltration and help ensure the recently replaced seals reach their intended service life. New urethane sealants should be installed throughout the exposed precast level topping slab, along with isolated traffic membrane strip installations and recoating at crossovers. City of Iowa City Parking Garages 36 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Silicone sealants should also be installed at exposed joints around the bearings of the precast panels on the south face of the garage. Repair and localized replacement of select stair tower elements, primarily corroding steel landings, tread and risers, should be scheduled within the next two years, along with installation of a new pedestrian grade traffic membrane coating, similar to what was recently installed in the Capitol and Chauncey Swan stair towers. In addition to these efforts, the roofing systems of both towers should be replaced to further mitigate leaking into the stairs and landings. For additional discussion on the structural and waterproofing recommendations outlined above, refer to the applicable sections of Appendix C. Mechanical/Electrical/Plumbing It is recommended to consider performing wall thickness testing on the existing storm risers to determine the extent that corrosion has reduced the piping wall thickness, then schedule repair or replacement as appropriate. The source of water leaking into the main electric room should also be further investigated and resolved. The stair tower ventilation system should be returned to working order to provide summer ventilation based on temperature at the top of the stair tower. The lower level garage exhaust fan should be returned to continuous operation or CO/NOx detection and control should be added to safely cycle the operation of the ventilation system in compliance with current building code. A ventilation exhaust fan and source of makeup air (louver) should be added to the main electrical room to remove heat from the space associated with the transformer impedance. The electrical distribution system is reaching the end of its life expectancy according to industry standards. It is recommended that the City coordinate a complete maintenance action per the manufacturer’s recommendation on all equipment, including an IR scan to insure proper connections. While not part of this proposed Master Plan, the City should be budgeting money to replace the equipment in the next ten years. City of Iowa City Parking Garages 37 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 The top deck exterior light poles are showing signs of age. These poles and fixtures should be replaced with new more energy efficient LED fixtures. Additionally, the photocell unit for control of the fixtures is located approximately 5’-0” above the deck level and are pointed at odd angles, in some cases directly back at the pole. Replacement of the poles should include new control devices at the top of the pole. The remaining fixtures for the parking area are in good condition. All of the existing fluorescent lights in the support spaces should be replaced with new LED light fixtures with vacancy sensing where applicable. The building mounted lighting and the stairwell lighting are LED with no noted issues or recommendations. The older exit lighting should be scheduled for replacement. Additional information on recommended testing frequencies in accordance with the National Fire Protection Association is included in Appendix D. City of Iowa City Parking Garages 38 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REPAIR AND MAINTENANCE MASTER PLAN THP has developed a 5-year (2020 through 2024) Repair and Maintenance Master Plan for structural, waterproofing, and MEP issues in the Dubuque Street Parking Ramp. The total opinion of probable cost for the full 5-year period is $610,000. A complete annual breakdown for the recommended scope of work for both Structural/Waterproofing and MEP efforts is included at the end of this report section. The Master Plan and its associated opinion of probable costs include an allowance for contractor overhead and profit, and all associated consulting fees. Opinion of probable costs reflect recently noted general increases for raw materials, shipping, etc. for similar THP administered efforts in the region. Opinion of probable costs have not been adjusted for inflation beyond 2020. Minor inflation over the life of the Master Plan should be accounted for within the available contingency funds. The conclusions and recommendations in this report are provided for repair/maintenance planning and budgeting purposes. This report is not intended to be used as a construction document. All findings and recommendations are based on conditions existing as of the date of the survey. It is important that the recommended repairs and maintenance are implemented in a timely manner. City of Iowa City Parking Garages 39 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Dubuque Street Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Annual Summary (Structural, Waterproofing, and MEP) Year Effort Opinion of Probable Cost(1)(2) 2020 Recommended Structural and Waterproofing Repairs .............................$185,000 Recommended MEP Efforts .......................................................................$45,000 2020 Subtotal ..........$230,000 2021 Recommended Structural and Waterproofing Repairs .............................$270,000 Recommended MEP Efforts........................................................no efforts planned 2021 Subtotal ..........$270,000 2022 Recommended Structural and Waterproofing Repairs ...............................$15,000 Recommended MEP Efforts........................................................no efforts planned 2022 Subtotal ............$15,000 2023 Recommended Structural and Waterproofing Repairs ...............no efforts planned Recommended MEP Efforts .......................................................................$55,000 2023 Subtotal ............$55,000 2024 Recommended Structural and Waterproofing Repairs ...............................$40,000 Recommended MEP Efforts........................................................no efforts planned 2024 Subtotal ............$40,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$610,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2)Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 40 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Dubuque Street Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Structural and Waterproofing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 (a) Concrete floor repairs and membrane patching...........................$115,000 (b) Concrete soffit repairs....................................................................$15,000 (c) Expansion joint repairs.....................................................................$5,000 (d) Stair tower roof replacements........................................................$40,000 (e) Contingency funds for annual garage maintenance (3)....................$10,000 2020 Subtotal ..........$185,000 2021 (a) Traffic membrane recoating at crossovers...................................$125,000 (b) New sealants at roof level topping slab .........................................$45,000 (c) North façade joint sealant replacements........................................$25,000 (d) Stair towers repairs and waterproofing ..........................................$65,000 (e) Contingency funds for annual garage maintenance (3)....................$10,000 2021 Subtotal ..........$270,000 2022 (a) Contingency funds for annual garage maintenance (3)....................$15,000 2022 Subtotal ............$15,000 2023 no efforts planned 2024 (a) Allowance for concrete floor repairs and membrane patching.......$20,000 (b) Contingency funds for annual garage maintenance (3)....................$20,000 2024 Subtotal ............$40,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$510,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. (3) Contingency funds for annual inspections and unidentified scope or efforts associated with structural and waterproofing maintenance. City of Iowa City Parking Garages 41 of 99 Dubuque Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Dubuque Street Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Mechanical/Electrical/Plumbing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 (a) Repair stair tower ventilation..........................................................$15,000 (b) Install CO/Nox control and repair ductwork ...................................$10,000 (c) Electrical room ventilation................................................................$5,000 (d) Complete IR Scan and maintenance of electrical equipment ........$15,000 2020 Subtotal ............$45,000 2021 no efforts planned 2022 no efforts planned 2023 (a) Replace top deck lighting and poles ..............................................$35,000 (b) Replace common area lighting fixtures..........................................$20,000 2023 Subtotal ............$55,000 2024 no efforts planned TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$100,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 42 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 V. TOWER PLACE RAMP DESCRIPTION Structural and Waterproofing The Tower Place Ramp was designed by Neumann Monson, PC and constructed in 2000. The structural engineer of record was Paragon Structural Design, Inc. The garage is located south of Iowa Avenue, between South Gilbert Street and Linn Street. The garage includes multiple levels of enclosed retail and business space located along the north and west sides of the structure, including the City Parking Office. The structure consists of six total levels, with five supported levels and a partial basement level located substantially below grade which is reportedly used for Senior Center parking. The structure includes 510 parking spaces, and approximately 180,000 square feet of supported parking structure. Each level includes two bays, oriented in the east-west direction, separated by an open 25-foot-wide bay in the middle of the garage that functions as a light well, and provides for snow collection and drainage from exposed levels above. The geometry of the garage is a double helix configuration, with the two adjacent bays sloped in opposing directions. Crossover traffic flow between bays is structured at the top and bottom of each level, plus an additional crossover at the common elevation between the two bays in the middle of each level. Additional parking and an expanded crossover is located on the west side of the top two levels, over occupied business space below. Vehicular access to the supported garage is from Iowa Avenue, while the partial basement level is accessible on the east side of the structure, from South Gilbert Avenue. The supported levels of the garage are post-tensioned concrete. The original construction drawings indicate the typical slab is nominally 5” thick, and spans to post- tensioned support beams located at 18 feet on center, which are in turn supported from cast-in-place columns. The primary slab reinforcement is 7 strand, ½” diameter, 270k strand tendons wrapped in extruded polyurethane sheathing. Tendons were additionally specified to have fully encapsulated, waterproof connections between the tendon and anchorage location. The City of Iowa City Parking Garages 43 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 location and profile of the tendons varies within the slab depth, from approximately 1” from the bottom of the slab at mid-span to approximately 1” from the top of the slab over support beams. This designed tendon drape within the slab allows the structure to maximize the beneficial compressive stresses imparted by the tendons – upward forces from tendons at mid-span regions, and downward forces from tendons over support beams. Tendons are anchored and stressed from either the expansion joints or the ends of the garage. Slabs are also reinforced with conventional reinforcement, again near the top surface in slab areas over beams, and near the bottom surface near midspans. Drawings do not indicate this secondary reinforcement was intended to be epoxy-coated or galvanized for additional corrosion protection. Beams cast integral with slabs are similarly reinforced with a combination of post- tensioning tendons and conventional rebar. Two separate north-south oriented expansion joints segment each level. These joints are located to the east of the center crossover, as well as the interface with the occupied space on the west side of the facility. Membrane is installed throughout the garage over occupied space on the first supported level, at crossovers between the north and south bays, and on west side of Level over the occupied businesses. The garage includes two integrated stair and elevator towers at the east and west sides of the light well. Stair construction is typically comprised of steel framed stringers, treads and risers. The facade of the Tower Place Ramp facility is a mixture of brick and stone construction. Decorative ornamental steel and aluminum elements adorn the open perimeter of the top two levels. MEP Systems The parking area is naturally ventilated except for the lowest level area used for non- public parking, which is equipped with mechanical ventilation. Stair towers are ventilated City of Iowa City Parking Garages 44 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 and heated utilizing exhaust fans at the top of the stair tower with make–up air louvers near the bottom. Heating is provided via electric unit heaters. The stair towers are equipped with manual standpipes. The parking decks are not suppressed except for the lowest level parking areas, which is equipped with a dry pipe system. The accessory spaces, such as the tenant spaces, boiler room, and Parking Department Office, are suppressed. Existing drainage for the parking decks appears to be piped to the City or municipality storm sewer systems. The Parking Department Office is served by a small, variable-air-volume air handler (VAV AH) unit equipped with cooling, heating, and airside economizer. VAV units for zone control are equipped with hot water (HW) reheat coils. Controls are direct digital controls (DDC). Cooling and Heating needs for the Parking Office and Tenant Spaces are provided by a central chiller plant / heating hot water boiler plant. The boiler plant is located at the lowest level of the facility adjacent to one of the snow pit areas. The electrical distribution system for the facility is served from a utility company pad mount transformer and multiple electric services in a main electric room located in the northwest part of the garage at the lower level. The garage has a 1200 amp, 480Y277 volt, 3-phase, 4-wire main fusible switchboard with multiple separately metered switchboards to serve the tenant spaces. All of the equipment is still from the original installation of the facility in approximately 2001. The parking area is lit by LED fixtures, with some fixtures equipped with a combination photocell and motion sensor for control. The top deck is outfitted with what appears to be the original poles and metal-halide fixtures. The location of the poles appears sufficient for adequate lighting at night. The poles are grounded to a lightning protection system. The majority of the support spaces in the garage still have the original light fixtures with T8 fluorescent lamps in them. The stairwell lighting appears to have been changed recently to newer LED based fixtures on the interior, with the original metal halide on the exterior. Exit signage are a mixed system with some incandescent and some compact fluorescent-based fixtures. City of Iowa City Parking Garages 45 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 The garage has a Simplex 4010 fire alarm system that was inspected and serviced on 3/1/2019. There are smoke detectors located in the elevator lobbies. There are fire alarm audio visual devices located in the common areas. Recent Repair and Maintenance Efforts THP has designed and coordinated several structural and waterproofing repair efforts in recent years as part of annual maintenance efforts. These efforts included widespread expansion joint repairs and replacements, with traffic membrane strip installations adjacent to expansion joints on the upper levels of the facility. Isolated concrete floor repairs have also been performed, including the repair of several failed post-tensioning tendons. City of Iowa City Parking