HomeMy WebLinkAboutN Gilbert Public Meeting No.1 - Presentation Slides_SMN. Gilbert Street
Reconstruction Project
Public Meeting No. 1
November 16, 2022
Introduction
Josh Straka, P.E. –Strand Associates
Consultant Engineer hired by City for Design Services
Tyler Olson, P.E. –Iowa City
Engineer from City –Project Manager
410 E. Washington Street
Iowa City, IA 52240
Office: (319) 356-5416
tolson@iowa-city.org
The Story
N Gilbert Street requires Full Reconstruction due to:
•Street pavement condition
•No storm sewer for most of the street section
•Aging sanitary sewer
This Reconstructed Street should implement City’s Complete Streets
Policy as much as possible
•In Summary: The Vision of the Complete Street policy is to realize
long-term cost-savings and, among other things, to have walkable
neighborhoods, create a sense of community pride, and improve
quality-of-life
•Complete Street is defined as a street that accommodates convenient
and safe use by everyone, regardless of age, ability, or mode of travel.
What is proposed for Construction?
Project is still in the early phase and may revise improvement item inclusion with the project as the project progresses. Pri ority items for
improvements include (in no particular order):
Undergrounding Existing
Aerial Utilities
Overhead wires and some utility poles
would be removed. Existing utility poles
with lights to remain. Will require
addition of pedestals and/or other utility
infrastructure.
Repaving North Gilbert
Street with New Concrete
Intersection of North Gilbert Street and
Brown Street would be reconstructed
with original brick as much as possible
Repaving Existing Driveway
Approaches with New
Concrete
Done as needed to tie back into newly
paved street.
Replacing Sanitary Sewer
Mains and Manholes
Extending Storm Sewer
Adding new storm sewer pipes and street
intakes to connect to existing intakes
Replacing and Extending
Sidewalks
For the entire length of project corridor
What are the Benefits?
Project is still in the early phase and may revise improvement item inclusion with the project as the project progresses. Gen erally, benefits for
improvements include (in no particular order):
Buried Utilities
Improves aesthetic look and provides
better protection from severe weather
New Concrete Street
Provides safer travel surface for vehicles
New Reconstructed Brick
Street Intersection
Preserves historic character of Brown
Street with original bricks to be reused
with new concrete curb and gutter
New Sanitary Sewer
Includes new mains and manholes will be
installed to replacing the aging system
below the street
New Expanded Storm Water
Management
New Street Curb and Gutter and New
Street Intakes help convey storm water
runoff and reduce stormwater
overwhelming the traffic paths
New Concrete Sidewalks
Provides ADA (Americans with
Disabilities Act) compliant pedestrian
pathways with connections to other
sidewalks along the adjoining streets
What is the Overall Project Schedule?
2022
Revised
Construction Year
Existing Field Survey (End of Fall)
Alternatives Research and Concept
Review (End of Fall)
Public Meeting No. 1 (End of Year)
Preliminary Concept Selected (End of
Year)
2023
If needed, any Property Acquisition
and/or Easement Agreements
Completed (2024)
Private Utility Undergrounding
(Summer 2023 thru Fall 2024)
Preliminary Design Plan (End of
Summer)
Public Meeting No. 2 (End of Fall)
Final Design (End of Year)
Contractor Bidding (2024)
2025
Pre-construction Public Meeting (Late
Winter / Early Spring)
Begin Construction (Spring)
Complete Major Construction Activity
(End of Fall)
As-Built Field Survey (End of Fall)
Complete Seeding and Planting
Restoration Work (End of Fall 2025
and if needed, may extend into
Spring of 2026)
Please note this schedule is an estimated timeline.
It may change as the project develops.
What are some Conflicts
Existing Width of Public Right-of-Way
Public Right-of-Way: Property dedicated to the public
use and intended for the movement of the public,
including utilities.
Need space for:
•Street
•Parkway
•Sidewalks
•Utility Access
Existing Condition Challenges
Existing Items:
•Retaining Walls
•Trees
•Sidewalks
•Fences
•Steep Roadway Grades
•Steep Driveways vs. Flat Driveways on Opposite
Sides of the Roadway
80’
Northern
Section
Southern
Section
Example of Potential Conflicts
Concept Alternatives
Alternative 1
•Utilizes existing public right-of-way
•22-feet wide concrete street with curbs
•4-feet wide sidewalks on both sides of the street with passing area to
meet ADA requirements
•No on-street parking
•Relatively limited conflicts with existing plantings, walls, and fences.
Alternative 2
•Utilizes existing public right-of-way
•26-feet wide concrete street with curbs
•4-feet wide sidewalks on both sides of the street with passing area to
meet ADA requirements
•Allows alternating ODD or EVEN day on-street parking
•Likely more conflicts than Alternatives 1 for existing plantings, walls,
and fences.
Questions?
If you later have any questions, please reach out to:
Tyler Olson, P.E. –Iowa City
Engineer from City –Project Manager
410 E. Washington Street
Iowa City, IA 52240
Office: (319) 356-5416
tolson@iowa-city.org
If you have not already, please fill out the
attendance sheet before you leave.
Thank you!