HomeMy WebLinkAbout2022-2026 Capital Improvement Program.pdfCAPITAL PROJECTS FUND
Fund Summary
Summary by Division
Summary by Funding Source
Annual Recurring Projects Project Summary by Name
Unfunded Projects
F
Y
2
0
2
3
CAPITAL PROJECTS FUND
The Capital Projects Fund accounts for the collection and disbursement of funds related
to capital improvements or significant capital equipment. The City annually updates and
issues a five-year capital improvement program (CIP). This program is the planning
guide for the City’s issuance of bonded debt and for the construction and replacement of
the City’s buildings and infrastructure. The first two years of the five-year capital
improvement program (CIP) are certified as part of the operating budget in the Capital
Projects Fund. The current five-year CIP is for years 2022-2026. Additional information
for the City’s five-year CIP program including maps and photos is available on the City’s
web page: https://www.icgov.org/budget under the Capital Improvement Program
heading.
Capital improvement projects involve the construction, purchase, or renovation of city
facilities or property. Most of the projects are specific, non-recurring major improvements
to the City's physical plant, are permanent in nature, and are greater than $25,000 and
have a useful life of three years or more. The City also budgets annually recurring
project funds for non-specified improvements of a specific nature; these funds are to be
spent on improvements that meet the same definition above. Funding sources for
capital improvement projects may be from operating funds, bond proceeds, grants,
donations, and a variety of other funding sources. The three largest sources of funds
are operating transfers in, bonded debt, and state and federal grants.
For the CIP for years 2022-2026, the total funding sources are $205,922,725, and the
total expenditures are $205,848,950. The difference between the total expenditures and
the total funding sources over the five-year period is a result of prior plan funding
sources that are being utilized to cover current plan expenditures such as engineering
and design.
The 2023 CIP expenditures of $47,356,220 will be certified as part of the fiscal year
2023 operating budget.
The 2023 CIP funding sources of $47,958,995 will also be certified as part of the fiscal
year 2023 operating budget. Budgeted fiscal year 2023 Capital Projects Fund revenues
and transfers in also include a transfer in from the TIF funds to reimburse for prior year
expenditures of $25,758. Total Capital Projects Fund fiscal year 2023 budgeted
revenues and transfer in are $47,984,753.
The changes to the 2022 CIP are amended into the fiscal year 2022 operating budget.
The fiscal year 2022 Capital Projects Fund expenditure budget also includes totals from
the carry forward of prior year projects that must be re-appropriated with the State. The
amounts being carried forward from prior years are not included in the five-year CIP
totals. The revised Capital Projects Fund expenditures for fiscal year 2022 are
$77,959,172; the revised budget includes the 2022 CIP expenditures of $28,788,020
514
and prior year project carry forwards of $49,171,152. A transfer out of $425,000 was
carried forward from fiscal year 2021 for the final payment of the State sales tax flood
mitigation grant loan to the Wastewater Fund.
The revised fiscal year 2022 Capital Projects Fund revenues and transfers in budget
also includes totals from the carry forward of prior year projects. The amounts being
carried forward from prior years are not included in the five-year CIP totals. The revised
Capital Projects Fund revenues and transfers in for fiscal year 2022 are $39,931,472;
the revised budget includes the 2022 CIP funding sources of $26,784,020 and a transfer
in from the TIF funds to reimburse for prior year expenditures of $18,191, and prior year
project carry forwards of $13,129,261.
Fund balance in the Capital Projects Fund primarily represents unspent funding sources
from the current year and prior years. This balance fluctuates based on the timing of the
issuance of bonds and the timing of the project expenditures. The estimated ending
fund balance for fiscal year 2023 is $4,272,915.
515
2019 2020 2021 2022 2023 2024
Actual Actual Actual Revised Budget Projected
Fund Balance, July 1 51,478,202$ 37,683,022$ 38,062,482$ 42,097,081$ 3,644,382$ 4,272,915$
Revenues:
Use Of Money And Property
Interest Revenues 745,132$ 499,001$ 162,752$ -$ -$ -$
Intergovernmental
Federal Intergovernmental Revenue 347,216 1,044,497 1,458,355 8,227,394 2,357,525 16,005,000
Disaster Assistance - - - - - -
Other State Grants 2,723,823 4,961,896 1,643,322 3,777,578 650,000 -
State 28E Agreements 161,848 90,661 91,484 50,000 425,000 272,000
Local 28E Agreements 25,000 25,000 31,740 1,600,000 - -
Charges of Fees & Services
Development Fees 63,645 93,462 355,368 - - -
Miscellaneous
Contributions & Donations 10,000 25,000 6,495 195,000 - -
Printed Materials 4,360 885 525 - - -
Other Miscellaneous Revenue 27,002 121,490 288,162 - - -
Other Financial Sources
Debt Sales 12,565,848 13,012,385 12,744,378 10,100,000 27,756,000 12,215,000
Sub-Total Revenues 16,673,874 19,874,276 16,782,581 23,949,972 31,188,525 28,492,000
Transfers In:
Transfers-In from Governmental Funds 6,987,195 4,751,737 4,456,604 6,558,661 4,906,228 9,874,770
Transfers-In from Enterprise Funds 9,138,147 8,020,378 7,447,763 8,509,863 10,890,000 14,355,000
Miscellaneous Transfers-In 107,684 3,335 35,351 87,976 - -
Internal Service (Non-Budgetary):
Equipment Fund - - - 825,000 1,000,000 3,500,000
Sub-Total Transfers In 16,233,026 12,775,451 11,939,718 15,981,500 16,796,228 27,729,770
Total Revenues & Transfers In 32,906,900$ 32,649,727$ 28,722,299$ 39,931,472$ 47,984,753$ 56,221,770$
Expenditures:
Governmental:
General Government 440,206$ 1,060,808$ 2,827,102$ 869,855$ -$ -$
Culture & Recreation 8,245,547 5,556,924 2,482,195 9,139,432 4,305,000 6,975,000
Community and Economic Dvlpmnt 8,407,063 237,979 97,096 398,077 - -
Public Safety 5,026 768,914 1,895,807 2,056,319 - 1,531,300
Public Works 22,655,067 16,948,609 11,031,324 41,630,909 15,460,470 20,860,470
Enterprise:
Parking Operations 288,825 70,266 61,616 3,141,861 700,000 632,000
Public Transportation 178,752 36,345 89,234 948,191 120,000 20,120,000
Wastewater Treatment 2,203,521 3,025,409 2,453,813 7,737,166 19,466,000 3,059,000
Water Operations 922,313 1,137,779 376,206 3,101,800 1,042,500 844,000
Refuse Operations - - - 550,000 - -
Landfill 1,698,022 - 879,645 3,452,104 5,175,000 840,000
Storm Water 226,608 594,327 879,466 3,136,294 690,000 990,000
Airport 156,128 1,082,908 664,196 1,797,164 397,250 450,000
Sub-Total Expenditures 45,427,080 30,520,267 23,737,700 77,959,172 47,356,220 56,301,770
Transfers Out:
Miscellaneous Transfers Out 1,275,000 1,750,000 950,000 425,000 - -
Sub-Total Transfers Out 1,275,000 1,750,000 950,000 425,000 - -
Total Expenditures & Transfers Out 46,702,080$ 32,270,267$ 24,687,700$ 78,384,172$ 47,356,220$ 56,301,770$
Fund Balance, June 30 37,683,022$ 38,062,482$ 42,097,081$ 3,644,382$ 4,272,915$ 4,192,915$
Capital Projects Fund
Fund Summary
516
Capital Improvement Plan 2022-2026
City of Iowa City, Iowa
',9,6,21 SUMMARY
thru2022 2026