Garages 46 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REVIEW AND FINDINGS Concrete Floor and Soffit Deterioration Throughout the post-tensioned slabs of the Tower Place Ramp, THP performed a representative chain drag survey of floor areas throughout the facility, with a focus on slab areas located over beam lines, where slab reinforcement would be typically be the highest. THP estimates a total of approximately 250 square feet of floor deterioration exists in the post-tensioned floor structure. The majority of this deterioration is in the lowest level of the garage, which is predominantly covered with a traffic membrane application. No issues were noted with previous floor repairs from the last several years. No significant issues related to visible grease spotting or tendon-induced cracking or significant deflection were noted which may be indicative of a failed post-tensioning tendon. Minor grease spotting was visible at a few isolated locations in the garage. These locations included a previous concrete repair in the northeast quadrant of the garage, with grease visible in the cracking on the patched surface (Refer to the attached Photo 01, included at the end of this report section). Grease spotting was also noted at two exposed grout-pocket for the anchorage of tendons, visible on the side of the middle crossover (Photo 02). Both of these locations have had visible grease spotting for several years, with no apparent issues to the floor slabs. No apparent problems or deterioration were noted in the exposed beams and columns throughout the garage. Chloride Testing of Concrete Powder Samples A test program was performed to determine the extent of chloride contamination throughout the exposed levels of the Tower Place Ramp. A total of 6 samples were taken from 3 different locations in 1” depth increments, at the 0”-1” and 1” to 2” depths. Floor locations were selected with a mix between drive lane and parking areas. Concentrations of between 1.3 to 1.9 lbs. of acid soluble chloride ions per cubic yard of concrete are normally considered the threshold level above which corrosion of embedded reinforcing steel will occur, given sufficient exposure to moisture and oxygen. Samples in the top 1” depth of slab typically indicate higher chloride content, since this City of Iowa City Parking Garages 47 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 depth is directly exposed to all road salt trafficked in by vehicles. However, in a newer post-tensioned structure such as the Tower Place Ramp, examination of the overall chloride build-up through the 1”-2” depth (where tendons are generally located over support beams) is more critical. Average chloride content in the garage was 3.89 lbs./CY for the 0-1” depth, but fell off as anticipated to an average value of 0.27 lbs/CY for the 1” to 2” depth. These values are similar to the results from the previous 2012 testing. Refer to Appendix A for a breakdown of the chloride data and a copy of the chloride sampling laboratory report from CTL Group. Expansion Joint, Membrane, and Sealant Conditions Expansion joints throughout the garage are a wing compression seal systems. Several seals have visible splits and tears, as well as deteriorated nosing material (Photo 03). The traffic bearing membrane throughout the lower levels of the garage was noted to be predominantly intact and functioning, though wear and minor deterioration was visible at several areas, including drive lanes and crossovers. No significant debonded or split areas were noted. Traffic membrane installations on the upper levels of the garage adjacent to stair towers and expansion joints were similarly worn at several locations (Photos 04 and 05). Exposed sealants throughout the garage were in various states of serviceability. Exposed level sealants at joints and previously sealed cracks were worn and degrading due to UV exposure (Photo 06). Cove sealants were typically not installed throughout the garage at exposed vertical surfaces. Membrane Bond Testing In anticipation of the need to begin at least partial recoating of traffic membrane installations throughout the Tower Place Ramp, THP performed two bond tests at select locations on the lowest supported level. The two tests carried bond strengths of 197 psi and 260 psi, with both failures recorded as adhesive failures of the existing coating to the concrete substrate. Refer to Appendix B for a more comprehensive breakdown of the membrane bond testing data. City of Iowa City Parking Garages 48 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 While no industry standards exist for pass/fail results of bond tests, THP mandates all new membrane installations or existing membrane substrates scheduled for recoating have a warranted value of 200 pounds per square inch (psi) average, with no single test result of less than 150 psi. All testing is performed per ASTM D4541 specifications. Membrane bond strengths below these values typically carry recommendations for removal to an acceptable substrate, in lieu of simply recoating the system. These criterion values were originally established during testing of older membrane systems in the early 1990’s, where typical minimum values of between 150 to 200 psi were recommended to ensure proper bond strength for the individual layers of the system (top coats to base coats, etc.), as well as for the overall system to the base substrate. A well-prepared substrate and quality installation of a typical modern membrane system will often achieve bond values of 300 psi or greater. Stair Towers Signs of ongoing water infiltration into the stair towers was noted at several levels, in particular at the upper levels of the west stair tower. At these locations, water appears to be bypassing the vestibule and leaking into the interior space (Photos 07 and 08). This leaking is causing corrosion of the metal tread and riser elements (Photo 09). Handrails Several posts for the handrail of the handicap ramp adjacent to the west occupied spaced on Level 2 had visible corrosion at the base, where anchored to the slab or ramp (Photo 10). Garage Facade Sealants and expansion joints throughout the brick facade were noted to be crazed and cracking due to UV exposure, and are nearing the end of their anticipated service life (Photo 11). Visible biological growth and failed mortar and sealant joints was noted below several cap stones accessible from the top level of the garage (Photo 12). City of Iowa City Parking Garages 49 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Mechanical/Electrical/Plumbing No issues were noted with the existing fire services, including the fire protection piping. Storm drainage piping appeared to be in similarly good condition. The stair tower summer ventilation systems did not appear operational, with interior temperature elevated to well above ambient. The existing air handler unit serving the Parking Office is in working order and appears to be operating properly. The central chilled water and heating hot water system equipment appears to have several issues. One of the original hot water boilers has been replaced. The removed boiler is currently stored in the mechanical room for spare parts to the other original boiler. While no issues were noted with the HW pumps, the cold-water (CW) pumps have elevated levels of corrosion on the pump frame, caused by elevated humidity levels in the mechanical while the chillers were operating. A portable de-humidifier has been installed in the mechanical room to deal with the humidity, and this may help prolong the life of the CW pumps. Boiler flues and generator engine exhaust do not appear to be extended far enough from garage ventilation openings to be code compliant. These vents are located partially up the elevation of the building directly adjacent to openings on the parking decks. The snow melt system has partially failed. Approximately one-third of the snow melt system is not functional due to failures in the underslab radiant pipe. Two variable frequency drives appear to have been replaced. The remaining five original variable frequency drives appear to be near the end of their life expectancy. No significant visual issues were noted with the electrical distribution equipment. No issues were noted with the parking area LED fixtures or exposed top level light poles. Support spaces throughout the garage have aging original fixtures with discolored or missing lenses and guards. City of Iowa City Parking Garages 50 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 The stairwell interior fixtures are in good condition and provide adequate lighting. However, the exterior fixtures have indications of leakage around the lens that severely limit the light output. Exit signage fixtures are showing signs of aging, with yellowing lenses that are hard to read. The garage has a Simplex 4010 fire alarm system that was inspected and serviced on 3/1/2019. There are smoke detectors located in the elevator lobbies. Fire alarm audio visual devices are located in the common areas. City of Iowa City Parking Garages 51 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Tower Place Photo 01 Visible grease leaking from floor patch on top level. Tower Place Photo 02 Visible grease leaking from two tendon pockets Tower Place Photo 03 Torn and deteriorated wing compression seal. Tower Place Photo 04 Heavily worn traffic coating adjacent to expansion joint on top level. City of Iowa City Parking Garages 52 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Tower Place Photo 05 Debonded and deteriorated traffic coating. Tower Place Photo 06 Typical deteriorated crack sealant. Tower Place Photo 07 Exterior view of vestibule curtain wall base. Tower Place Photo 08 Visible leaking at interior soffit of vestibule. City of Iowa City Parking Garages 53 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Tower Place Photo 09 Corroding metal steps in stair tower. Tower Place Photo 10 Corroding rail post base. Tower Place Photo 11 Visibly deteriorated sealant at façade control joint. Tower Place Photo 12 Deteriorated cap stone mortar joint. City of Iowa City Parking Garages 54 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 RECOMMENDATIONS Structural and Waterproofing The leaking in the stair towers should be addressed to mitigate ongoing corrosion of the stair tread and risers. This repair effort will likely require some exploratory and additional investigation efforts into the as-built conditions for the vestibule curtain wall, which may be contributing to the leaking. In conjunction with this work, the exterior traffic membrane coating adjacent to the stair vestibules should be recoated to further alleviate potential avenues for water to infiltrate the stair towers. Following remediation of the active leaking into the stair tower, the existing stair structure should have new sealants and a slip-resistant epoxy coating scheduled for installation, along with cleaning and coating of select corroding elements. The deteriorated wing compression seal expansion joints in the garage should be scheduled for repair or replacement, in conjunction with recoating of select adjacent membrane strips which are beginning to wear. Existing floor deterioration should be repaired, with new traffic membrane patches where applicable. In conjunction with this work, additional exploratory efforts should be performed to isolated locations of visible grease spotting to assess and repair potential sheathing issues. While no active leaks were noted with the existing traffic membrane coating over the lower level occupied space, the system appears to be wearing. It is recommended to budget and plan for at least partial recoating of this level, up to 25%, within the next 5 years. The coating should continue to be reviewed annually, and the timing and final scope of this work modified in the coming years as appropriate. Exposed vertical control joint sealants and expansion joints in the facade should be scheduled for replacement, to prevent potential water infiltration and associated deteriorated to the adjacent brick and backup systems. To mitigate existing and future brick growth, joints exposed during replacement should also be routed to create a minimum 3/8” opening width. In conjunction with these efforts, isolated mortar and City of Iowa City Parking Garages 55 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 sealant joint repairs to cap stones at the perimeter of the roof level should be coordinated and performed. For additional discussion on the structural and waterproofing recommendations outlined above, refer to the applicable sections of Appendix C. Mechanical/Electrical/Plumbing The stair tower ventilation system should be returned to working order to provide summer ventilation based on temperature at the top of the stair tower. The chilled water pump frame will require annual inspections. The addition of a dehumidifier in the mechanical room is also recommended to help mitigate any further corrosion on the frame. The boiler flue and generator exhaust should be piped to the top of the garage and seven feet above the nearest parking deck surface, such that the installation complies with code requirements related to terminations of chimneys and vents. The remaining original boiler will need to be replaced within the next five years. This boiler is near the end of its life expectancy and the availability of replacement parts will likely become an issue. The new replacement boiler should match the other replaced boiler. With part of the existing underslab snow melt system already in failure, the entire underslab snow melt piping should be replaced. All five of the original variable frequency drives are near the end of their life expectancy and should be scheduled for replacement. While no issues were noted with the electrical distribution system, it is recommended that the City coordinate a complete maintenance action per the manufacturer’s recommendation on all equipment, including an IR scan to insure proper connections. City of Iowa City Parking Garages 56 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 The top deck exterior pole mounted lights are showing signs of age and should be replaced with new poles and more energy efficient LED fixtures. Replacement of the poles should include new control devices at the top of the pole. All of the existing fluorescent lights in the support spaces should be replaced with new LED light fixtures where applicable. The older exit lighting and exterior wall pack lights on the stair tower should similarly be scheduled for replacement with new LED based fixtures. Additional information on recommended testing frequencies in accordance with the National Fire Protection Association is included in Appendix D. City of Iowa City Parking Garages 57 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REPAIR AND MAINTENANCE MASTER PLAN THP has developed a 5-year (2020 through 2024) Repair and Maintenance Master Plan for structural, waterproofing, and MEP issues in the Tower Place Parking Ramp. The total opinion of probable cost for the full 5-year period is $600,000. A complete annual breakdown for the recommended scope of work for both Structural/Waterproofing and MEP efforts is included at the end of this report section. The Master Plan and its associated opinion of probable costs include an allowance for contractor overhead and profit, and all associated consulting fees. Opinion of probable costs reflect recently noted general increases for raw materials, shipping, etc. for similar THP administered efforts in the region. Opinion of probable costs have not been adjusted for inflation beyond 2020. Minor inflation over the life of the Master Plan should be accounted for within the available contingency funds. The conclusions and recommendations in this report are provided for repair/maintenance planning and budgeting purposes. This report is not intended to be used as a construction document. All findings and recommendations are based on conditions existing as of the date of the survey. It is important that the recommended repairs and maintenance are implemented in a timely manner. City of Iowa City Parking Garages 58 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Tower Place Street Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Annual Summary (Structural, Waterproofing, and MEP) Year Effort Opinion of Probable Cost(1)(2) 2020 Recommended Structural and Waterproofing Repairs ...............................$45,000 Recommended MEP Efforts .......................................................................