HomeMy WebLinkAboutCoralville - North Ridge Trail Reconstruction ProjectCity of Coralville
Engineering Department
1512 7th Street, Coralville, Iowa 52241 Phone: 319.248.1720
Page 1 of 1
F
Date: February 24, 2025
Project: North Ridge Trail Reconstruction
ITEMIZED BREAKDOWN
The following cost estimate breakdown was developed based on the costs of reconstructing a
trail within the last year:
Mobilization $ 50,000
Paving $ 130,000
Removals $ 25,000
Earthwork, Clearing and Grubbing $ 5,000
Easements $ 5,000
Topsoil, Seeding, Erosion Control $ 10,000
Storm Sewer $ 25,000
Special Compaction of Sugrade $ 5,000
Railroad Protection Liability Insurance $ 10,000
Traffic Control $ 10,000
Railroad Panels $ 40,000
Engineering Services $ 70,000
Project Total $ 385,000