TotalCategory20222023202420252026
Airport 1,148,750 397,250 450,000 1,400,000 1,170,000 4,566,000
Equipment 825,000 1,000,000 11,000,000 12,825,000
Fire 95,000 1,422,800 1,700,000 3,217,800
Government Buildings 955,000 1,700,000 1,100,000 550,000 350,000 4,655,000
Landfill 838,800 5,175,000 840,000 280,000 7,133,800
Library 150,000 375,000 400,000 925,000
Parking Operations 2,090,000 700,000 632,000 737,500 500,000 4,659,500
Parks Maintenance 1,480,000 2,605,000 3,720,000 1,240,000 3,220,000 12,265,000
Police 125,000 108,500 233,500
Public Works Administration 750,000 750,000
Recreation 100,000 500,000 5,500,000 6,100,000
Senior Center 2,720,000 1,655,000 1,745,000 6,120,000
Stormwater 1,625,000 690,000 990,000 240,000 240,000 3,785,000
Street Operations 11,870,470 13,710,470 9,860,470 27,147,470 17,010,470 79,599,350
Transit Operations 120,000 120,000 20,120,000 120,000 120,000 20,600,000
Wastewater Treatment 3,464,000 19,466,000 3,059,000 3,338,000 3,519,500 32,846,500
Water Operations 1,181,000 1,042,500 844,000 1,200,000 1,300,000 5,567,500
28,788,020 47,356,220 56,301,770 43,592,970 29,809,970 205,848,950TOTAL
517
Airport, $4,566,000
Fire, $3,217,800
Equipment, $12,825,000
Landfill, $7,133,800
Library, $925,000 Government Buildings,
$4,655,000 Parks Maint,
$12,265,000 Parking, $4,659,500
Transit, $20,600,000
Police, $233,500
Public Works Admin,
$750,000
Recreation, $6,100,000
Senior Center,
$6,120,000
Stormwater, $3,785,000
Streets, $79,599,350
Wastewater,
$32,846,500
Water, $5,567,500
Capital Improvement Program
by Division
2022-2026
$205,848,950
518
Capital Improvement Plan 2022-2026
City of Iowa City, Iowa
PROJECTS BY ',9,6,21
2022 2026thru
Total20222023202420252026CategoryProject #Priority
Airport
A3447 75,00075,000Airport Parking Lot Expansion 3
A3462 94,00094,000Hangar A Door Replacement 2
A3465 150,000150,000Runway 7 Environmental Assessment 1
A3466 1,170,0001,170,000Runway 7 Extension (213')2
A3470 566,000566,000Runway 25 Threshold Relocation 1
A3471 397,250397,250Runway 12/30 Threshold Displacement/Relocation 1
A3473 1,250,0001,250,000Airport Apron Expansion 2
A3474 250,000250,000Runway 7/25 Pavement Repairs 2
A3475 200,000200,000Runway 12/30 Pavement Repairs 2
A3476 413,750413,750South Hanger Development Apron Expansion 1
4,566,0001,148,750 397,250 450,000 1,400,000 1,170,000Airport Total
Equipment
P3953 12,000,0001,000,000 11,000,000Equipment Maintenance Facility replacement 2
P3987 825,000825,000Non-Public Safety Radio System Upgrade 1
12,825,000825,000 1,000,000 11,000,000Equipment Total
Fire
Z4406 2,560,0001,360,000 1,200,000Fire Apparatus Replacement Program 1
Z4409 95,00095,000Fire Station #1 Apparatus Bay Slab Reconstruction 2
Z4410 62,80062,800Fire Station #1 Carpet/Tile Flooring Replacement 2
Z4411 500,000500,000Fire Station #5 Construction and #3 Replacement 2
3,217,80095,000 1,422,800 1,700,000Fire Total
Government Buildings
R4129 810,000400,000 260,000 50,000 50,000 50,000City Hall - Other Projects 1
R4194 1,250,000250,000 250,000 250,000 250,000 250,000Climate Action Facility Improvements 3
R4330 250,00050,000 50,000 50,000 50,000 50,000Annual Recreation Center Improvements 1
R4332 205,000205,000Upgrade Building BAS Controls 3
R4351 950,000250,000 700,000Recreation Center Improvements 1
R4370 640,000640,000Robert A. Lee Recreation Center Pool Filter & HVAC 2
R4381 300,00050,000 250,000Event Facility Improvements 2
R4388 250,00050,000 200,000ADA Elevator Improvements 1
4,655,000955,000 1,700,000 1,100,000 550,000 350,000Government Buildings Total
Landfill
L3328 1,100,000100,000 1,000,000Landfill Equipment Building Replacement 2
L3333 330,00030,000 300,000Compost Pad Improvements 2
L3335 600,00060,000 540,000Landfill Dual Extraction System Expansion 3
L3338 4,300,000215,000 4,085,000Future Landfill Cell 1
L3340 175,000175,000Bulk Water Fill Station 2
L3342 150,000150,000Leachate Lagoon updates 2
519
Total20222023202420252026CategoryProject #Priority
L3344 198,800198,800ACM Landfill Gas Infrastructure Expansion 1
L3345 280,000280,000Excavator for compost operations 2
7,133,800838,800 5,175,000 840,000 280,000Landfill Total
Library
B4343 775,000375,000 400,000Carpet and Furnishings Replacement 2
B4346 150,000150,000Automated Material Handler/Sorter 3
925,000150,000 375,000 400,000Library Total
Parking Operations
T3004 2,650,000650,000 500,000 500,000 500,000 500,000Parking Facility Restoration Repair 2
T3021 100,000100,000Video Cameras for Parking Facilities 3
T3022 90,00090,000Parking Enforcement Vehicles 3
T3023 1,000,0001,000,000Parking Ramp Automated Parking Equipment 2
T3025 400,000200,000 200,000Replacement of LED fixtures in Parking Facilities 2
T3026 237,500237,500Tower Place Drainage Modifications 1
T3027 50,00050,000Parking Ramp Stairwell Roof Replacement 1
T3028 132,000132,000Tower Place Office Remodel 3
4,659,5002,090,000 700,000 632,000 737,500 500,000Parking Operations Total
Parks Maintenance
R4130 450,00090,000 90,000 90,000 90,000 90,000Parks Annual Improvements/Maintenance 1
R4132 150,00030,000 30,000 30,000 30,000 30,000Park Annual ADA Accessibility Improvements 2
R4206 125,00025,000 25,000 25,000 25,000 25,000Intra-city Bike Trails 2
R4227 1,700,000200,000 1,500,000Hwy 6 Sidepath - Broadway to Fairmeadows 5
R4346 700,000350,000 350,000Palisades or Stone Bridge Park Development 2
R4350 390,000390,000Chadek Green Park Playground & and Shelter 2
R4357 150,000150,000Whispering Meadows Park Ecological Restoration 2
R4358 600,000600,000Lower City Park Shelters & Restroom Replacement 2
R4359 425,000425,000Kiwanis Park Playground & Shelter Renovation 2
R4362 450,000450,000Napoleon Park Softball Fields 5-8 Renovation 3
R4363 600,00050,000 550,000Upper City Park Improvements 2
R4365 245,000245,000Hickory Hill Park Conklin St Shelter & Restrooms 2
R4368 450,000450,000Court Hill Park Shelter & Playground Replacement 2
R4371 175,000175,000Happy Hollow Playground Replacement 2
R4372 1,250,0001,250,000Terrell Mill Skate Park Redevelopment 2
R4374 950,000950,000Mercer Park Ball Diamond Improvements 3
R4375 300,000300,000Hunter's Run Park Playground & Shelter 2
R4380 500,000100,000 100,000 100,000 100,000 100,000Annual Contracted Tree Planting 4
R4382 180,000180,000Off Road Bike Trail Development 5
R4384 135,000135,000Benton Hills Playground Replacement 2
R4385 350,000350,000College Green Park Playground 2
R4387 575,00065,000 510,000Willow Creek Trail Replacement 2
R4389 300,000300,000N. Market Square Playground Replacement 2
R4390 240,000240,000Reno Street Park Renovations 2
R4391 175,000175,000Tennis Court Renovations 5
R4392 700,000700,000Westside Park Land Acquisition 2
12,265,0001,480,000 2,605,000 3,720,000 1,240,000 3,220,000Parks Maintenance Total
Police
Y4446 125,000125,000Digital Photo Evidence Management 3
Y4447 108,500108,500Animal Shelter Standy Generator 2
233,500125,000 108,500Police Total
520
Total20222023202420252026CategoryProject #Priority
Public Works Administration
P3988 750,000750,000Entrance Way Improvements 4
750,000750,000Public Works Administration Total
Recreation
R4229 6,000,000500,000 5,500,000City Park Pool Replacement 3
R4230 100,000100,000Splash Pad Improvements 2
6,100,000100,000 500,000 5,500,000Recreation Total
Senior Center
K1001 2,720,0002,720,000Senior Center Facility Exterior Improvements 4