$60,000 2020 Subtotal ..........$105,000 2021 Recommended Structural and Waterproofing Repairs .............................$135,000 Recommended MEP Efforts........................................................no efforts planned 2021 Subtotal ..........$135,000 2022 Recommended Structural and Waterproofing Repairs ...............no efforts planned Recommended MEP Efforts .....................................................................$250,000 2022 Subtotal ..........$250,000 2023 Recommended Structural and Waterproofing Repairs ...............................$55,000 Recommended MEP Efforts........................................................no efforts planned 2023 Subtotal ............$55,000 2024 Recommended Structural and Waterproofing Repairs ...............................$55,000 Recommended MEP Efforts........................................................no efforts planned 2024 Subtotal ............$55,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$600,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2)Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 59 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Tower Place Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Structural and Waterproofing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 (a) Stair tower vestibule leaking and membrane at adjacent floor areas........................................................................$40,000 (b) Contingency funds for annual garage maintenance (3)......................$5,000 2020 Subtotal ............$45,000 2021 (a) Concrete floor repairs and membrane patching.............................$25,000 (b) Expansion joint replacements and membrane strip recoating .......$70,000 (c) Stair tower waterproofing...............................................................$25,000 (d) Handrail embedment repairs............................................................$5,000 (e) Contingency funds for annual garage maintenance (3)....................$10,000 2021 Subtotal ..........$135,000 2022 no efforts planned 2023 (a) Façade expansion joint and control joint sealant replacement and miscellaneous repairs............................$40,000 (b) Contingency funds for annual garage maintenance (3)....................$10,000 2022 Subtotal ............$55,000 2024 (a) Façade expansion joint and control joint sealant replacement and miscellaneous repairs............................$20,000 (b) Lower level traffic membrane partial recoating ..............................$25,000 (c) Contingency funds for annual garage maintenance (3)....................$10,000 2024 Subtotal ............$55,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$290,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. (3) Contingency funds for annual inspections and unidentified scope or efforts associated with structural and waterproofing maintenance. City of Iowa City Parking Garages 60 of 99 Tower Place Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Tower Place Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Mechanical/Electrical/Plumbing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 (a) Repair stair tower ventilation..........................................................$15,000 (b) Relocate boiler flue ........................................................................$30,000 (c) Complete IR Scan and maintenance of electrical equipment ........$15,000 2020 Subtotal ............$60,000 2021 no efforts planned 2022 (a) Replace chilled water pumps.........................................................$50,000 (b) Replace 200MHB boiler.................................................................$85,000 (c) Replace snowmelt piping...............................................................$95,000 (d) Replace common area lighting fixtures..........................................$20,000 2023 Subtotal ..........$250,000 2023 no efforts planned 2024 no efforts planned TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$310,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 61 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 VI. CHAUNCEY SWAN RAMP DESCRIPTION Structural and Waterproofing The Chauncey Swan Ramp was designed by Neumann Monson, PC and constructed in 1993. The structural engineer of record was Rich and Associates. The garage includes approximately 475 parking spaces and is located west of Van Buren Street, between Washington Street and College Street. The structure consists of two and one half supported levels, and just less than 100,000 square feet of supported parking structure. The garage consists of two adjacent, 60-foot-wide bays, oriented in the north-south direction, with the east bay sloped to provide vehicular traffic between levels. The supported garage floors are not connected to the on-grade level, though all levels are accessible to pedestrian access from a stair tower located at the northwest corner of the garage, and a stair/elevator tower located at the southwest corner. Vehicular access to the supported floors of the garage is available from College Street on the south, while the on-grade parking is accessible from Washington Street to the north. The supported garage levels are comprised of 8-foot-wide, precast, prestressed concrete double tees with a nominal 3” thick bonded cast-in-place topping slab. Architectural precast concrete panels form the facade of the garage. Construction joints are located in the slab that mirror the joints between adjacent precast double tees below, with additional construction joints installed over precast support beams. There are approximately 6,500 linear feet of construction joints in the Chauncey Swan Ramp, with most joint sealed with urethane. A single expansion joint is located where the supported garage level intersects the adjacent street. The integral stair and elevator towers in the garage are typically comprised of steel framing with concrete-filled metal pan treads. Decorative precast and curtain wall facades adorn the enclosed stair towers. In recent years, modifications to the west facade have been performed to accommodate access to the new tower development located directly west of the property. City of Iowa City Parking Garages 62 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 MEP Systems The parking garage is naturally ventilated. Stair towers ventilation and heating utilizes exhaust fans located at the top of the stair tower, with makeup air louvers installed at the base. Heating is provided via electric unit heaters. The elevator machine room is equipped with a small packaged air-conditioning unit, to maintain appropriate conditions for the elevator controller. The stair towers are equipped with manual standpipes, and the parking decks are not suppressed. Existing drainage for the parking decks is piped to the City or municipality storm sewer systems. The facility is served from a utility company pad mount transformer and has a main electric service room towards the northwest part of the garage. The garage has a 400- amp 480/277 volt main panel board. All of the electrical distribution equipment is installed in NEMA 3R enclosures along an exterior wall of a stairwell in the garage. A majority of the electrical distribution equipment appears to be from the original installation of the facility. The parking area is lit by LED fixtures, with some fixtures equipped with a combination photocell and motion sensor for control. The top deck is outfitted with original poles and high-pressure sodium fixtures. The stairwell well lighting is provided by fluorescent fixtures. Exit signage are compact fluorescent fixtures with some exterior housings. The garage has a Simplex 4002 fire alarm system installed. There are smoke detectors located in the elevator lobbies. Limited fire alarm audio visual devices are located in the stairwells or elevator lobbies. Recent Repair and Maintenance Efforts THP has designed and coordinated several structural and waterproofing repair efforts in recent years as part of annual maintenance efforts. These efforts included replacement of exposed level urethane joint sealants and repair of the entrance bridge from College Street, including floor, soffit and beam repairs and a new expansion joint seal. The two stair tower interiors have been renovated with new finishes and traffic coatings on the exposed steps and landings. City of Iowa City Parking Garages 63 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REVIEW AND FINDINGS Precast Concrete Tees The cast-in-place topping slab of the Chauncey Swan Ramp has isolated locations of minimal cracking, spalling, or other deterioration. THP performed a chain drag survey of all crossovers throughout the garage, and estimates less than 50 square feet of delaminated floor repairs, with no visible spalls. The soffits of the precast double tees were in good overall condition. Cracking between the tee flange and stem were noted at isolated locations throughout the garage, often with visible efflorescence leaching through the crack (refer to Photo 01, included at the end of this section). No significant spalls or deterioration were noted at precast tee stem bearings. However, several bearing pads between the tee stem and support structure are below the roof level, similar to conditions noted by THP in 2012. Bearing pads elsewhere in the structure continue to exhibit little-to-no visible movement or rotation. Chloride Testing of Concrete Powder Samples A test program was performed to determine the extent of chloride contamination throughout the exposed levels of the Chauncey Swan Ramp. A total of 6 samples were taken from 3 different locations in 1” depth increments, at the 0”-1” and 1” to 2” depths. Floor locations were selected with a mix between drive lane and parking areas. Concentrations of between 1.3 to 1.9 lbs. of acid soluble chloride ions per cubic yard of concrete are normally considered the threshold level above which corrosion of embedded reinforcing steel will occur, given sufficient exposure to moisture and oxygen. Samples in the top 1” depth of slab typically indicate higher chloride content, since this depth is directly exposed to all road salt trafficked in by vehicles. Lightly reinforced mesh topping slabs, such as those throughout the Chauncey Swan Ramp, can typically absorb higher chloride rates than those listed above without significant corrosion problems. City of Iowa City Parking Garages 64 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Average chloride content in the garage was 13.00 lbs./CY for the 0-1” depth and 3.04 lbs/CY for the 1” to 2” depth. These limited readings are trending higher than the results from 2012 at both depths, by approximately 50% in each instance. Refer to Appendix A for a breakdown of the chloride data and a copy of the chloride sampling laboratory report from CTL Group. Sealants and Membrane Systems No significant issues were noted with sealants below the top level, which were replaced in recent years as part of annual garage maintenance projects. Isolated locations of failed and partially leaking tee joints were noted (Photo 02). Shear connections at all joints appeared to be substantially intact, with little discernible differential movement of adjacent joints under wheel load. Isolated membrane strips installed over crossovers have visible signs of wear, often to bare concrete (Photo 03). Connector Bridge to Street Level The connector bridge between the garage and College Street was substantially restored several years ago as part of annual garage maintenance project. Visible hairline cracking and minor spalls exist at sealant joints in the new topping slab over the bridge (Photo 04), though THP’s sounding survey indicated no significant concrete delaminations or repairs. The expansion joint at the intersection with the elevated road structure had minor visible tears and deterioration (Photo 05). Isolated soffit spalling and beam deterioration was noted below the bridge. Spandrel Panels Supplemental wall top handrails are installed on top of the precast façade panels at the roof level. The majority of these steel elements have visible minor corrosion at isolated areas of chipped or loose paint. THP also noted isolated spandrel panel lateral connections to adjacent columns with missing nuts at threaded rods (Photo 06). Stair and Elevator Towers While the stair and elevator towers interior finishes were recently replaced, ongoing isolated water infiltration continues to create issues. Minor bubbling and deterioration of City of Iowa City Parking Garages 65 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 finishes was noted at isolated locations, though at least some of these issues may be attributed to condensation in the stair towers resulting from poor ventilation – refer to the Mechanical/Electrical/Plumbing section for additional discussion. The existing tread/riser and stair framing elements had no significant issues. The exposed landings and tread risers were recently coated with a pedestrian traffic coating in conjunction with other interior work in the stair towers. The stair tower curtain wall had visible deterioration at the door, near the weather stripping (Photo 07), as well as split isolation sealant joints at the interface between the garage floor and stair tower facade (Photo 08). Mechanical/Electrical/Plumbing The manual standpipe system had some apparent corrosion of the exposed painted piping. Insulation on the storm drain piping was noted to be damaged in multiple locations. The stair tower ventilation system did not appear to be operational. The temperature within the stair towers was elevated well above ambient. The existing electric unit heaters and elevator machine room AC unit appeared to be functional. The electrical distribution equipment has no significant issues, but corrosion and rust was visible on equipment enclosures. The top deck light poles have signs of visible, though minor, corrosion. No issues were noted with the light pole fixtures, which are less efficient high-pressure sodium high-intensity discharge (HID) lamps. No significant issues were noted with the interior garage lighting or stair tower fixtures. Exit signage fixtures are showing signs aging with yellowing, hard-to-read lenses. No issues were noted with the garage fire alarm system, smoke detectors, or Isolated fire alarm audio visual devices. City of Iowa City Parking Garages 66 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Chauncey Swan Photo 01 Visible flange/stem cracking and efflorescence. Chauncey Swan Photo 02 Isolated leaking below precast joint. Chauncey Swan Photo 03 Isolated failed traffic coating. Chauncey Swan Photo 04 Visible cracking and joint edge deterioration in connector bridge slab. City of Iowa City Parking Garages 67 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Chauncey Swan Photo 05 Minor wing seal damage at connector bridge. Chauncey Swan Photo 06 Missing nut on spandrel panel threaded rod connection. Chauncey Swan Photo 07 Deteriorated weather stripping at base of stair tower door. Chauncey Swan Photo 08 Split and failed sealant around stair tower interface. City of Iowa City Parking Garages 68 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 RECOMMENDATIONS Structural and Waterproofing While no significant items were noted in the Chauncey Swan Ramp, several issues should be addressed over the next several years. The entrance connector bridge from College Street should have minor repairs at construction joints, along with new sealants and repair of the adjacent wing compression seal. In conjunction with this work, isolated soffit and beam repairs below the bridge should be performed. Following these repairs, to provide additional long-term durability, the surface of the connector bridge should be coated with a fast-curing poly methyl methacrylate (PMMA) traffic coating. While expensive, this type of coating would allow quick turnaround of the entrance bridge and provide better long-term durability with less frequent maintenance compared to a more traditional epoxy or urethane-based traffic coating system. Isolated leaks at the stair tower should continue to be addressed, either through warranties for the recent work (where applicable) or as part of annual maintenance. These efforts should include repairs to the storefront curtainwall system and door weather stripping, and isolation joint surrounding the perimeter of the towers. Isolated floor repairs throughout the garage should be repaired, and select cracks at precast tee stem and flange interfaces should be epoxy injected