K1002 3,400,0001,655,000 1,745,000Senior Center Interior Improvements Project 3
6,120,0002,720,000 1,655,000 1,745,000Senior Center Total
Stormwater
M3631 960,000240,000 240,000 240,000 240,000Annual Stormwater Improvements 2
M3633 1,625,0001,625,000North Westminster Storm Sewer Upgrades 2
M3634 350,000350,000Rundell Street Pump Station Vault Modifications 2
M3635 850,000100,000 750,000River Street Storm Sewer Improvements 2
3,785,0001,625,000 690,000 990,000 240,000 240,000Stormwater Total
Street Operations
S3814 1,100,000300,000 200,000 200,000 200,000 200,000Annual Traffic Signal Projects 3
S3816 110,00050,000 15,000 15,000 15,000 15,000Traffic Calming 3
S3822 500,000100,000 100,000 100,000 100,000 100,000Curb Ramps-ADA 1
S3824 10,536,9402,107,388 2,107,388 2,107,388 2,107,388 2,107,388Annual Pavement Rehabilitation 1
S3826 940,410188,082 188,082 188,082 188,082 188,082Underground Electrical Facilities 2
S3827 750,000150,000 150,000 150,000 150,000 150,000Bicycle Master Plan Implementation 3
S3910 1,250,000250,000 250,000 250,000 250,000 250,000Annual Bridge Maintenance & Repair 1
S3939 3,000,000300,000 2,700,000Dubuque Street Reconstruction 1
S3940 100,000100,000Kirkwood Avenue to Capitol Street Connection 2
S3946 6,600,000150,000 6,450,000Court Street Reconstruction 2
S3950 6,350,0006,350,000Rochester Ave Reconst- First Ave. to Ralston Creek 2
S3951 150,000150,000Hwy 1/Hwy 6 Intersection Improvements Study 2
S3952 15,750,00015,750,000Dodge Street Reconstruct - Governor to Burlington 2
S3955 1,437,000200,000 1,237,000N. Gilbert Street Reconstruction 2
S3956 3,125,0003,125,000Gilbert Street Bridge Replacement 1
S3958 6,700,000700,000 6,000,000Park Road Reconstruct - Rocky Shore to Riverside 2
S3959 11,000,0001,000,000 10,000,000Taft Avenue Reconstruct - Am Legion to Lwr West Br 2
S3960 100,000100,000Oakdale Blvd Extension - Alignment Study 2
S3963 750,000750,000Burlington Street Bridge Replacement 1
S3965 1,350,0001,350,000Fairchild Street Reconstruction 2
S3977 2,250,000150,000 2,100,000Iowa Avenue Bridge Rehabilitation 2
S3978 1,300,000225,000 1,075,000Riverside Dr. Pedestrian Bridge at Iowa Ave Rehab 1
S3979 1,850,000250,000 1,600,000South Dubuque St Reconstruction - Wright to Benton 2
S3980 2,600,000300,000 2,300,000Market & Jefferson Street Two-Way Conversion 5
79,599,35011,870,470 13,710,470 9,860,470 27,147,470 17,010,470Street Operations Total
Transit Operations
T3055 20,000,00020,000,000Transit Maintenance Facility Relocation 2
T3067 600,000120,000 120,000 120,000 120,000 120,000Transit Interchange and Bus Stop Improvements 2
521
Total20222023202420252026CategoryProject #Priority
20,600,000120,000 120,000 20,120,000 120,000 120,000Transit Operations Total
Wastewater Treatment
V3101 3,750,000750,000 750,000 750,000 750,000 750,000Annual Sewer Main Replacement 2
V3151 12,801,000880,000 11,921,000Digester Complex Rehabilitation 1
V3154 1,025,00025,000 1,000,000Hawkeye Lift Station Rehabilitation 2
V3155 4,500,000110,000 4,390,000Rohret South Sewer 2
V3157 238,000238,000Wastewater Plant Mixer Improvements 2
V3158 170,000170,000Biosolids Conveyor Improvements 2
V3162 580,000580,000Benton Street Trunk Sewer Improvements 1
V3163 300,000300,000Aeration Basin Electric & Instrument Improvements 3
V3164 1,009,0001,009,000Return Activated Sludge Pump Replacement 2
V3165 605,000605,000Replacement of Influent Pump Station Pumps 2
V3167 394,000394,000Replace Grit Classifiers 2
V3169 1,475,0001,475,000Napoleon Lift Station Improvements 1
V3170 900,000300,000 300,000 300,000WWTP Roof Replacements 1
V3172 150,000150,000Highlander Lift Station Improvements 2
V3173 175,000175,000Jet Truck Replacement 1
V3174 2,036,0002,036,000Aeration Equipment Improvements 3
V3175 251,000251,000Influent Flow Monitoring 1
V3176 71,00071,000Treatment Plant Paving Improvements 2
V3177 371,00035,000 336,000HVAC Replacement 2
V3178 526,000526,000Primary Clarifier Repairs 2
V3179 1,210,0001,210,000Rotating Drum Thickener Replacement 2
V3180 97,50097,500Peninsula Control Panel and Pump Improvement 2
V3181 212,000212,000Wastewater Division Master Plan 2
32,846,5003,464,000 19,466,000 3,059,000 3,338,000 3,519,500Wastewater Treatment Total
Water Operations
W3300 650,00050,000 600,000Bradford Drive Water Main Replacement 3
W3313 526,000526,000Hwy 1 (Hawk Ridge to WalMart) Water Main Repl 2
W3314 650,00050,000 600,000High Service Pump VFD Replacement 2
W3316 200,000200,000Chlorine Feeder System Upgrade 2
W3317 65,00065,000Water Front Meeting Room A/V Upgrades 3
W3318 40,00040,000GSR Generator Enclosure Replacement 2
W3320 661,50067,500 594,000Hwy 6 (Fairmeadows to Ind Park Rd) Water Main Repl 1
W3321 150,000150,000Treatment Technology Study 2
W3322 1,000,000100,000 900,000Collector Well #2 Cleaning and Upgrade 1
W3323 250,000250,000Water Distribution Asset Inventory 2
W3324 75,00075,000Water Plant HVAC Study 3
W3325 100,000100,000Roof Replacements 2
W3326 600,000600,000Treatment Process Update 2
W3327 600,000600,000Melrose Water Main Camp Cardinal to 218 2
5,567,5001,181,000 1,042,500 844,000 1,200,000 1,300,000Water Operations Total
GRAND TOTAL 205,848,95028,788,020 47,356,220 56,301,770 43,592,970 29,809,970
522
Capital Improvement Plan 2022-2026
City of Iowa City, Iowa
FUNDING SOURCE SUMMARY
2022 thru 2026
TotalSource20222023202420252026
AIRPORT FUND 415,56381,063 32,500 45,000 140,000 117,000
EMERGENCY LEVY 1,750,000350,000 350,000 350,000 350,000 350,000
EQUIPMENT FUND 5,325,000825,000 1,000,000 3,500,000
FACILITY REPLACEMENT RESERVE 11,800,0005,500,000 5,800,000 500,000
FEDERAL GRANTS 29,211,212765,687 2,357,525 16,005,000 5,010,000 5,073,000
GENERAL FUND 5,534,300950,000 1,520,000 1,014,300 920,000 1,130,000
GO BONDS-ESSENTIAL PURPOSE 51,077,0008,700,000 7,600,000 8,765,000 11,382,000 14,630,000
GO BONDS-GENERAL PURPOSE 9,185,0001,400,000 2,485,000 3,450,000 1,400,000 450,000
LANDFILL FUND 3,333,800623,800 1,090,000 1,340,000 280,000
LANDFILL REPLACEMENT RESERVE 5,300,0001,215,000 4,085,000
OTHER STATE GRANTS 10,638,000138,000 650,000 9,850,000
PARKING FUND 3,659,5001,090,000 700,000 632,000 737,500 500,000
REFUSE COLLECTION FUND 250,000250,000
REVENUE BONDS 17,671,00017,671,000
ROAD USE TAX FUND 13,620,0002,832,000 2,697,000 2,697,000 2,697,000 2,697,000
STORMWATER FUND 4,035,0001,625,000 690,000 1,240,000 240,000 240,000
TAX INCREMENT FINANCING 2,000,0002,000,000
TRANSIT FUND 5,600,000120,000 120,000 5,120,000 120,000 120,000
UNIVERSITY OF IOWA 937,000425,000 272,000 240,000
UTILITY FRANCHISE TAX 1,567,350313,470 313,470 313,470 313,470 313,470
WASTEWATER FUND 16,545,5002,474,000 3,130,000 4,084,000 3,338,000 3,519,500
WATER FUND 6,467,5001,281,000 1,042,500 1,644,000 1,200,000 1,300,000
26,784,020 47,958,995 56,221,770 43,497,970 31,459,970 205,922,725GRAND TOTAL
523
Utility Franchise Tax,
$1,567,350
Facility Replacement
Reserve, $11,800,000
Federal Grants,
$29,211,212
University of Iowa,
$937,000
Other State Grants,
$10,638,000General Fund, $5,534,300Road Use Tax,
$13,620,000
Water, $6,467,500
Wastewater, $16,545,500
Parking, $3,659,500
Transit, $5,600,000
Airport, $415,563
Landfill, $8,633,800
Stormwater, $4,035,000
Tax Increment Financing,
$2,000,000
Emergency Levy,
$1,750,000
Refuse Collection,
$250,000
Equipment, $5,325,000 GO Bonds, $60,262,000
Revenue Bonds,
$17,671,000