to re-establish integrity of the structure. Isolated leaks at precast joints should be repaired on an annual basis. Miscellaneous issues, such as the missing hardware for the spandrel panel connections, should be replaced or repaired as appropriate. Given the anticipated increased traffic from the adjacent tower construction, it is prudent to plan on full replacement of the top level sealants within a five year period, along with replacement of a nominal amount – approximately 25% – of interior level sealants. In conjunction with these efforts, it is recommended to recoat existing isolated traffic membrane installations throughout the facility, and install new traffic membrane strips over tee joints in the flat western bay of the garage, similar to what has recently been implemented in the Capitol Street Ramp. City of Iowa City Parking Garages 69 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 For additional discussion on the structural and waterproofing recommendations outlined above, refer to the applicable sections of Appendix C. Mechanical/Electrical/Plumbing The stair tower ventilation system should be returned to working order to provide summer ventilation based on temperature at the top of the stair tower. Following the renovation of the stair tower ventilation, any remaining condensation effects can be assessed, and recommendations incorporated into annual maintenance projects. The damaged sections of insulation on storm drain piping should be replaced. These sections of piping are in areas of the parking garage that are not protected from the elements above, which could result in additional damage from annual freeze/thaw cycles. Future insulation should be protected by PVC or metal jacketing. The electrical distribution system shows signs of deterioration and is reaching the end of its life expectancy according to industry standards. It is recommended that the City coordinate a complete maintenance action on all equipment per the manufacturer’s recommendation, including an IR scan to insure proper connections. While not part of this Master Plan, the city should be budgeting money for the likely replacement of the equipment within the next ten years. The top deck exterior pole mounted lights are showing signs of age and should be replaced with new poles and more energy efficient LED fixtures. Replacement of the poles should include new control devices at the top of the pole. All of the existing fluorescent lights and exit lighting in the support spaces should be replaced with new LED light fixtures where applicable. Installation of new audio/visual fire alarm devices in the elevator lobbies, stairwells and other employee or public spaces should be evaluated. Other garages managed by the City have similar devices in these areas. Additional information on recommended testing frequencies in accordance with the National Fire Protection Association is included in Appendix D. City of Iowa City Parking Garages 70 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REPAIR AND MAINTENANCE MASTER PLAN THP has developed a 5-year (2020 through 2024) Repair and Maintenance Master Plan for structural, waterproofing, and MEP issues in the Chauncey Swan Parking Ramp. The total opinion of probable cost for the full 5-year period is $345,000. A complete annual breakdown for the recommended scope of work for both Structural/Waterproofing and MEP efforts is included at the end of this report section. The Master Plan and its associated opinion of probable costs include an allowance for contractor overhead and profit, and all associated consulting fees. Opinion of probable costs reflect recently noted general increases for raw materials, shipping, etc. for similar THP administered efforts in the region. Opinion of probable costs have not been adjusted for inflation beyond 2020. Minor inflation over the life of the Master Plan should be accounted for within the available contingency funds. The conclusions and recommendations in this report are provided for repair/maintenance planning and budgeting purposes. This report is not intended to be used as a construction document. All findings and recommendations are based on conditions existing as of the date of the survey. It is important that the recommended repairs and maintenance are implemented in a timely manner. City of Iowa City Parking Garages 71 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Chauncey Swan Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Annual Summary (Structural, Waterproofing, and MEP) Year Effort Opinion of Probable Cost(1)(2) 2020 Recommended Structural and Waterproofing Repairs ...............no efforts planned Recommended MEP Efforts .......................................................................$40,000 2020 Subtotal ............$40,000 2021 Recommended Structural and Waterproofing Repairs ...............................$10,000 Recommended MEP Efforts........................................................no efforts planned 2021 Subtotal ............$10,000 2022 Recommended Structural and Waterproofing Repairs ...............................$75,000 Recommended MEP Efforts........................................................no efforts planned 2022 Subtotal ............$75,000 2023 Recommended Structural and Waterproofing Repairs ...............no efforts planned Recommended MEP Efforts .......................................................................$75,000 2023 Subtotal ............$75,000 2024 Recommended Structural and Waterproofing Repairs .............................$145,000 Recommended MEP Efforts........................................................no efforts planned 2024 Subtotal ..........$145,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$345,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2)Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 72 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Chauncey Swan Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Structural and Waterproofing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 no efforts planned 2021 (a) Isolated garage, spandrel, and stair tower repairs...........................$5,000 (b) Contingency funds for annual garage maintenance (3)......................$5,000 2021 Subtotal ............$10,000 2022 (a) Concrete floor repairs.....................................................................$10,000 (b) Epoxy injection of stem/flange cracks in precast .............................$5,000 (c) Entrance ramp soffit and floor repairs and waterproofing..............$50,000 (d) Contingency funds for annual garage maintenance (3)....................$10,000 2022 Subtotal ............$75,000 2023 no efforts planned 2024 (a) Sealant replacement and membrane strip installations at exposed top level.....................................................................$125,000 (b) Contingency funds for annual garage maintenance (3)....................$20,000 2024 Subtotal ..........$145,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$230,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. (3) Contingency funds for annual inspections and unidentified scope or efforts associated with structural and waterproofing maintenance. City of Iowa City Parking Garages 73 of 99 Chauncey Swan Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Chauncey Swan Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Mechanical/Electrical/Plumbing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 (a) Repair stair tower ventilation..........................................................$25,000 (b) Complete IR Scan and maintenance of electrical equipment ........$15,000 2020 Subtotal ............$40,000 2021 no efforts planned 2022 no efforts planned 2023 (a) Replace top deck lighting and poles ..............................................$40,000 (b) Replace common area lighting fixtures..........................................$20,000 (c) Repair storm drain insulation .........................................................$15,000 2023 Subtotal ............$75,000 2024 no efforts planned TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$115,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 74 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 VII. COURT STREET TRANSPORTATION CENTER DESCRIPTION Structure and Waterproofing The Court Street Transportation Center was designed by OPN Architects Incorporated and constructed in 2003 and 2004. The structural engineer of record was Desman Associates. The garage is located west of Dubuque Street, between Burlington Street (to the north) and Court Street (to the south). The garage includes retail and business space located in the on-grade east bay. The structure consists of five supported levels totaling approximately 600 parking spaces, with over 180,000 square feet of supported parking structure. The garage consists of two adjacent, 60 foot wide bays, oriented in the north-south direction, with the west bay sloped to provide vehicular traffic between levels. Vehicular access to the garage is provided from Dubuque Street and Court Street. The supported levels of the garage are a post-tensioned concrete structure. The original construction drawings indicate the typical slab is nominally 6” thick, and spans to post- tensioned support beams located at 24 feet on center, which are in turn supported from cast-in-place columns. Slabs are reinforced with 7 strand, ½” diameter, 270k strand tendons wrapped in extruded polyurethane sheathing. The location and profile of the tendons varies within the slab depth, typically between 1-1/4” to 2” from the bottom of the slab at mid-span to approximately 2-1/4” from the top of the slab over support beams. This designed tendon drape within the slab allows the structure to maximize the beneficial compressive stresses imparted by the tendons – upward forces from tendons at mid-span regions, and downward forces from tendons over support beams. Tendons are anchored and stressed from either end of the garage, with supplemental anchorage at interior construction joints in the slab. All non-post tensioning tendon reinforcement in the slabs and beams were specified to be epoxy coated. City of Iowa City Parking Garages 75 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 No expansion joints exist in the garage. Construction joints between adjacent slab pours are typically sealed with urethane. No sealant is typically installed along interfaces with vertical projections. A sacrificial topping slab with buried waterproofing is located over the on-grade retail and business spaces. The garage includes two isolated, enclosed stair and elevator towers at the northeast and southeast corners. Stair construction is typically comprised of precast treads and risers. The facade of the Transportation Center is composed of precast panels with decorative brick fascia. The façade panels are typically offset almost 2” from the adjacent slab, creating a horizontal opening around the perimeter of the garage at each supported level. Decorative steel elements adorn the façade openings on the north, south and east sides, while the majority of the west facade is infilled with precast from grade to allow the garage to abut future construction on the same block. In recent years, modifications to the west façade have been performed to accommodate vehicular and pedestrian access points to the new hotel development located directly west of the property. MEP Systems The parking garage is naturally ventilated. Stair towers are ventilated and heated by utilizing exhaust fans installed at the top of the stair tower with make–up air louvers located at the base. Heating is provided via electric unit heaters. The stair towers are equipped with manual standpipes, while the parking deck itself is not fire-suppressed. Existing drainage for the parking decks utilizes the City or municipality storm sewer systems. The parking areas is equipped with drainable hose bibs for garage wash purposes. Tenant spaces within the facility have mechanical and electrical rooms located adjacent to the garage floors, and use the parking area as their means of access to these spaces. This facility is served from a utility company pad mount transformer and multiple electric services are located in a main electric room towards the northwest part of the garage. City of Iowa City Parking Garages 76 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 The garage has a 2000 amp 480/277 volt, 3-phase, 4-wire main switchboard with multiple separately metered switchboards to serve the tenant spaces. All of the electrical distribution equipment is from the original installation of the facility. The parking area is lit by LED fixtures, with some fixtures equipped with a combination photocell and motion sensor for control. The top deck is outfitted with original poles and metal-halide fixtures, with no apparent grounding to a lightning protection system. The majority of the support spaces have light fixtures with T8 fluorescent lamps. The stairwell lighting includes newer LED based fixtures on both the interior and exterior. The fixtures are in good condition and provide adequate lighting. Exit signage are a mixed system, with some incandescent and some compact fluorescent-based fixtures. The garage has a Simplex 4010 fire alarm system installed that was inspected and serviced on 3/1/2019. There are smoke detectors located in the elevator lobbies. There are limited fire alarm audio visual devices in the common areas. City of Iowa City Parking Garages 77 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REVIEW AND FINDINGS Concrete Floor Slabs No significant issues were noted with the post-tensioned floor slabs throughout the Transportation Center. No grease spotting was noted in the soffits, which can be indicative of damaged tendon sheathing. Sealants Sealants throughout the construction joints of the garage are in varied states of serviceability. Sealants on the exposed top level showed typical cracking and crazing due to UV exposure, and are nearing the end of its useful life (refer to Photo 01, included at the end of this section). Garage Facade At the south side of the exposed top level, a damaged spandrel panel was noted with a spalled lateral connection clip near midspan (Photo 02) and a broken barrier cable (Photo 03). This damage reportedly happened as a result of snow removal efforts. No issues were noted with the bearing connections and remaining lateral clips for the panel. The ornamental steel facade elements around the perimeter of the garage were noted to have isolated areas of chipped and peeling paint, with minor surface corrosion visible at several locations (Photo 04). Several of the clip connections for the facade panels have hard shims for construction tolerance. At isolated locations, these shim stacks have shifted or moved (Photo 05). Isolated holes were noted in the brick facade panels at the southeast corner of the facility (Photo 06), presumably at abandoned fixtures or signage. Stair and Elevator Towers No significant issues were noted with the concrete stair towers. Minor isolated cracking, edge deterioration, and rail post embedment deterioration was noted at several locations throughout both towers, though these issues were more pronounced in the northeast stair. City of Iowa City Parking Garages 78 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 An isolation joint exists at the interface between the stair towers and the garage slab that is sealed with silicone. Exposed level isolation joint sealants on the roof level are typically wearing due to UV exposure Mechanical/Electrical/Plumbing No issues were noted with the manual standpipe. Insulation on the storm drain piping was noted to be damaged at isolated locations, mostly evident at the ground level. This damage appears to be the result of roosting and perching birds. The stair tower ventilation system did not appear to be operational. The temperature within the stair towers was elevated well above ambient. The existing electric unit heaters and elevator machine room AC unit appeared to be functional. A cursory walk through the existing tenant HVAC spaces was performed. Several of the pieces of combustion equipment, specifically HW boilers, appear to be drawing combustion air from the enclosed garage. If accurate, this condition is not compliant with the building code. The building code requires that combustion air not be drawn from spaces or sources which could contain combustible fumes or vapors, such as cars parked immediately adjacent to the intake locations. During the walkthrough, air