Capital Improvement Program
by Funding Source
2022-2026
$205,922,725
524
Capital Improvement Plan 2022-2026
City of Iowa City, Iowa
PROJECTS BY FUNDING SOURCE
2022 2026thru
TotalSourceProject #Priority 2022 2023 2024 2025 2026
AIRPORT FUND
A3462 19,00019,000Hangar A Door Replacement 2
A3465 15,00015,000Runway 7 Environmental Assessment 1
A3466 117,000117,000Runway 7 Extension (213')2
A3471 32,50032,500Runway 12/30 Threshold Displacement/Relocation 1
A3473 125,000125,000Airport Apron Expansion 2
A3474 25,00025,000Runway 7/25 Pavement Repairs 2
A3475 20,00020,000Runway 12/30 Pavement Repairs 2
A3476 62,06362,063South Hanger Development Apron Expansion 1
415,56381,063 32,500 45,000 140,000 117,000AIRPORT FUND Total
EMERGENCY LEVY
R4194 1,250,000250,000 250,000 250,000 250,000 250,000Climate Action Facility Improvements 3
R4380 500,000100,000 100,000 100,000 100,000 100,000Annual Contracted Tree Planting 4
1,750,000350,000 350,000 350,000 350,000 350,000EMERGENCY LEVY Total
EQUIPMENT FUND
P3953 4,500,0001,000,000 3,500,000Equipment Maintenance Facility replacement 2
P3987 825,000825,000Non-Public Safety Radio System Upgrade 1
5,325,000825,000 1,000,000 3,500,000EQUIPMENT FUND Total
FACILITY REPLACEMENT RESER
K1002 2,000,0001,000,000 1,000,000Senior Center Interior Improvements Project 3
P3953 4,000,0004,000,000Equipment Maintenance Facility replacement 2
R4229 5,300,000500,000 4,800,000City Park Pool Replacement 3
Z4411 500,000500,000Fire Station #5 Construction and #3 Replacement 2
11,800,0005,500,000 5,800,000 500,000FACILITY REPLACEMENT
RESERVE Total
FEDERAL GRANTS
A3465 135,000135,000Runway 7 Environmental Assessment 1
A3466 1,053,0001,053,000Runway 7 Extension (213')2
A3470 414,000414,000Runway 25 Threshold Relocation 1
A3471 357,525357,525Runway 12/30 Threshold Displacement/Relocation 1
A3473 1,125,0001,125,000Airport Apron Expansion 2
A3474 225,000225,000Runway 7/25 Pavement Repairs 2
A3475 180,000180,000Runway 12/30 Pavement Repairs 2
A3476 351,687351,687South Hanger Development Apron Expansion 1
R4227 520,000520,000Hwy 6 Sidepath - Broadway to Fairmeadows 5
R4372 600,000600,000Terrell Mill Skate Park Redevelopment 2
525
TotalSourceProject #Priority 2022 2023 2024 2025 2026
S3952 3,750,0003,750,000Dodge Street Reconstruct - Governor to Burlington 2
S3956 1,000,0001,000,000Gilbert Street Bridge Replacement 1
S3959 3,500,0003,500,000Taft Avenue Reconstruct - Am Legion to Lwr West Br 2
S3977 1,000,0001,000,000Iowa Avenue Bridge Rehabilitation 2
T3055 15,000,00015,000,000Transit Maintenance Facility Relocation 2
29,211,212765,687 2,357,525 16,005,000 5,010,000 5,073,000FEDERAL GRANTS Total
GENERAL FUND
B4343 775,000375,000 400,000Carpet and Furnishings Replacement 2
B4346 150,000150,000Automated Material Handler/Sorter 3
P3988 650,000650,000Entrance Way Improvements 4
R4129 150,00050,000 50,000 50,000City Hall - Other Projects 1
R4130 450,00090,000 90,000 90,000 90,000 90,000Parks Annual Improvements/Maintenance 1
R4132 150,00030,000 30,000 30,000 30,000 30,000Park Annual ADA Accessibility Improvements 2
R4206 125,00025,000 25,000 25,000 25,000 25,000Intra-city Bike Trails 2
R4230 100,000100,000Splash Pad Improvements 2
R4330 250,00050,000 50,000 50,000 50,000 50,000Annual Recreation Center Improvements 1
R4346 700,000350,000 350,000Palisades or Stone Bridge Park Development 2
R4357 150,000150,000Whispering Meadows Park Ecological Restoration 2
R4374 250,000250,000Mercer Park Ball Diamond Improvements 3
R4381 300,00050,000 250,000Event Facility Improvements 2
R4382 180,000180,000Off Road Bike Trail Development 5
R4384 135,000135,000Benton Hills Playground Replacement 2
R4388 250,00050,000 200,000ADA Elevator Improvements 1
R4391 175,000175,000Tennis Court Renovations 5
S3951 150,000150,000Hwy 1/Hwy 6 Intersection Improvements Study 2
S3960 100,000100,000Oakdale Blvd Extension - Alignment Study 2
Y4446 125,000125,000Digital Photo Evidence Management 3
Y4447 108,500108,500Animal Shelter Standy Generator 2
Z4406 48,00048,000Fire Apparatus Replacement Program 1
Z4410 62,80062,800Fire Station #1 Carpet/Tile Flooring Replacement 2
5,534,300950,000 1,520,000 1,014,300 920,000 1,130,000GENERAL FUND Total
GO BONDS-ESSENTIAL PURPOSE
R4227 1,180,0001,180,000Hwy 6 Sidepath - Broadway to Fairmeadows 5
R4350 450,000450,000Chadek Green Park Playground & and Shelter 2
R4358 600,000600,000Lower City Park Shelters & Restroom Replacement 2
R4359 425,000425,000Kiwanis Park Playground & Shelter Renovation 2
R4363 600,000600,000Upper City Park Improvements 2
R4365 245,000245,000Hickory Hill Park Conklin St Shelter & Restrooms 2
R4368 450,000450,000Court Hill Park Shelter & Playground Replacement 2
R4371 175,000175,000Happy Hollow Playground Replacement 2
R4375 300,000300,000Hunter's Run Park Playground & Shelter 2
R4385 350,000350,000College Green Park Playground 2
R4389 300,000300,000N. Market Square Playground Replacement 2
R4390 240,000240,000Reno Street Park Renovations 2
S3939 3,000,0003,000,000Dubuque Street Reconstruction 1
S3946 6,600,0006,600,000Court Street Reconstruction 2
S3950 6,350,0006,350,000Rochester Ave Reconst- First Ave. to Ralston Creek 2
S3952 2,400,0002,400,000Dodge Street Reconstruct - Governor to Burlington 2
S3955 1,437,0001,437,000N. Gilbert Street Reconstruction 2
S3956 2,300,0002,300,000Gilbert Street Bridge Replacement 1
526
TotalSourceProject #Priority 2022 2023 2024 2025 2026
S3958 6,700,0006,700,000Park Road Reconstruct - Rocky Shore to Riverside 2
S3959 7,500,0007,500,000Taft Avenue Reconstruct - Am Legion to Lwr West Br 2
S3965 1,450,0001,450,000Fairchild Street Reconstruction 2
S3977 1,250,0001,250,000Iowa Avenue Bridge Rehabilitation 2
S3978 325,000325,000Riverside Dr. Pedestrian Bridge at Iowa Ave Rehab 1
S3979 1,850,0001,850,000South Dubuque St Reconstruction - Wright to Benton 2
S3980 2,600,0002,600,000Market & Jefferson Street Two-Way Conversion 5
Z4406 2,000,0001,040,000 960,000Fire Apparatus Replacement Program 1
51,077,0008,700,000 7,600,000 8,765,000 11,382,000 14,630,000GO BONDS-ESSENTIAL PURPOSE
Total
GO BONDS-GENERAL PURPOSE
K1001 700,000700,000Senior Center Facility Exterior Improvements 4
K1002 1,400,000700,000 700,000Senior Center Interior Improvements Project 3
P3953 700,000700,000Equipment Maintenance Facility replacement 2
R4129 660,000400,000 260,000City Hall - Other Projects 1
R4229 700,000700,000City Park Pool Replacement 3
R4332 205,000205,000Upgrade Building BAS Controls 3
R4351 950,000250,000 700,000Recreation Center Improvements 1
R4362 450,000450,000Napoleon Park Softball Fields 5-8 Renovation 3
R4370 700,000700,000Robert A. Lee Recreation Center Pool Filter & HVAC 2
R4372 650,000650,000Terrell Mill Skate Park Redevelopment 2
R4374 700,000700,000Mercer Park Ball Diamond Improvements 3
R4387 575,000575,000Willow Creek Trail Replacement 2
R4392 700,000700,000Westside Park Land Acquisition 2
Z4409 95,00095,000Fire Station #1 Apparatus Bay Slab Reconstruction 2
9,185,0001,400,000 2,485,000 3,450,000 1,400,000 450,000GO BONDS-GENERAL PURPOSE
Total
LANDFILL FUND
L3328 1,100,000100,000 1,000,000Landfill Equipment Building Replacement 2
L3333 330,00030,000 300,000Compost Pad Improvements 2
L3335 600,00060,000 540,000Landfill Dual Extraction System Expansion 3
L3340 175,000175,000Bulk Water Fill Station 2