handling unit AH-2 appeared to be out of operation and in the middle of being serviced. The electrical distribution equipment has no significant issues. The top deck light poles have signs of visible, though minor, corrosion. No issues were noted with the metal halide pole fixtures. No significant issues were noted with the interior garage lighting or stair tower fixtures, except for one fixture near the exit that appeared to have some LED modules not operating. Support space fixtures are aged with discolored or missing lenses and guards. Exit signage fixtures are showing signs aging with yellowing, hard- to-read lenses. No issues were noted with the garage fire alarm system, smoke detectors, or Isolated fire alarm audio visual devices. City of Iowa City Parking Garages 79 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Court Street Photo 01 Typical exposed level construction joint sealant. Court Street Photo 02 Spalled clip connection at damaged facade panel. Court Street Photo 03 Broken barrier cable at damaged facade panel. Court Street Photo 04 Isolated peeling and corroding steel facade elements. City of Iowa City Parking Garages 80 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Court Street Photo 05 Shifted shim plates at garage facade lateral connection. Court Street Photo 06 Open hole in brick facade. City of Iowa City Parking Garages 81 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 RECOMMENDATIONS Structural and Waterproofing Replacement of construction joint sealants throughout the facility is recommended, starting with exposed level sealants deteriorating due to UV exposure. During this work, it also recommended to install urethane traffic membrane strips along these joints to provide additional protection to intermediate tendon anchorages. Sealant replacement and maintenance throughout the Level 2 topping slab over occupied space should be coordinated and performed in conjunction with these efforts. The damaged spandrel panel lateral connection and broken barrier cable should be repaired within the next year, to ensure proper stability of the spandrel panel. Dumping of snow over the side of the panel should not be permitted until repairs can be performed. Isolated, phased cleaning and coating of corroding or deteriorating façade elements should be scheduled. Loose or shifted shims at façade connections should be reset. Minor isolated concrete repairs are recommended to the stairs, in particular at cracking and deterioration along stringer and step edges and at rail post embedments. While still predominantly intact and water tight, the isolation joint sealants between the stair towers and adjacent garage floors are beginning to soften and fail, and will likely require replacement over the course of the Master Plan. Because of the size of the opening, these joints should be replaced with a compressible expansion joint seal with a preformed silicone cap. For additional discussion on the structural and waterproofing recommendations outlined above, refer to the applicable sections of Appendix C. Mechanical/Electrical/Plumbing The stair tower ventilation system should be returned to working order to provide summer ventilation based on temperature at the top of the stair tower. City of Iowa City Parking Garages 82 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 The damaged sections of insulation on the ground level drain piping should be replaced and protected by PVC jacketing. Consideration should also be given to installation of netting or other bid-deterrent. The use of the air from the parking area as a source of combustion air for the tenant combustion equipment should be further evaluated and modified as appropriate. Air handling unit AH-2, serving a tenant space, should be reviewed and repair as required. While no issues were noted with the electrical distribution system, it is recommended that the City coordinate a complete maintenance action on all equipment per the manufacturer’s recommendation, including an IR scan to insure proper connections. The top deck exterior pole mounted lights are showing signs of age and should be replaced with new poles and more energy efficient LED fixtures. Replacement of the poles should include new control devices at the top of the pole. The non-operational LED modules in the fixture near the garage exist should be repaired. All of the existing fluorescent lights in the support spaces should be replaced with new LED light fixtures where applicable. It is also recommended that all of the exit signs be replaced with new LED based fixtures for energy savings. Common areas throughout the facility should be evaluated for additional fire alarm devices, similar to other garages managed by the City. Additional information on recommended testing frequencies in accordance with the National Fire Protection Association is included in Appendix D. City of Iowa City Parking Garages 83 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REPAIR AND MAINTENANCE MASTER PLAN THP has developed a 5-year (2020 through 2024) Repair and Maintenance Master Plan for structural, waterproofing, and MEP issues in the Court Street Transportation Center Parking Ramp. The total opinion of probable cost for the full 5-year period is $610,000. A complete annual breakdown for the recommended scope of work for both Structural/Waterproofing and MEP efforts is included at the end of this report section. The Master Plan and its associated opinion of probable costs include an allowance for contractor overhead and profit, and all associated consulting fees. Opinion of probable costs reflect recently noted general increases for raw materials, shipping, etc. for similar THP administered efforts in the region. Opinion of probable costs have not been adjusted for inflation beyond 2020. Minor inflation over the life of the Master Plan should be accounted for within the available contingency funds. The conclusions and recommendations in this report are provided for repair/maintenance planning and budgeting purposes. This report is not intended to be used as a construction document. All findings and recommendations are based on conditions existing as of the date of the survey. It is important that the recommended repairs and maintenance are implemented in a timely manner. City of Iowa City Parking Garages 84 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Court Street Transportation Center Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Annual Summary (Structural, Waterproofing, and MEP) Year Effort Opinion of Probable Cost(1)(2) 2020 Recommended Structural and Waterproofing Repairs .................................$5,000 Recommended MEP Efforts .......................................................................$40,000 2020 Subtotal ............$45,000 2021 Recommended Structural and Waterproofing Repairs ...............................$15,000 Recommended MEP Efforts........................................................no efforts planned 2021 Subtotal ............$15,000 2022 Recommended Structural and Waterproofing Repairs ...............................$65,000 Recommended MEP Efforts........................................................no efforts planned 2022 Subtotal ............$65,000 2023 Recommended Structural and Waterproofing Repairs ...............no efforts planned Recommended MEP Efforts .......................................................................$65,000 2023 Subtotal ............$65,000 2024 Recommended Structural and Waterproofing Repairs ...............................$10,000 Recommended MEP Efforts........................................................no efforts planned 2024 Subtotal ............$10,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$200,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2)Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 85 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Court Street Transportation Center Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Structural and Waterproofing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 (a) Repair of deteriorated spandrel panel..............................................$5,000 2020 Subtotal ..............$5,000 2021 (a) Clean and coat miscellaneous façade elements............................$10,000 (b) Contingency funds for annual garage maintenance (3)......................$5,000 2021 Subtotal ............$15,000 2022 (a) Construction joint sealant replacement and membrane strips.......$40,000 (b) Isolated stair tower repairs and waterproofing...............................$10,000 (c) Clean and coat miscellaneous façade elements............................$10,000 (d) Contingency funds for annual garage maintenance (3)......................$5,000 2022 Subtotal ............$65,000 2023 no efforts planned 2024 (a) Clean and coat miscellaneous façade elements..............................$5,000 (b) Contingency funds for annual garage maintenance (3)......................$5,000 2024 Subtotal ............$10,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .........................$95,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. (3) Contingency funds for annual inspections and unidentified scope or efforts associated with structural and waterproofing maintenance. City of Iowa City Parking Garages 86 of 99 Court Street Transportation Center Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Court Street Transportation Center Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Mechanical/Electrical/Plumbing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 (a) Repair stair tower ventilation..........................................................$15,000 (b) Repair AH-2 and tenant space combustion air ..............................$10,000 (c) Complete IR Scan and maintenance of electrical equipment ........$15,000 2020 Subtotal ............$40,000 2021 no efforts planned 2022 no efforts planned 2023 (a) Replace top deck lighting and poles ..............................................$40,000 (b) Replace common area lighting fixtures..........................................$15,000 (c) Repair storm drain insulation .........................................................$10,000 2023 Subtotal ............$65,000 2024 no efforts planned TOTAL OPINION OF PROBABLE COSTS (2020-2024) .......................$105,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 87 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 VIII. HARRISON STREET PARKING RAMP DESCRIPTION Structure and Waterproofing The Harrison Street Parking Ramp was designed by Neumann Monson Architects and constructed between 2016 and 2018. The structural engineer of record was Walker Parking Consultants. The garage is located at the southwest corner of East Harrison Street and South Dubuque Street, and bound by East Prentiss Street to the south. The east and south facades of the garage abut a row of single unit townhouses along South Dubuque Street and East Prentiss Street. These townhouses are privately developed and not maintained as part of the City infrastructure, and as such are excluded from this assessment. The structure consists of five supported levels totaling approximately 600 parking spaces, with over 160,000 square feet of supported parking structure. The garage consists of two adjacent, 60-foot-wide bays, oriented in the north-south direction, with both bays sloped to provide continuous vehicular traffic between levels. Vehicular access to the garage is provided from Harrison Street. The supported levels of the garage are a post-tensioned concrete structure. The original construction specifications indicate the typical slab is nominally 6” thick, and spans to post-tensioned support beams located at 24 feet on center, which are in turn supported from cast-in-place columns. Slabs are reinforced with 7 strand, ½” diameter, 270k tendons wrapped in extruded polyurethane sheathing. The location and profile of the tendons varies within the slab depth. This designed tendon drape within the slab allows the structure to maximize the beneficial compressive stresses imparted by the tendons – upward forces from tendons at mid-span regions, and downward forces from tendons over support beams. Tendons are anchored and stressed from either end of the garage, with supplemental anchorage at interior construction joints in the slab. All non-post tensioning tendon reinforcement in the slabs and beams were specified to be epoxy coated. City of Iowa City Parking Garages 88 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 A single wing compression expansion joint seal exists at the interface between the supported levels and the slab-on-grade construction. No expansion joints exist in the garage. Construction joints between adjacent slab pours are typically sealed with urethane and coated with a urethane traffic membrane strip. The garage includes two isolated, enclosed stair towers at the northwest and southwest corners, with an elevator in the northwest tower. Stair construction is typically comprised of concrete-filled metal pan steps supported by steel stringers and framing. A skybridge is located at the west side of Level 5, adjacent to the stair and elevator tower, which connects the garage to the adjacent MidWestOne Bank facility. The facade is composed of several different elements. Along the east and south facades, a concrete masonry block wall separates the garage and adjacent townhomes that were still under construction at the time of THP’s survey. An ornamental perforated metal panel façade is located over most of the north and east facades and is integral with exposed brick elements at the street level at the main garage entrance. The stair towers are enclosed in curtain wall, with integration of the ornamental metal panels in the northwest tower. MEP Systems The parking area is naturally ventilated except for the lowest level. The lowest level is equipped with mechanical ventilation which is tied into a carbon monoxide-nitrogen dioxide detection system. Stair towers are ventilation only, utilizing exhaust fans at the top of the stair tower with makeup air louvers near the bottom. The stair towers are equipped with manual standpipes, while the parking decks are not fire-suppressed except for the lowest level parking areas which is equipped with a dry pipe system. The electric room, IT/Tele room and the elevator machine room are all cooled by mini- split systems and heated by electric unit heaters. The maintenance garage is ventilated and heated by two electric unit heaters and an exhaust fan located on the top level. The maintenance garage contains a carbon monoxide-nitrogen dioxide detection system tied to an alarm. Controls are DDC. City of Iowa City Parking Garages 89 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 This facility is served from a utility company pad mount transformer and multiple electric services in a main electric room located in the lower level of the northwest corner of the garage. The garage has a 1200 amp, 208Y120 volt, 3-phase, 4-wire main fusible switchboard for the parking area. Each tenant is provided with separately metered panelboard at the transformer. The parking area is lit by LED fixtures, with some equipped with a combination photocell and motion sensor for control. The top deck is similarly outfitted with LED fixtures. The top deck light poles are grounded to a lightning protection system. All non-space fixtures are also LED based. The garage has a Notifier fire alarm system. Smoke detectors are located in the elevator lobbies. Fire alarm audio visual devices are located in the common areas. City of Iowa City Parking Garages 90 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REVIEW AND FINDINGS Garage Structural and Waterproofing No significant issues were noted with the post-tensioned floor slabs throughout the Harrison Street Ramp. Minor hairline cracking was noted at several slab areas, though no significant signs of water infiltration were visible on the soffits below. Similarly, the urethane traffic membrane installations at joints and other isolated locations had no apparent issues, as well as exposed sealants and the wing compression seal at grade. The garage is designed with open, full height snow pits and gates to allow for more efficient removal of snow from the exposed level of the garage. Spalls were noted at anchors of isolated gate locations (refer to Photo 01, included at the end of this section). In addition, visible corrosion was noted at scratches in the galvanized steel finish of the gates and frames surrounding the pits (Photo 02). Garage Facade The