L3342 150,000150,000Leachate Lagoon updates 2
L3344 198,800198,800ACM Landfill Gas Infrastructure Expansion 1
L3345 280,000280,000Excavator for compost operations 2
P3953 500,000500,000Equipment Maintenance Facility replacement 2
3,333,800623,800 1,090,000 1,340,000 280,000LANDFILL FUND Total
LANDFILL REPLACEMENT RESE
L3338 4,300,000215,000 4,085,000Future Landfill Cell 1
T3023 1,000,0001,000,000Parking Ramp Automated Parking Equipment 2
5,300,0001,215,000 4,085,000LANDFILL REPLACEMENT
RESERVE Total
OTHER STATE GRANTS
A3447 63,00063,000Airport Parking Lot Expansion 3
A3462 75,00075,000Hangar A Door Replacement 2
S3952 9,850,0009,850,000Dodge Street Reconstruct - Governor to Burlington 2
527
TotalSourceProject #Priority 2022 2023 2024 2025 2026
S3978 650,000650,000Riverside Dr. Pedestrian Bridge at Iowa Ave Rehab 1
10,638,000138,000 650,000 9,850,000OTHER STATE GRANTS Total
PARKING FUND
T3004 2,650,000650,000 500,000 500,000 500,000 500,000Parking Facility Restoration Repair 2
T3021 100,000100,000Video Cameras for Parking Facilities 3
T3022 90,00090,000Parking Enforcement Vehicles 3
T3025 400,000200,000 200,000Replacement of LED fixtures in Parking Facilities 2
T3026 237,500237,500Tower Place Drainage Modifications 1
T3027 50,00050,000Parking Ramp Stairwell Roof Replacement 1
T3028 132,000132,000Tower Place Office Remodel 3
3,659,5001,090,000 700,000 632,000 737,500 500,000PARKING FUND Total
REFUSE COLLECTION FUND
P3953 250,000250,000Equipment Maintenance Facility replacement 2
250,000250,000REFUSE COLLECTION FUND Total
REVENUE BONDS
V3151 12,921,00012,921,000Digester Complex Rehabilitation 1
V3155 4,750,0004,750,000Rohret South Sewer 2
17,671,00017,671,000REVENUE BONDS Total
ROAD USE TAX FUND
S3814 1,100,000300,000 200,000 200,000 200,000 200,000Annual Traffic Signal Projects 3
S3816 110,00050,000 15,000 15,000 15,000 15,000Traffic Calming 3
S3822 500,000100,000 100,000 100,000 100,000 100,000Curb Ramps-ADA 1
S3824 9,910,0001,982,000 1,982,000 1,982,000 1,982,000 1,982,000Annual Pavement Rehabilitation 1
S3827 750,000150,000 150,000 150,000 150,000 150,000Bicycle Master Plan Implementation 3
S3910 1,250,000250,000 250,000 250,000 250,000 250,000Annual Bridge Maintenance & Repair 1
13,620,0002,832,000 2,697,000 2,697,000 2,697,000 2,697,000ROAD USE TAX FUND Total
STORMWATER FUND
M3631 960,000240,000 240,000 240,000 240,000Annual Stormwater Improvements 2
M3633 1,625,0001,625,000North Westminster Storm Sewer Upgrades 2
M3634 350,000350,000Rundell Street Pump Station Vault Modifications 2
M3635 850,000100,000 750,000River Street Storm Sewer Improvements 2
P3953 250,000250,000Equipment Maintenance Facility replacement 2
4,035,0001,625,000 690,000 1,240,000 240,000 240,000STORMWATER FUND Total
TAX INCREMENT FINANCING
K1001 2,000,0002,000,000Senior Center Facility Exterior Improvements 4
2,000,0002,000,000TAX INCREMENT FINANCING Total
TRANSIT FUND
T3055 5,000,0005,000,000Transit Maintenance Facility Relocation 2
528
TotalSourceProject #Priority 2022 2023 2024 2025 2026
T3067 600,000120,000 120,000 120,000 120,000 120,000Transit Interchange and Bus Stop Improvements 2
5,600,000120,000 120,000 5,120,000 120,000 120,000TRANSIT FUND Total
UNIVERSITY OF IOWA
P3988 100,000100,000Entrance Way Improvements 4
S3978 325,000325,000Riverside Dr. Pedestrian Bridge at Iowa Ave Rehab 1
Z4406 512,000272,000 240,000Fire Apparatus Replacement Program 1
937,000425,000 272,000 240,000UNIVERSITY OF IOWA Total
UTILITY FRANCHISE TAX
S3824 626,940125,388 125,388 125,388 125,388 125,388Annual Pavement Rehabilitation 1
S3826 940,410188,082 188,082 188,082 188,082 188,082Underground Electrical Facilities 2
1,567,350313,470 313,470 313,470 313,470 313,470UTILITY FRANCHISE TAX Total
WASTEWATER FUND
P3953 1,000,0001,000,000Equipment Maintenance Facility replacement 2
V3101 3,750,000750,000 750,000 750,000 750,000 750,000Annual Sewer Main Replacement 2
V3154 1,025,0001,025,000Hawkeye Lift Station Rehabilitation 2
V3157 238,000238,000Wastewater Plant Mixer Improvements 2
V3158 170,000170,000Biosolids Conveyor Improvements 2
V3162 580,000580,000Benton Street Trunk Sewer Improvements 1
V3163 300,000300,000Aeration Basin Electric & Instrument Improvements 3
V3164 1,009,0001,009,000Return Activated Sludge Pump Replacement 2
V3165 605,000605,000Replacement of Influent Pump Station Pumps 2
V3167 394,000394,000Replace Grit Classifiers 2
V3169 1,475,0001,475,000Napoleon Lift Station Improvements 1
V3170 900,000300,000 300,000 300,000WWTP Roof Replacements 1
V3172 150,000150,000Highlander Lift Station Improvements 2
V3173 175,000175,000Jet Truck Replacement 1
V3174 2,036,0002,036,000Aeration Equipment Improvements 3
V3175 251,000251,000Influent Flow Monitoring 1
V3176 71,00071,000Treatment Plant Paving Improvements 2
V3177 371,00035,000 336,000HVAC Replacement 2
V3178 526,000526,000Primary Clarifier Repairs 2
V3179 1,210,0001,210,000Rotating Drum Thickener Replacement 2
V3180 97,50097,500Peninsula Control Panel and Pump Improvement 2
V3181 212,000212,000Wastewater Division Master Plan 2
16,545,5002,474,000 3,130,000 4,084,000 3,338,000 3,519,500WASTEWATER FUND Total
WATER FUND
P3953 800,000800,000Equipment Maintenance Facility replacement 2
W3300 650,00050,000 600,000Bradford Drive Water Main Replacement 3
W3313 626,000626,000Hwy 1 (Hawk Ridge to WalMart) Water Main Repl 2
W3314 650,00050,000 600,000High Service Pump VFD Replacement 2
W3316 200,000200,000Chlorine Feeder System Upgrade 2
W3317 65,00065,000Water Front Meeting Room A/V Upgrades 3
W3318 40,00040,000GSR Generator Enclosure Replacement 2
W3320 661,50067,500 594,000Hwy 6 (Fairmeadows to Ind Park Rd) Water Main Repl 1
W3321 150,000150,000Treatment Technology Study 2
529
TotalSourceProject #Priority 2022 2023 2024 2025 2026
W3322 1,000,000100,000 900,000Collector Well #2 Cleaning and Upgrade 1
W3323 250,000250,000Water Distribution Asset Inventory 2
W3324 75,00075,000Water Plant HVAC Study 3
W3325 100,000100,000Roof Replacements 2
W3326 600,000600,000Treatment Process Update 2
W3327 600,000600,000Melrose Water Main Camp Cardinal to 218 2
6,467,5001,281,000 1,042,500 1,644,000 1,200,000 1,300,000WATER FUND Total
205,922,72526,784,020 47,958,995 56,221,770 43,497,970 31,459,970GRAND TOTAL
530
Capital Improvement Plan 2022-2026
City of Iowa City, Iowa
$QQXDO5HFXUULQJ3URMHFWV
2022 2026thru
PARKS & RECREATION
Total20222023202420252026DepartmentProject #Priority
R4129 810,000400,000 260,000 50,000 50,000 50,000City Hall - Other Projects 1
R4130 450,00090,000 90,000 90,000 90,000 90,000Parks Annual Improvements/Maintenance 1
R4132 150,00030,000 30,000 30,000 30,000 30,000Park Annual ADA Accessibility Improvements 1
R4194 1,250,000250,000 250,000 250,000 250,000 250,000Climate Action Facility Improvements 1
R4206 125,00025,000 25,000 25,000 25,000 25,000Intra-city Bike Trails 1
R4330 250,00050,000 50,000 50,000 50,000 50,000Annual Recreation Center Improvements 1
R4380 500,000100,000 100,000 100,000 100,000 100,000Annual Contracted Tree Planting 1
3,535,000945,000 805,000 595,000 595,000 595,000PARKS & RECREATION Total
2022 - Roof Replacement; 2023 - Renovate lower level restrooms. 2024 - Remodel Employee Fitness room bathroom to become ADA
compliant and add toilet and sink. Update finishes and lighting in space; 2025 and 2026 - Undesignated.