concrete masonry divider wall between the east and south facades and the townhome developments had no visible issues. However, there is an open joint at the interface of these walls with the garage floor slab, with regularly spaced clip angle connections to the floor slabs providing lateral support for the walls. Minor signs of water infiltration were noted below these open joints (Photo 03). No issues were noted with the ornamental metal panel facade elements. However, cracking was noted at a few isolated connections between the panels and the garage (Photo 04). Stair and Elevator Towers Isolated cracking was noted at several locations in the stair tower treads and landings. More critically, visible corrosion is already starting to develop on the exposed face of the metal risers, as well as several of the perforated metal panel elements which integrate into the northwest tower (Photo 05). City of Iowa City Parking Garages 91 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Minor splits and damage were noted at the base of the exposed level curtain wall surrounding the stair towers, likely from plows or cleaning equipment (Photo 06). Mechanical/Electrical/Plumbing The stair tower ventilation system did not appear to be operational. The temperature within the stair towers was elevated well above ambient. Many of the lighting fixtures in the lobby have bugs covering the lens, obscuring the light output and potentially creating a fire hazard. City of Iowa City Parking Garages 92 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Harrison Street Photo 01 Spalled snow gate connection. Harrison Street Photo 02 Typical minor surface corrosion on gate. Harrison Street Photo 03 Visible staining below open top level joint. Harrison Street Photo 04 Isolated spall at facade connection. City of Iowa City Parking Garages 93 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Harrison Street Photo 05 Visible corrosion at stair tower. Harrison Street Photo 06 Isolated split at base of stair tower curtain wall. City of Iowa City Parking Garages 94 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 RECOMMENDATIONS Structural and Waterproofing Visible cracking in the floor slabs will eventually require routing and sealing, beginning with the exposed level cracking and joints near the main vehicle entrance. While no issues were noted with the isolated traffic membrane strip installations, it is likely these elements will require some maintenance and repair within the next five years, followed by full recoat applications in within 10 years. It is recommended the City verify any existing warranties for this and all other garage maintenance items from the original construction which may be still in effect. The damaged connections for the snow gates and fencing should be repaired, and visible scrapes cleaned, prepped, and coated with a cold-galvanizing spray to provide the intended durability. It is likely these items will become a standard maintenance item for the facility, and should be identified and addressed on annual basis in early spring, following the substantial end of winter weather conditions. Cracking in the stair towers should be routed and sealed, and new sealant installed around the perimeter of the steps and landings to mitigate water infiltration into the metal pan supports. At least a portion of the visible surface corrosion throughout the tower appears to be partially related to lack of ventilation in the stair towers, creating a humid environment and condensation on exposed surfaces. Refer to the Mechanical/Electrical/Plumbing section for additional recommendations on stair tower ventilation. The damaged seals at the base of the curtain wall enclosing the stair towers should be repaired. To provide additional visual deterrent for plows and vehicles, flexible traffic delineators should be installed on the slabs in front of the towers. For additional discussion on the structural and waterproofing recommendations outlined above, refer to the applicable sections of Appendix C. City of Iowa City Parking Garages 95 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Mechanical/Electrical/Plumbing The stair tower ventilation system should be returned to working order to provide summer ventilation based on temperature at the top of the stair tower. Following the renovation of the stair tower ventilation, any remaining condensation effects can be assessed, and recommendations incorporated into annual maintenance projects. The common area fixtures should be cleaned of bugs to mitigate a potential fire hazard, then the lens sealed when the fixture is reattached. Additional information on recommended testing frequencies in accordance with the National Fire Protection Association is included in Appendix D. City of Iowa City Parking Garages 96 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 REPAIR AND MAINTENANCE MASTER PLAN THP has developed a 5-year (2020 through 2024) Repair and Maintenance Master Plan for structural, waterproofing, and MEP issues in the Harrison Street Parking Ramp. The total opinion of probable cost for the full 5-year period is $45,000. A complete annual breakdown for the recommended scope of work for both Structural/Waterproofing and MEP efforts is included at the end of this report section. The Master Plan and its associated opinion of probable costs include an allowance for contractor overhead and profit, and all associated consulting fees. Opinion of probable costs reflect recently noted general increases for raw materials, shipping, etc. for similar THP administered efforts in the region. Opinion of probable costs have not been adjusted for inflation beyond 2020. Minor inflation over the life of the Master Plan should be accounted for within the available contingency funds. The conclusions and recommendations in this report are provided for repair/maintenance planning and budgeting purposes. This report is not intended to be used as a construction document. All findings and recommendations are based on conditions existing as of the date of the survey. It is important that the recommended repairs and maintenance are implemented in a timely manner. City of Iowa City Parking Garages 97 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Harrison Street Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Annual Summary (Structural, Waterproofing, and MEP) Year Effort Opinion of Probable Cost(1)(2) 2020 Recommended Structural and Waterproofing Repairs ...............no efforts planned Recommended MEP Efforts .......................................................................$25,000 2020 Subtotal ............$25,000 2021 Recommended Structural and Waterproofing Repairs .................................$5,000 Recommended MEP Efforts........................................................no efforts planned 2021 Subtotal ..............$5,000 2022 Recommended Structural and Waterproofing Repairs .................................$5,000 Recommended MEP Efforts........................................................no efforts planned 2022 Subtotal ..............$5,000 2023 Recommended Structural and Waterproofing Repairs .................................$5,000 Recommended MEP Efforts........................................................no efforts planned 2023 Subtotal ..............$5,000 2024 Recommended Structural and Waterproofing Repairs .................................$5,000 Recommended MEP Efforts........................................................no efforts planned 2024 Subtotal ..............$5,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .........................$45,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2)Probable costs assume all garage work will be packaged and performed annually by a single contractor. City of Iowa City Parking Garages 98 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Harrison Street Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Structural and Waterproofing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 no efforts planned 2021 (a) Route and seal floor cracks and minor, miscellaneous efforts.........$5,000 2021 Subtotal ..............$5,000 2022 (a) Route and seal floor cracks and minor, miscellaneous efforts.........$5,000 2022 Subtotal ..............$5,000 2023 (a) Contingency funds for annual garage maintenance (3)....................$20,000 2023 Subtotal ..............$5,000 2024 (a) Contingency funds for annual garage maintenance (3)......................$5,000 2024 Subtotal ..............$5,000 TOTAL OPINION OF PROBABLE COSTS (2020-2024) .........................$20,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. (3) Contingency funds for annual inspections and unidentified scope or efforts associated with structural and waterproofing maintenance. City of Iowa City Parking Garages 99 of 99 Harrison Street Ramp Condition Assessment and THP Limited, Inc. Master Plan Report June, 2020 Harrison Street Parking Ramp Proposed Repair and Maintenance Master Plan, 2020-2024 Mechanical/Electrical/Plumbing Recommendations Year Effort Opinion of Probable Cost(1)(2) 2020 (a) Clean and seal common area light fixtures....................................$10,000 (b) Complete IR Scan and maintenance of electrical equipment ........$15,000 2020 Subtotal ............$25,000 2021 no efforts planned 2022 no efforts planned 2023 no efforts planned 2024 no efforts planned TOTAL OPINION OF PROBABLE COSTS (2020-2024) .........................$25,000 Notes:(1) Probable costs do not include an adjustment for inflation beyond 2020. Probable costs include allowances for Contractor general conditions and A/E fees. (2) Probable costs assume all garage work will be packaged and performed annually by a single contractor. APPENDIX A Parking Facility Chloride Testing Data Iowa City Garages Chloride Testing Data THP #19040.00 THP ID Facility Level Test Depth (wt%) (lbs/CY) 1A Dubuque 5 (Drivelane)0" - 1" 0.119 4.66 1B Dubuque 5 (Drivelane)1" - 2" 0.006 0.23 2A Dubuque 6 (Drivelane)0" - 1" 0.230 9.00 2B Dubuque 6 (Drivelane)1" - 2" 0.099 3.88 3A Dubuque 5 (Parking)0" - 1" 0.225 8.81 3B Dubuque 5 (Parking)1" - 2" 0.086 3.37 4A Capitol 4 (Parking)0" - 1" 0.011 0.43 4B Capitol 4 (Parking)1" - 2" 0.013 0.51 5A Capitol 5 (Drivelane)0" - 1" 0.024 0.94 5B Capitol 5 (Drivelane)1" - 2" 0.013 0.51 6A Capitol 5 (Drivelane)0" - 1" 0.026 1.02 6B Capitol 5 (Drivelane)1" - 2" 0.013 0.51 7A Tower Place 5 (Parking)0" - 1" 0.048 1.88 7B Tower Place 5 (Parking)1" - 2" 0.004 0.16 8A Tower Place 4 (Drivelane)0" - 1" 0.077 3.01 8b Tower Place 4 (Drivelane)1" - 2" 0.006 0.23 9A Tower Place 2 (Drivelane)0" - 1" 0.173 6.77 9B Tower Place 2 (Drivelane)1" - 2" 0.011 0.43 10A Chauncey Swan 3 (Parking)0" - 1" 0.169 6.62 10B Chauncey Swan 3 (Parking)1" - 2" 0.021 0.82 11A Chauncey Swan 3 (Drivelane)0" - 1" 0.591 23.14 11B Chauncey Swan 3 (Drivelane)1" - 2" 0.173 6.77 12A Chauncey Swan 2 (Drivelane)0" - 1" 0.236 9.24 12B Chauncey Swan 2 (Drivelane)1" - 2" 0.039 1.53 Note : Numbers in RED indicate chloride concentration levels capable of causing accelerated corrosion in reinforcing steel. Determined Cl Client:THP Limited, Inc.CTL Project No:400229 Project:A/S Chloride Testing CTL Project Mgr.:Sai Vaidya PO No. : 19110 Analyst:Kevin Arias Contact:Christopher A. Hauke Approved:Sai Vaidya Submitter:Christopher A. Hauke Date Analyzed:10-Jun-19 Date Received:10-Jun-19 Date Reported:11-Jun-19 REPORT of ACID-SOLUBLE CHLORIDE Determined Sample Identification Chloride CTL ID Client ID Description (wt% sample)(ppm Cl) 4920301 1A Concrete 0.119 1190 4920302 1B Concrete 0.006 60 4920303 2A Concrete 0.230 2300 4920304 2B Concrete 0.099 990 4920305 3A Concrete 0.225 2250 4920306 3B Concrete 0.086 860 4920307 4A Concrete 0.011 110 4920308 4B Concrete 0.013 130 4920309 5A Concrete 0.024 240 4920310 5B Concrete 0.013 130 4920311 6A Concrete 0.026 260 4920312 6B Concrete 0.013 130 4920313 7A Concrete 0.048 480 4920314 7B Concrete 0.004 40 4920315 8A Concrete 0.077 770 4920316 8B Concrete 0.006 60 4920317 9A Concrete 0.173 1730 4920318 9B Concrete 0.011 110 4920319 10A Concrete 0.169 1690 4920320 10B Concrete 0.021 210 4920321 11A Concrete 0.591 5910 4920322 11B Concrete 0.173 1730 4920323 12A Concrete 0.238 2380 4920324 12B Concrete 0.039 390 Notes: 1. This analysis represents specifically the samples submitted as received. 2. Analysis by potentiometric titration with silver nitrate. (ASTM C1152-04(2012)ᵉ¹) 3. This report may not be reproduced except in its entirety. QLT 40-027 Corporate Office and Laboratory: 5400 Old Orchard Road Skokie, Illinois 60077-1030 Page 1 of 1 Revision 4 400229_49203_01-24_AS_C1152_Chloride_1556.xlsx APPENDIX B Parking Facility Membrane Bond Test Data Iowa City Garages Membrane Bond Test Data THP #19040.00 Facility Level THP ID Pull Test (psi)Majority Failure Dubuque 4 BT1 339 Basecoat 4 BT2 134 Glue to Disc 3 BT3 276 Concrete 3 BT4 339 Concrete 3 BT5 197 Concrete 3 BT6 166 Concrete 4 BT7 181 Concrete Capitol 3 BT8 260 Concrete 3 BT9 166 Concrete 3 BT10 245 Concrete 2 BT11 181 Concrete 2 BT12 166 Glue to Disc 2 BT13 197 Concrete Tower Place 2A BT14 197 Concrete 1B BT15 260 Concrete APPENDIX C Discussion of Typical Parking Garage Issues City of Iowa City Parking Garages 1 of 6 THP Limited, Inc. Appendix C October, 2019 DISCUSSION OF TYPICAL PARKING GARAGE ISSUES I. Salt-Induced Corrosion in Reinforced Concrete Structures Garage Applicability – All Structures Over fifty years ago, state highway departments in the northern United States adopted policies of “bare-pavement” winter roadway maintenance. These policies led to the use of vast quantities of deicer salts. Toward the end of the 1960’s a significant increase in the rate of deterioration of highway structures was noted. In the late 1970’s it became generally recognized that this increased deterioration was due to corrosion of embedded reinforcement accelerated by the presence of chloride, which is the major chemical component in deicer salts. In the late 1970’s, it also became generally recognized that parking structures in the northern United Sates were suffering from the same symptoms as highway structures. It is difficult to overstate the severity of salt-induced corrosive deterioration on reinforced concrete structures. On the national level, its destruction of both public and private infrastructure has been estimated as high as $5 billion per year. The process of salt-induced concrete deterioration begins when vehicles track in salt laden slush. The slush melts into saltwater that drips onto the deck and is absorbed into the concrete. When salt dissolves in water, chloride ions are liberated. These ions lower an otherwise high pH concrete matrix, which provides a natural passivity to embedded reinforcing steel. A pH of greater than 11.5 is believed to stabilize the protective film on the embedded steel. Once the pH drops below this value the natural passivity, or protective film, is destroyed and corrosion can be supported and sustained. Steel reinforcing embedded in concrete will, after a period of time, be completely surrounded with a thin film of oxide compounds. This thin film serves as a protective barrier between the steel and oxygen-bearing moisture which penetrates the concrete through cracks and pores in the concrete surface. As long as the oxide barrier remains intact, the steel is protected from corroding. City of Iowa City Parking Garages 2 of 6 THP Limited, Inc. Appendix C October, 2019 Concrete is normally an alkaline material which is responsible for the maintenance of the protective oxide film. The stability of the oxide film is upset, however, by the presence of negatively charged chloride ions. Both sodium chloride and calcium chloride deicing agents ionize in water, releasing over 60 percent of their weight as chloride ions. These highly reactive ions lower the pH (reduce the alkalinity) of concrete and eventually compromise the iron-oxide film surrounding the embedded steel reinforcing. The compromised oxide film allows the detrimental corrosion process to begin if the steel is exposed to oxygen and moisture. Research has shown that a certain “threshold” concentration of chloride ions will support the corrosion process and cause it to continue at approximately the same rate regardless of higher chloride ion concentrations. Once the concentration of chloride ions is over the threshold level, the amount of oxygen-bearing water at the level of the steel reinforcement influences the corrosion rate. Since time is required for the ions and moisture to penetrate the overlaying concrete, the depth of steel reinforcement cover, the permeability of the concrete, and the presence of a water seal on the surface of the concrete are critical factors, among others, in establishing the time before the corrosion process begins, and the rate of the corrosion process once it has commenced. Before steel can corrode, positive iron ions must leave the surface of the steel. These iron ions then normally combine with negative oxygen ions in the local environment of the steel reinforcement. Since these iron ions are actually positively charged atoms, their ability to leave the parent metal requires the material surrounding the steel bar to be a conductor of electrical charge. Salt dissolved in water is a far superior conductor of electric charge than water alone. This electrolytic solution, or electrolyte, does act in surrounding the steel reinforcement in salt-contaminated concrete and greatly enhances the flow of iron ions from the reinforcement after the passive oxide film has been removed. The iron-oxide (rust) that is produced as a result of the exposure of the steel to oxygen-bearing moisture has a much larger volume than the parent metal. As a steel reinforcement bar rusts, its volume increases by over a factor of six. This expansion produces large internal splitting stresses in the concrete. In the case of City of Iowa City Parking Garages 3 of 6 THP Limited, Inc. Appendix C October, 2019 a reinforced concrete slab where the steel reinforcement is in layers below the surface of the concrete, this pressure from expanding rust first splits the concrete above the rebar away from the concrete below the rebar. This action is termed a “delamination.” At the initial stages it may or may not be visible from the surface. At this stage, however, the concrete ceases to be a coherent mass, and the bond between the concrete and steel reinforcement (which is structurally critical) is lost. Continued internal pressure will eventually crack the concrete through to the surface, resulting in a “spall”. The Progressive Steps of Chloride-induced Corrosion (ref. Figure 1): 1. Application of salt deicing compounds either by direct application to the structure or by indirect application from melt water and slush carried onto the structure by vehicles. 