R4129
City Hall - Other Projects
Annual funding for small capital projects and improvements throughout park system. Priorities per the 2017 Park Master Plan are: Park
Signs, Site Furnishings, Shelter/Facility Maintenance, Court Maintenance, Partner Opportunities for Small Projects and Emerging
Opportunities and Needs.
R4130
Parks Annual Improvements/Maintenance
Small projects in parks to improve and enhance physical accessility to park facilities and activity centers. 2022 - Oak Grove; 2023 - Kiwanis,
Hunter's Run and Ryerson's Woods; 2024 - Reno St; 2025 - Thornberry and Crandic; 2026 - Undetermined
R4132
Park Annual ADA Accessibility Improvements
Improvements to municipal facilities that reduce carbon emmissions and conserve resources such as LED lighting improvements, solar panel
additions, window replacements, etc.
R4194
Climate Action Facility Improvements
Annual appropriation for the construction or repair of bike trails.
R4206
Intra-city Bike Trails
Annual projects to maintain RALRC & Mercer/Scanlon Recreation Centers.
2022 - RALRC Lower Level Flooring; 2023 RALRC Craft Room Renovations; 2024 - Renovate former shooting range and lower level
storage; 2025 and 2026 not yet designated.
R4330
Annual Recreation Center Improvements
Annual contracted tree program for additions to street trees, neighborhood infill and park tree plantings. Areas of emphasis include low
income neighborhoods as well as neighborhoods that lost trees to the Emerald Ash Borer or the 2020 Derecho storm.
R4380
Annual Contracted Tree Planting
531
PUBLIC WORKS
Total20222023202420252026DepartmentProject #Priority
M3631 960,000240,000 240,000 240,000 240,000Annual Stormwater Improvements 1
S3814 1,100,000300,000 200,000 200,000 200,000 200,000Annual Traffic Signal Projects 1
S3816 110,00050,000 15,000 15,000 15,000 15,000Traffic Calming 1
S3822 500,000100,000 100,000 100,000 100,000 100,000Curb Ramps-ADA 1
S3824 10,536,9402,107,388 2,107,388 2,107,388 2,107,388 2,107,388Annual Pavement Rehabilitation 1
S3826 940,410188,082 188,082 188,082 188,082 188,082Underground Electrical Facilities 1
S3827 750,000150,000 150,000 150,000 150,000 150,000Bicycle Master Plan Implementation 1
S3910 1,250,000250,000 250,000 250,000 250,000 250,000Annual Bridge Maintenance & Repair 1
V3101 3,750,000750,000 750,000 750,000 750,000 750,000Annual Sewer Main Replacement 1
19,897,3503,895,470 4,000,470 4,000,470 4,000,470 4,000,470PUBLIC WORKS Total
This is an annual project that will repair and/or improve storm water infrastructure throughout the City.
M3631
Annual Stormwater Improvements
This is an annual project to replace or add traffic signals at intersections with outdated traffic signal equipment or at dangerous and
uncontrolled intersections. This project will install pan/tilt/zoom (PTZ) cameras at signalized intersections that do not currently have PTZ
cameras (approximately 57 intersections) in 2022.
S3814
Annual Traffic Signal Projects
Annual appropriation for traffic calming projects
S3816
Traffic Calming
Annual appropriation for the construction of ADA accessible curb ramps.
S3822
Curb Ramps-ADA
Annual appropriation for resurfacing roadways and alleys including asphalt, concrete, and brick.
S3824
Annual Pavement Rehabilitation
This is an annual project to convert overhead electrical systems to underground.
Dubuque Street, Riverside Drive, and Gilbert Street are currently the priority corridors for undergrounding electrical facilities.
S3826
Underground Electrical Facilities
This is an annual project to implement the recommendations of the bicycle master plan. Improvement projects include construction of bike
lanes, bike boulevards, and other features that will improve streets to promote equal access and usability for all modes of transportation.
Projects also fund the conversion of 4-lane roads into 3-lane roads in certain areas that are highly used by all of the various modes of
transportation. Projects are scheduled as follows:
2022 - Keokuk 4 to 3 lane conversion; Gilbert 4 to 3 lane conversion, south of highway 6; Southgate Bike Lanes (Gilbert to Keokuk;
Wetherby Bicycle Boulevard (Lakeside, Sandusky, Taylor, Wetherby); Hollywood Bike Bike Blvd; Lakeside Bicycle Blvd; 2023 - Sunset
Bike Lanes (Benton to Highway 1); Oakcrest Bike Blvd; Emerald Bike Blvd; Arlington Bicycle Blvd; 2024 - Dover /Westminster Bike Blvd;
Highland Bicycle Blvd; 2025 - Church Street Bicycle Blvd; Broadway Bike Lanes (Sandusky to Highway 6); Ridge/Broadway Bike Blvd;
2026 - Washington Street Bike Blvd (Scott Blvd to 1st Avenue); River Bike Blvd; Woolf Bike Blvd; Newton Marked Route
S3827
Bicycle Master Plan Implementation
This provides for the biennial inspection and preservation of Iowa City's bridges including major repairs and restoration. 2019 funding for
this project was moved to the 2nd Avenue Bridge Replacement project.
S3910
Annual Bridge Maintenance & Repair
This project consists of annual sanitary sewer repairs and preventive maintenance throughout the sewer system.
V3101
Annual Sewer Main Replacement
532
TRANSPORTATION SERVICES
Total20222023202420252026DepartmentProject #Priority
T3004 2,650,000650,000 500,000 500,000 500,000 500,000Parking Facility Restoration Repair 1
T3067 600,000120,000 120,000 120,000 120,000 120,000Transit Interchange and Bus Stop Improvements 1
3,250,000770,000 620,000 620,000 620,000 620,000TRANSPORTATION SERVICES
Total
This annual project includes concrete restoration, application of concrete sealants, repair of control and expansion joints in addition to other
parking facility specific repairs.
T3004
Parking Facility Restoration Repair
To improve pedestrian safety and traffic flow at the downtown interchange and improve amenities at transit stops throughout the community
as recommended through the 2019-2020 Transit Study planning process. This project will include annual bus stop repairs and amenity
installations including concrete pads, benches, trash containers, lighting, information amenities, and bike racks.