2. Absorption of the ionized chloride and water into the concrete through cracks and surface pores, and penetration to the level of the reinforcing steel. 3. Lowering of the pH of the concrete in the vicinity of the reinforcing steel and compromising of the protective oxide layer around the steel. 4. Increase of the electrical conductivity of the concrete in the vicinity of the reinforcing steel. 5. Electrochemical corrosion of the now unprotected steel in the presence of water, oxygen, and a conductive electrolyte creating a complex of iron- oxide corrosion products (rust). 6. Expansion of the reinforcing steel due to the formation of rust and the creation of internal pressures. 7. Internal splitting or “delamination” of the concrete. 8. The separation reaches the surface and a “spall” is created. 9. The spall is removed by the action of traffic and the pressure of entrapped freezing water. 10. Continuation of the process with continued exposure of the structure to moisture. 11. Eventual loss of reinforcing steel bond to the concrete, reduction of usable steel area, and loss of concrete cross-sectional area until the reinforced concrete loses its structural integrity. City of Iowa City Parking Garages 4 of 6 THP Limited, Inc. Appendix C October, 2019 City of Iowa City Parking Garages 5 of 6 THP Limited, Inc. Appendix C October, 2019 II. Slab Tendons in Post-Tensioned Concrete Structures Garage Applicability – Dubuque (Levels 1 through 5), Tower, Transportation Center, and Harrison In Post-Tensioned Concrete Structures, the primary floor slab reinforcement are highly stressed tendons composed of multiple high-strength steel wires, with typically seven or more wires per each tendon. These tendons are installed in the slab prior to the concrete being placed. After the concrete slabs harden, these tendons are pulled and stretched with hydraulic jacks to very high stress levels and then locked-off at anchorages. The term “post-tensioning” refers to jacking or tensioning of these embedded steel tendons, after the concrete is cast, to produce a beneficial compressive stress in the concrete. Due to the high stresses in the tendons resulting from the post-tensioning process, great energy is released when tendons break, analogous to breaking a stretched rubber band. Because of their highly stressed state, tendons can undergo very little corrosion before breaking. After breaking, a tendon’s structural value can be lost throughout its entire length between anchorage locations, leading to potentially costly structural repairs. As a result, protection of tendons, especially at anchorage locations, is critical. To facilitate the tendon stressing in the hardened concrete slabs, tendons are greased and encased in a protective sheathing. By the early 1980’s, the durability of post-tensioning construction improved to typically include extruded plastic sheathing of tendons, which provides more protection than the older plastic sheathing with heat welded seams. In many older post tensioned structures, protective sheathing at cable ends and intermediate construction joints often stopped short of anchorage hardware, exposing short (1/2” to 2”) tendon lengths to migrating moisture and chlorides. Issues from this condition will typically begin to manifest as visible grease staining on soffits below and, if left unaddressed, can lead to long-term corrosion and failure of the tendons at these locations. City of Iowa City Parking Garages 6 of 6 THP Limited, Inc. Appendix C October, 2019 III. Lateral Stability and Movement in Parking Garages Garage Applicability – Dubuque (Levels 6 and 7), Capitol, and Chauncey In all structures, lateral loads are transferred through the individual levels, into lateral restraining elements (such as shear walls) and finally to the foundation. Lateral loads are result of movements related to thermal loads, wind loads, seismic loads, and loads imparted to the structure through vehicular acceleration and breaking. Precast concrete parking structures are constructed of numerous elements, typically linked together by steel connections and end bearings. In this type of flexible construction, transferring lateral loads at each level though these steel connections and bearings can cause minor movements and rotations of the precast elements. Over time, the accumulative effect of these movements creates stresses which can result in cracks and spalls, mostly at bearing locations adjacent to expansion joints where some allowance for movement is intended, and points of restraint, such as shear walls, stair towers, connector bridges, and vehicle crossovers between adjacent garage bays. For these types of structures, it is recommended to maintain a program to survey the precast elements once annually for signs of cracking, bearing deterioration and distress. This survey should be performed in early spring after the decks begin to expand following the cold winter months. Along with this survey, minor concrete knockdowns and repairs to soffits and tee stem bearings should be a typical, annually budgeted maintenance item. APPENDIX D NFPA Recommended System Testing Frequencies City of Iowa City Parking Garages 1 of 6 THP Limited, Inc. Appendix D October, 2019 NATIONAL FIRE PROTECTION ASSOCIATION RECOMMENDED SYSTEM TESTING FREQUENCIES NFPA 70B Table L.1 Interval Guidelines Item/Equipment Task/Function Interval Reference Visual inspection/clean 3 years 17.7 through 17.11 Molded-Case Circuit Breakers    Mechanical test 2 years 17.11 Electrical test 3–5 years 11.10.5 17.7 Types of Maintenance. Maintenance of insulated-case/molded-case circuit breakers generally can be divided into two categories: mechanical and electrical. Mechanical maintenance consists of inspection involving good housekeeping, maintenance of proper mechanical mounting and electrical connections, and manual operation as outlined in Sections 17.8 through 17.10. Electrical testing under field test conditions is covered in 11.10.2. 17.8 Inspection and Cleaning. Insulated-case/molded-case circuit breakers should be kept clean of external contamination so that internal heat can be dissipated normally. Further, a clean case reduces potential arcing conditions between live conductors and between live conductors and ground. The structural strength of the case is important in withstanding the stresses imposed during fault-current interruptions. Therefore, the case should be inspected for cracks and replaced if necessary. 17.9 Loose Connections. Excessive heat in a circuit breaker can cause a malfunction in the form of nuisance tripping and possibly an eventual failure. Loose connections are the most common cause of excessive heat. Periodic maintenance checks should involve checking for loose connections or evidence of overheating. Loose connections should be checked for tightness in accordance with Section 8.11. Insulated-case/molded-case circuit breakers having noninterchangeable trip units are properly adjusted, tightened, and sealed at the factory. Those having interchangeable trip units installed away from the factory could overheat if not tightened properly during installation. All connections should be maintained in accordance with manufacturers' recommendations. 17.10 Mechanical Mechanism Exercise. Devices with moving parts require periodic checkups, and an insulated-case/molded-case circuit breaker is no exception. Manual operation of the circuit breaker will help keep the contacts clean and will help the lubrication perform properly. Although manual operations will exercise the breaker mechanism, none of the mechanical linkages in the tripping mechanisms will be moved with this exercise. Some circuit breakers have push-to-trip buttons that should be manually operated to exercise the tripping mechanism linkages. (Refer to Annex K, Long-Term Maintenance Guidelines; Annex L, Maintenance Intervals; and ANSI/NETA MTS, Standard for Maintenance Testing Specifications for Electrical Power Distribution Equipment and Systems, for guidance on frequency of exercise as appropriate.) City of Iowa City Parking Garages 2 of 6 THP Limited, Inc. Appendix D October, 2019 17.11 Electrical Testing. For further information on testing see 11.10.5. 11.10.5 Insulated-Case/Molded-Case Circuit-Breaker Testing. When performing insulated-case/molded-case circuit-breaker testing, the criteria in 11.10.5.1 through 11.10.5.3 should be utilized. 11.10.5.1 Insulated-Case/Molded-Case Circuit Breakers — General. 11.10.5.1.1 Insulated-case/molded-case circuit breakers are available in a wide variety of sizes, shapes, and ratings. Voltage ratings up to 1000 volts ac or 1500 volts dc and current ratings up to 6000 amperes are available. Insulated- case/molded-case circuit breakers can be categorized generally by the types of trip units employed as described in Section 17.5. 11.10.5.1.2 Electrical testing should be performed in a manner and with the type of equipment required by the type of trip unit employed. 11.10.5.1.3 For further information on insulated-case/molded-case circuit breakers, see Chapter 17. 11.10.5.1.4 Insulation Resistance Tests. Measure insulation resistance tests for 1 minute on each pole, phase-to-phase and phase-to-ground, with the circuit breaker closed and across each open pole. Apply voltage in accordance with manufacturer’s published data. Insulation resistance values should be in accordance with manufacturer’s published data. For further information on insulation resistance testing see 11.9.2.3. 11.10.5.1.5 Contact/Pole Resistance or Millivolt Drop Tests. Measure contact/pole resistance or millivolt drop. These tests are used to test the quality of the contacts. The contact resistance or millivolt drop should be kept as low as possible to reduce power losses at the contacts with the resultant localized heating, which will shorten the life of both the contacts and nearby insulation. Microhm or millivolt drop values should not exceed the high levels of the normal range as indicated in the manufacturer’s published data. 11.10.5.2 Testing Thermal-Magnetic Trip Units. 11.10.5.2.1 The electrical testing of thermal-magnetic trip units in circuit breakers can be divided into three steps: (1) Overload of individual poles at 300 percent of trip rating (2) Verification of test procedures (3) Verification of manufacturer's published data City of Iowa City Parking Garages 3 of 6 THP Limited, Inc. Appendix D October, 2019 11.10.5.2.2 Complete and detailed instructions for testing insulated-case/molded-case circuit breakers in accordance with the steps in 11.10.5.2.1 are outlined in detail in NEMA AB 4, Guidelines for Inspection and Preventive Maintenance of Molded-Case Circuit Breakers Used in Commercial and Industrial Applications. Individual manufacturers also publish recommended testing procedures as well as time–current characteristic tripping curves. 11.10.5.2.3 When circuit-breaker tripping characteristics are tested, it is recommended that the inverse time trip (thermal or long time-delay element) tests be performed on individual poles at 300 percent of rated current. 11.10.5.2.4 The reaction of the circuit breaker to this overload is indicative of its reaction throughout its entire overcurrent tripping range. This load is chosen as the test point because it is relatively easy to generate the required current in the field, and the wattage per pole from line to load is large enough that the dissipation of heat in the nonactive pole spaces is minor and does not affect the test results appreciably. 11.10.5.2.5 Values for Inverse Time Trip (Thermal or Long Time-Delay Element) Data. Table 11.10.5.2.5 outlines the current and trip-time values as recommended by NEMA. The minimum/maximum range of values in Table 11.10.5.2.5 was developed to encompass most brands. For more specific values, refer to the manufacturer's data for the circuit breaker being tested. Table 11.10.5.2.5 Values for Inverse Time Trip Test (at 300 Percent of Rated Continuous Current of Circuit Breaker) Maximum Trip Time in Seconds* Rated Current in Amperes ≤250 V 251–600 V 0–30 50 70 31–50 80 100 51–100 140 160 101–150 200 250 151–225 230 275 226–400 300 350 401–600 —450 601–800 —500 City of Iowa City Parking Garages 4 of 6 THP Limited, Inc. Appendix D October, 2019 Table 11.10.5.2.5 Values for Inverse Time Trip Test (at 300 Percent of Rated Continuous Current of Circuit Breaker) Maximum Trip Time in Seconds* Rated Current in Amperes ≤250 V 251–600 V 801–1000 —600 1001–1200 —700 1201–1600 —775 1601–2000 —800 2001–2500 —850 2501–5000 —900 6000 —1000 *For integrally fused circuit breakers, trip times may be substantially longer if tested with the fuses replaced by solid links (shorting bars). 11.10.5.2.6 Testing the instantaneous (magnetic) element of a trip unit requires the use of the appropriate test equipment coupled with accurate current-monitoring instrumentation, preferably with digital readouts, for accurate test results. Instantaneous pickup values of insulated-case/molded-case circuit breakers should fall within the manufacturer’s published tolerances. In the absence of manufacturer’s published tolerances, refer to Table 11.10.5.2.6 with values as recommended in Table 4 of ANSI/NEMA AB4, Guidelines for Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and Industrial Applications. Table 11.10.5.2.6 Instantaneous Trip Tolerances for Field Testing of Circuit Breakers Tolerances of Manufacturers’ Published Trip Range Breaker Type Tolerances of Settings High Side Low Side Electronic trip units*+30%—— City of Iowa City Parking Garages 5 of 6 THP Limited, Inc. Appendix D October, 2019 Table 11.10.5.2.6 Instantaneous Trip Tolerances for Field Testing of Circuit Breakers Tolerances of Manufacturers’ Published Trip Range Breaker Type Tolerances of Settings High Side Low Side −30%—— Adjustable*+40%—— −30%—— Nonadjustable†—+25%−25% *Tolerances are based on variations from the nominal settings. †Tolerances are based on variations from the manufacturer’s published trip band (i.e., −25 percent below the low side of the band, +25 percent above the high side of the band). 11.10.5.3 Testing Instantaneous-Only Circuit Breakers. The testing of instantaneous-only circuit breakers requires the use of the appropriate test equipment coupled with accurate current-monitoring instrumentation, preferably with a digital readout, for accurate test results. Instantaneous pickup values of insulated-case/molded-case circuit breakers should fall within the manufacturer’s published tolerances. 11.10.5.4 Testing Solid-State Trip Units. Breakers employing solid-state trip units offer testing opportunities not readily available in thermal-magnetic or instantaneous only trip units. These devices have two or more of the following elements. 11.10.5.4.1 Long Time-Delay Element. This element is designed to operate on overloads between its pickup setting and the pickup of a short time delay or an instantaneous element. The long time-delay pickup adjustment is generally within the range of 80 percent to 160 percent of the trip-device rating. Settings higher than solid-state trip-device ampere rating do not increase the continuous-current rating of the trip device, and in no event is the rating increased beyond the breaker frame size. The operating time of this element ranges from seconds to minutes. Determine long-time pickup and delay. Long-time pickup values should be as specified, and the trip characteristic should not exceed manufacturer’s published time– current characteristic tolerance band, including adjustment factors. City of Iowa City Parking Garages 6 of 6 THP Limited, Inc. Appendix D October, 2019 11.10.5.4.2 Short Time-Delay Element. This element has a time delay measured in cycles and is used to protect against moderate fault currents and short circuits. This element usually can be adjusted to pick up within the range of 250 percent to 1000 percent of the trip- device rating. Determine short-time pickup and delay. Short-time pickup values should be as specified, and the trip characteristic should not exceed manufacturer’s published time–current tolerance band. 11.10.5.4.3 Instantaneous Element. This element has no intentional time delay and is used to protect against heavy fault currents and short circuits. The pickup settings for this type of element usually range from 500 percent to 1500 percent of the trip-device rating. Determine instantaneous pickup. Instantaneous pickup values should be within the tolerances of manufacturer’s published data. 11.10.5.4.4 Ground-Fault Element. This element is available only on solid-state devices and is used to protect against ground-fault currents at levels below those that would be sensed otherwise. Determine ground-fault pickup and delay. Ground-fault pickup values should be as specified, and the trip characteristic should not exceed manufacturer’s published time–current tolerance band. RFP – Parking Garage Eng. Services B-1 City of Iowa City APPENDIX B – CONSULTANT AGREEMENT RFP – Parking Garage Eng. Services B-2 City of Iowa City Consultant Agreement This Agreement, made and entered into this ___________ day o f ____________________, ______________, by and between the City of Iowa City, a municipal corporation, hereinafter referred to as the City and _____________________, of _____________________, hereinafter referred to as the Consultant. INSERT BRIEF PROJECT DESCRIPTION BEGINNING WITH “WHEREAS” Now Therefore, it is agreed by and between the parties hereto that the City does now contract with the Consultant to provide services as set forth herein. I. Scope of Services Consultant agrees to perform the following services for the City, and to do so in a timely and satisfactory manner. INSERT DESCRIPTION OF SCOPE OF SERVICES II. Time of Completion The Consultant shall complete the following phases of the Project in accordance with the schedule shown. INSERT SCHEDULE OF SERVICES III. Compensation for Services INSERT DESCRIPTION OF COMPENSATION RFP – Parking Garage Eng. Services B-3 City of Iowa City IV. General Terms A. The Consultant shall not commit any of the following employment practices and agrees to prohibit the following practices in any subcontracts. 1. To discharge or refuse to hire any individual because of their race, color, religion, sex, national origin, disability, age, marital status, gender identity, or sexual orientation. 2. To discriminate against any individual in terms, conditions, or privileges of employment because of their race, color, religion, sex, national origin, disability, age, marital status, gender identity, or sexual orientation. B. Should the City terminate this Agreement, the Consultant shall be paid for all work and services performed up to the time of termination. However, such sums shall not be greater than the "not-to-exceed" amount listed in Section IV. The City may terminate this Agreement upon seven (7) calendar days' written notice to the Consultant. C. This Agreement shall be binding upon the successors and assigns of the parties hereto, provided that no assignment shall be without the written consent of all Parties to said Agreement. D. It is understood and agreed that the retention of the Consultant by the City for the purpose of the Project shall be as an independent contractor and shall be exclusive, but the Consultant shall have the right to employ such assistance as may be required for the performance of the Project. E. It is agreed by the City that all records and files pertaining to information needed by the Consultant for the project shall be available by said City upon reasonable request to the Consultant. The City agrees to furnish all reasonable assistance in the use of these records and files. F. It is further agreed that no Party to this Agreement shall perform contrary to any state, federal, or local law or any of the ordinances of the City of Iowa City, Iowa. G. At the request of the City, the Consultant shall attend meetings of the City Council relative to the work set forth in this Agreement. Any requests made by the City shall be given with reasonable notice to the Consultant to assure attendance. H. The Consultant agrees to furnish, upon termination of this Agreement and upon demand by the City, copies of all basic notes and sketches, charts, computations, and any other data prepared or obtained by the Consultant pursuant to this Agreement without cost, and without restrictions or limitation as to the use relative to specific projects covered under this Agreement. In such event, the Consultant shall not be liable for the City's use of such documents on other projects. RFP – Parking Garage Eng. Services B-4 City of Iowa City I. The Consultant agrees to furnish all reports, specifications, and drawings with the seal of a licensed professional as required by Iowa law. J. The City agrees to tender the Consultant all fees in a timely manner, excepting, however, that failure of the Consultant to satisfactorily perform in accordance with this Agreement shall constitute grounds for the City to withhold payment of the amount sufficient to properly complete the Project in accordance with this Agreement. K. Should any section of this Agreement be found invalid, it is agreed that the remaining portion shall be deemed severable from the invalid portion and continue in full force and effect. L. Original contract drawings shall become the property of the City. The Consultant shall be allowed to keep reproducible copies for the Consultant's own filing use. M. Fees paid for securing approval of authorities having jurisdiction over the Project will be paid by the City. N. Upon signing this Agreement, Consultant acknowledges that Section 362.5 of the Iowa Code prohibits a City officer or employee from having an interest in a contract with the City, and certifies that no employee or officer of the City, which includes members of the City Council and City boards and commissions, has an interest, either direct or indirect, in this Agreement, that does not fall within the exceptions to said statutory provision enumerated in Section 362.5. O. Indemnification. 1. To the full extent permitted by law, Consultant agrees to defend, indemnify, and hold harmless the City against any and all claims, demands, suits, loss, expenses, including attorney’s fees, and for any damages which may be asserted, claimed or recovered against or from the City by reason of personal injury, including bodily injury or death, and property damages, including loss of use thereof, caused by Consultant's negligent acts, errors or omissions in performing the work and/or services provided by Consultant to the City pursuant to the provisions of this Agreement. 2. Consultant assumes full responsibility for any and all damage or injuries which may result to any person or property by reason of Consultant's negligent acts, errors or omissions in connection with the work and/or services provided by Consultant to the City pursuant to this Agreement, and agrees to pay the City for all damages caused to the City's premises resulting from the negligent acts, errors or omissions of Consultant. 3. The Consultant’s obligation to indemnify the City shall not include the obligation to indemnify, hold harmless, or defend the City against lability, RFP – Parking Garage Eng. Services B-5 City of Iowa City claims, damages, losses, or expenses, including attorney fees, to the extent caused by or resulting from the negligent act, error, or omission of the City. 4. For purposes of this paragraph, the term "Consultant" means and includes the Consultant, its officers, agents, employees, sub-consultants, and others for whom Consultant is legally liable, and the term “City” means and includes the City of Iowa City, Iowa its Mayor, City Council members, employees, and volunteers. P. Insurance 1. The Consultant agrees at all times material to this Agreement to have and maintain professional liability insurance covering the Consultant’s liability for the Consultant’s negligent acts, errors and omissions in the sum of $1,000,000 Per Claim, $1,000,000 Annual Aggregate, or a $1,000,000 Combined Single Limit. To the fullest extent permitted by applicable state law, a Waiver of Subrogation Clause (endorsement) shall be added. 2. Consultant agrees to provide the City a certificate of insurance evidencing that all coverages, limits and endorsements required herein are maintained and in full force and effect, and certificates of Insurance shall provide a minimum thirty (30) day endeavor to notify, when available by Consultant’s insurer. If the Consultant receives a non-renewal or cancellation notice from an insurance carrier affording coverage required herein, or receives notice that coverage no longer complies with the insurance requirements herein, Consultant agrees to notify the City within five (5) business days with a copy of the non-renewal or cancellation notice. Q. Standard of Care. 1. The Consultant shall perform services for, and furnish deliverables to, the City pertaining to the Project as set forth in this Agreement. The Consultant shall possess a degree of learning, care and skill ordinarily possessed by reputable professionals, practicing in this area under similar circumstances The Consultant shall use reasonable diligence and professional judgment in the exercise of skill and application of learning. 2. Consultant represents that the Services and all its components shall be free of defects caused by negligence; shall be performed in a manner consistent with the standard of care of other professional service providers in a similar Industry and application; shall conform to the requirements of this Agreement; and shall be sufficient and suitable for the purposes expressed in this Agreement. 3. All provisions of this Agreement shall be reconciled in accordance with the generally accepted standards of the Engineering Profession. RFP – Parking Garage Eng. Services B-6 City of Iowa City 4. Consultant's obligations under this Section shall exist without regard to, and shall not be construed to be waived by, the availability or unavailability of any insurance, either of City or Consultant. R. There are no other considerations or monies contingent upon or resulting from the execution of this Agreement, it is the entire Agreement, and no other monies or considerations have been solicited. S. This Agreement shall be interpreted and enforced in accordance with the laws of the State of Iowa. Any legal proceeding instituted with respect to this Agreement shall be brought in a court of competent jurisdiction in Johnson County, Iowa. The parties hereto hereby submit to personal jurisdiction therein and irrevocably waive any objection as to venue therein, including any argument that such proceeding has been brought in an inconvenient forum. For the City For the Consultant By: By: Title: Title: Date: Date: Attest: Approved by: City Attorney's Office Date RFP – Parking Garage Eng. Services C-1 City of Iowa City APPENDIX C – CITY OF IOWA CITY WAGE THEFT POLICY RFP – Parking Garage Eng. Services 2 City of Iowa City CITY OF IOWA CITY WAGE THEFT POLICY It is the policy of the City of Iowa City, as expressed by City Council Resolution No. 15 -364 adopted on November 10, 2015, not to enter into certain contracts with, or provide discretionar y economic development assistance to, any person or entity (including an owner of more than 25% of the entity) who has admitted guilt or liability or been adjudicated guilty or liable in any judicial or administrative proceeding of committing a repeated or willful violation of the Iowa Wage Payment Collection law, the Iowa Minimum Wage Act, the Federal Fair Labor Standards Act or any comparable state statute or local ordinance, which governs the payment of wages, for a period of five (5) years from the date of the last conviction, entry of plea, administrative finding or admission of guilt. (hereinafter “Wage Theft Policy”) I. Application. The Wage Theft Policy applies to the following: a. Contracts in excess of $25,000 for goods, services or public improvements. b. Contracts for discretionary economic development assistance. “Discretionary” economic development assistance shall mean any economic development assistance provided by the City of Iowa City that is not required by law. II. Exceptions. The Wage Theft Policy does not apply to emergency purchases of goods and services, emergency construction or public improvement work, sole source contracts excepted by the City’s purchasing manual, cooperative/piggyback purchasing or contracts with other governmental entities. III. Affidavit. The contracting entity must complete the attached affidavit showing compliance with the Wage Theft Policy and provide it to the Contracting Department prior to the execution of the contract. Contract provision: Any contract to which this policy is applicable will include the following contract provision: If the City becomes aware that a person or entity (including an owner of more than 25% of the entity) has admitted guilt or liability or been adjudicated guilty or liable in any judicial or administrative proceeding of committing a repeated or willful violation of the Iowa Wage Payment Collection law, the Iowa Minimum Wage Act, the Federal Fair Labor Standards Act or any comparable state statute or local ordinance, which governs the payment of wages, within the five (5) year period prior to the award or at any time after the award, such violation shall constitute a default under the contract. IV. Waivers. If a person or entity is ineligible to contract with the City as a result of the Wage Theft Policy it may submit a request in writing indicating that one or more of the following actions have been taken: a. There has been a bona fide change in ownership or control of the ineligible person or entity; b. Disciplinary action has been taken against the individual(s) responsible for the acts giving rise to the violation(s); c. Remedial action has been taken to prevent a recurrence of the acts giving rise to the disqualification or default; or d. Other factors that the person or entity believes are relevant. RFP – Parking Garage Eng. Services 3 City of Iowa City The City Manager or Designee shall review the documentation submitted, make any inquiries deemed necessary, request additional documentation if warranted and determine whether a reduction in the ineligibility period or waiver is warranted. Should the City Manager or Designee determine that a reduction or waiver of the ineligibility period is warranted the City Manager or Designee shall make such recommendation to the City Council. The City Council will make a final decision as to whether to grant a reduction or waiver. Any objection that your company has regarding this policy must be stated in the space provided below. If your company is in agreement with this policy and is able to uphold the policy, provide a statement in the space provided below. ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ _______________________________ ________________________________ Signature of Company Representative Date