T3067
Transit Interchange and Bus Stop Improvements
533
Capital Project Funds
Project Listing
Project Page
Airport
A3447 – Airport Parking Lot Expansion…………………………………………………... .. . 537
A3462 – Hangar A Door Replacement……………………………………………………… 537
A3465 - Runway 7 Environmental Assessment ............................................................ 538
A3466 - Runway 7 Extenstion……………………………………………………………….. 539
A3470 – Runway 25 Threshold Relocation…………………………………………………..539
A3471 - Runway 12/30 Threshold Displacement/Relocation……………………………...540
A3473 - Airport Apron Expansion………………………………………………………. ....... 540
A3474 – Runway 7/25 Pavement Repairs……………………………………………….. .... 541
A3475 - Runway 12/30 Pavement Repairs……………………………………………….. .. 541
A3476 - South Hanger Development Apron Expansion……………………………………542
Fire
Z4406 - Fire Apparatus Replacement Program……………………………………………. . 543
Z4409 – Fire Station #1 Apparatus Bay Slab Reconstruction……………………………. 544
Z4410 - Fire Station #1 Carpet/Tile Flooring Replacement………………………………. 545
Z4411 - Fire Station #5 Construction and #3 Replacement……………………………….545
Library
B4343 – Library Carpet and Furnishings Replacement……………………………………..546
B4346 – Automated Material Handler/Sorter……………………………………………….. 547
Parks & Recreation
R4227 - Hwy 6 Trail – Broadway to Fairmeadows………………………………………….548
R4229 - City Park Pool Replacement………………………………………………………...549
R4230 - Splash Pad Improvements…………………………………………………………..550
R4332 - Upgrade Building BAS Controls…………………………………………………….551
R4346 – Palisades & Stone Bridge Park Development……………………………………. 552
R4350 – Chadek Green Park Restrooms and Shelter………………………………………553
R4351 - Recreation Center Improvements…………………………………………………..554
R4357 – Whispering Meadows Shelter & Playground………………………………………555
R4358 – Lower City Park Shelters & Restroom Replacement……………………………..556
R4359 – Kiwanis Park Playground & Shelter Renovation…………………………………..557
R4362 – Napoleon Park Softball Fields 5 – 8 Renovation………………………………….558 R4363 – Upper City Park Shelters & Restroom Replacement……………………………..559
R4365 – Hickory Hill Park Conklin St Shelter & Restrooms……………………………… . 560
R4368 – Court Hill Park Shelter & Playground Replacement………………………………561
R4370 - RAL Pool Filter and HVAC………………………………………………………… . 562
R4371 – Happy Hollow Playground Replacement………………………………………… . 563
R4372 – Terrill Mill Skate Park Redevelopment…………………………………………… . 564
R4374 - Mercer Park Ball Diamond #1 Turf Conversion………………………………… .. 565
R4375 – Hunter’s Run Park Playground & Shelter…………………………………………. 566
R4381 - Event Facility Improvements……………………………………………………... .. 567
R4382 - Off Road Bike Trail Development………………………………………………... .. 568
R4384 - Benton Hill Playground Replacement……………………………………………. . 569
R4385 - College Green Park Playground………………………………………………….. . 569
R4387 - Willow Creek Trail Replacement………………………………………………….. . 570
R4388 - ADA Elevator Improvements………………………………………………………. 571
R4389 – N. Market Square Playground Replacement…………………………………….. 572
R4390 - Reno Street Park Renovations……………………………………………………. 573
R4391 - Tennis Court Renovations…………………………………………………………. 574
R4392 - Westside Park Land Acquisition…………………………………………………... 575
534
Project Page
Police
Y4446 – Digital Photo Evidence Management……………………………………………... 575
Y4447 - Animal Shelter Standy Generator…………………………………………………. 576
Public Works
L3328 - Landfill Equipment Building Replacement……………………………………… ... 577
L3333 – Compost Pad Improvements………………………………………………………. . 578
L3335 – Landfill Dual Extraction System Expansion………………………………………..579
L3338 - Future Landfill Cell Design…………………………………………………………..580
L3340 - Bulk Water Fill Station………………………………………………………………. 581
L3342 - Leachate Lagoon updates…………………………………………………………...581
L3344 - ACM Landfill Gas Infrastructure Expansion………………………………………..582
L3345 - Excavator for Compost Operations…………………………………………………583
M3633 – North Westminster Storm Sewer Upgrades……………………………………….584
M3634 - Rundell Street Pump Station Vault Modifications………………………………...585
M3635 - River Street Storm Sewer Improvements………………………………………….586
P3953 - Equipment Maintenance Facility Replacement……………………………………587
P3987 - Non-Public Safety Radio System Upgrade……………………………………….. 588
P3988 - Entrance Way Improvements………………………………………………………..588
S3939 - Dubuque Street Reconstruction……………………………………………………. 589
S3940 – Kirkwood Avenue to Capitol Street Connection………………………………….. 590
S3946 – Court Street Reconstruction………………………………………………………... 591
S3950 – Rochester Ave Reconstruction – First Ave to Ralston Creek…………………... 592
S3951 – Hwy 1/Hwy 6 Intersection Improvements Study…………………………………. 593
S3952 – Dodge Street Reconstruction – Governor to Burlington………………………... . 594
S3955 - N. Gilbert Street Reconstruction…………………………………………………… 595
S3956 - Gilbert Street Bridge Replacement……………………………………………….. . 596
S3958 - Park Road Reconstruct – Rocky Shore to Riverside…………………………… . 597
S3959 - Taft Avenue Reconstruct – Am Legion to Lwr West Br………………………… . 598
S3960 - Oakdale Blvd Extension – Alignment Study……………………………………... . 599
S3963 - Burlington Street Bridge Replacement…………………………………………… . 600
S3965 - Fairchild Street Reconstruction…………………………………………………… . 601
S3977 - Iowa Avenue Bridge Rehabilitation…………………………………………………602
S3978 - Riverside Dr. Pedestrian Bridge at Iowa Ave Rehab……………………………..603
S3979 - South Dubuque St Reconstruction – Wright to Benton…………………………..604
S3980 - Market & Jefferson Street Two-Way Conversion…………………………………605
V3151 – Digester Complex Rehabilitation…………………………………………………. . 606
V3154 – Hawkeye Lift Station Rehabilitation………………………………………………. . 607
V3155 – Rohret South Sewer……………………………………………………………….. . 608
V3157 - Wastewater Plant Mixer Improvements………………………………………….. .609
V3158 - Biosolids Conveyor Improvements………………………………………………. .. 610
V3162 - Benton Street Trunk Sewer Improvements……………………………………… . 611
V3163 - Aeration Basin Electric & Instrument Improvements…………………………… . 612
V3164 - Return Activated Sludge Pump Replacement…………………………………... . 613
V3165 - Replacement of Influent Pump Station Pumps………………………………….. 614
V3167 - Replace Grit Classifiers……………………………………………………………. . 615
V3169 - Napoleon Lift Station Improvements……………………………………………... . 616
V3170 - WWTP Roof Replacements……………………………………………………….. 617
V3172 - Highlander Lift Station Improvements………………………………….………… . 618
V3173 - Jet Truck Replacement……………………………………………………………. .619
V3174 - Aeration Equipment Improvements………………………………………………. .620
V3175 - Influent Flow Monitoring……………………………………………………………..621
V3176 – Treatment Plant Paving Improvements…………………………………………….622
V3177 - HVAC Replacement…………………………………………………………………623
V3178 - Primary Clarifier Repairs……………………………………………………………624
V3179 - Rotating Drum Thickener Replacement…………………………………………..625
V3180 - Peninsula Control Panel and Pump Improvement……………………………… 626
V3181 - Wastewater Division Master Plan………………………………………………… 627
W3300 – Bradford Drive Water Main Replacement………………………………………... 628 535
Project Page W3313 – Hwy 1 (Hawk Ridge to Walmart) Water Main Replacement……………………. 629
W3314 – High Service Pump VFD Replacement……………………………………………630
W3316 – Chlorine Feeder System Upgrade………………………………………………… 630
W3317 - Water Front Meeting Room A/V Upgrades……………………………………… 631
W3318 - GSR Generator Enclosure Replacement………………………………………….631
W3320 - Hwy 6 (Fairmeadows to Ind Park Rd) Water Main Repl…………………………632
W3321 - Treatment Technology Study……………………………………………………….633
W3322 - Collector Well #2 Cleaning and Upgrade………………………………………….634
W3323 - Water Distribution Asset Inventory…………………………………………………634
W3324 - Water Plant HVAC Study……………………………………………………………635
W3325 - Roof Replacement…………………………………………………………………...635
W3326 - Treatment Process Update………………………………………………………… 636
W3327 - Melrose Water Main Camp Cardinal to 218……………………………………… 636
Senior Center
K1001 – Senior Center Facility Exterior Improvements……………………………………637
K1002 - Senior Center Interior Improvements……………………………………………..638
Transportation & Resource Management
T3021 – Video Cameras for Parking Facilities……………………………………………….639
T3022 – Parking Enforcement Vehicles……………………………………………………… 639
T3023 – Parking Ramp Automated Parking Equipment…………………………………….640
T3025 - Replacement of LED fixtures in Parking Facilities………………………………...640
T3026 - Tower Place Drainage Modifications………………………………………………. 641
T3027 - Parking Ramp Stairwell Roof Replacemet…………………………………………642
T3028 - Tower Place Office Remodel………………………………………………………..642
T3055 – Transit/Equipment Facility Relocation……………………………………………. . 643
536
Description
Expand airport parking to construct additional spaces around the airport beacon circle. Project would create 15-20 additional spaces.
Project #A3447
Priority Efficiency Improvement (3)
Justification
Airport parking is becoming frequently more full as the airport has become better utilized by charter passenger customers and other groups and employees using the
airport. There are now weekly occurances where the parking is 100% full.
Budget Impact/Other
There will be a minor increase in pavement maintenance costs for recurring maintenance/striping and snow and ice removal.
Useful Life 20 years
Project Name Airport Parking Lot Expansion
Category Airport
Type One Phase
Total Project Cost:$75,000
Contact Michael Tharp
Department AIRPORT
MATCH %20%
GRANTEE IDOT
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
10,00010,000PLANNING/DESIGN
65,00065,000CONSTRUCTION
75,000 75,000Total
Total20222023202420252026Funding Sources
63,00063,000OTHER STATE GRANTS
63,000 63,000Total
Prior
12,000
Total
Description
Hangar A door replacement; Hangar A has 10 doors to be replaced. Phase 1 and 2 will replace approximately 4 doors each pending bids. Phase 3 is a future
project.
Project #A3462
Priority Essential (2)
Justification
Hangar building A contains doors that are manual operation on a pulley/counterweight system. These doors are becoming difficult for some tenants to operate, and
are frequently the last hangars to be rented when openings occur. Proposal is to replace the doors with electric motor doors which would enhance the appeal of the
hangar and allow for rates to be in line with other hangars of similar size with motorized doors.
Budget Impact/Other
Minor decrease in operating expenses due to decreased maintenance and repair expenses on the doors. The decrease in operating expenditures is less than $10,000.
Useful Life 50 years
Project Name Hangar A Door Replacement
Category Airport
Type Multi-Phase
Total Project Cost:$94,000
Contact Michael Tharp
Department AIRPORT
MATCH %30%
GRANTEE IDOT
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
19,00019,000PLANNING/DESIGN
75,00075,000CONSTRUCTION
94,000 94,000Total
Total20222023202420252026Funding Sources
19,00019,000AIRPORT FUND
75,00075,000OTHER STATE GRANTS
94,000 94,000Total
3URMHFW6XPPDU\%\1DPH
537
Description
Follow up project from Runway 7/25 Conversion. This is the Environmental Assessment required before constructing an approximately 213 feet extension at the
Runway 7 end of Runway 7/25.
Project #A3465
Priority Critical (1)
Justification
One of the primary comments from pilots was a concern of the landing distance on 7/25. This project is for completion of the Environmental Assessment a future
extension of Runway 7 and stopway without expanding the protection zones.
Budget Impact/Other
The operating impact is negligible.
Useful Life 10 years
Project Name Runway 7 Environmental Assessment
Category Airport
Type One Phase
Total Project Cost:$150,000
Contact Michael Tharp
Department AIRPORT
MATCH %10%
GRANTEE FAA
TIF DISTRICT None
PLAN Airport Master Plan
Status Active
Total20222023202420252026Expenditures
150,000150,000PLANNING/DESIGN
150,000 150,000Total
Total20222023202420252026Funding Sources
15,00015,000AIRPORT FUND
135,000135,000FEDERAL GRANTS
150,000 150,000Total
538
Description
Follow up project from Runway 7/25 Conversion. This is the Environmental Assessment required before constructing an approximately 213 feet extension at the
Runway 7 end of Runway 7/25.
Project #A3466
Priority Essential (2)
Justification
One of the primary comments from pilots was a concern of the landing distance on 7/25. This project is the second part of the 7/25 runway categorical change and
will extend the Runway 7/25 runway by approximately 213 feet.
Budget Impact/Other
This project will add additional runway to clear during inclement weather and to provide additional maintenance and repairs. The estimated additional expenditures
are less than $10,000 per year.
Useful Life 50 years
Project Name Runway 7 Extension (213')
Category Airport
Type One Phase
Total Project Cost:$1,170,000
Contact Michael Tharp
Department AIRPORT
MATCH %10%
GRANTEE FAA
TIF DISTRICT None
PLAN Airport Master Plan
Status Active
Total20222023202420252026Expenditures
235,000235,000PLANNING/DESIGN
935,000935,000CONSTRUCTION
1,170,000 1,170,000Total
Total20222023202420252026Funding Sources
117,000117,000AIRPORT FUND
1,053,0001,053,000FEDERAL GRANTS
1,170,000 1,170,000Total
Description
Runway 25 Threshold Relocation and Re-lighting.
Project #A3470
Priority Critical (1)
Justification
The 808' displaced threshold is no longer required due to change in critical design aircraft. This project shifts the location of the displaced threshold to gain 700 feet
of additional takeoff and landing distance distance for pilots using Runway 25.
Budget Impact/Other
The budget impact of this change is neutral; it does not add or remove existing infrastructure.
Useful Life 20 years
Project Name Runway 25 Threshold Relocation
Category Airport
Type One Phase
Total Project Cost:$566,000
Contact Michael Tharp
Department AIRPORT
MATCH %10%
GRANTEE FAA
TIF DISTRICT None
PLAN Airport Master Plan
Status Active
Total20222023202420252026Expenditures
106,000106,000PLANNING/DESIGN
460,000460,000CONSTRUCTION
566,000 566,000Total
Total20222023202420252026Funding Sources
414,000414,000FEDERAL GRANTS
414,000 414,000Total
Prior
152,000
Total
539
Description
Runway 12 Threshold Displacement - Runway 30 Threshold Relocation
Project #A3471
Priority Critical (1)
Justification
The Airport Master Plan completed in 2016 identifies a threshold displacement on Runway 12 of 500 feet to minimize the number of potential obstructions to the
Runway 12 approach. The plan mitigated the impactes to Runway 12/30 by adding length to the Runway 30 end that is available for takeoff but not for landings.
Budget Impact/Other
This project will add minor paving maintenance expenses due to the added pavement at Runway 30.
Useful Life 20 years
Project Name Runway 12/30 Threshold Displacement/Relocation
Category Airport
Type One Phase
Total Project Cost:$397,250
Contact Michael Tharp
Department AIRPORT
MATCH %10%
GRANTEE FAA
TIF DISTRICT None
PLAN Airport Master Plan
Status Active
Total20222023202420252026Expenditures
72,25072,250PLANNING/DESIGN
325,000325,000CONSTRUCTION
397,250 397,250Total
Total20222023202420252026Funding Sources
32,50032,500AIRPORT FUND
357,525357,525FEDERAL GRANTS
390,025 390,025Total
Prior
7,225
Total
Description
This project adds additonal apron space for aircraft parking.
Project #A3473
Priority Essential (2)
Justification
Larger aircraft utilizing the airport require hard surface parking. Our exisiting ramp is too small based on FAA formulas for operations and parking. This project
provides additional parking space to support those aircraft types.
Budget Impact/Other
The operating impact will be increased costs for snow removal and maintenance due to increased surface pavement. The estimated increase in operating
expenditures is less than $10,000.
Useful Life 20 years
Project Name Airport Apron Expansion
Category Airport
Type One Phase
Total Project Cost:$1,250,000
Contact Michael Tharp
Department AIRPORT
MATCH %10%
GRANTEE FAA
TIF DISTRICT None
PLAN Airport Master Plan
Status Active
Total20222023202420252026Expenditures
375,000375,000PLANNING/DESIGN
875,000875,000CONSTRUCTION
1,250,000 1,250,000Total
Total20222023202420252026Funding Sources
125,000125,000AIRPORT FUND
1,125,0001,125,000FEDERAL GRANTS
1,250,000 1,250,000Total
540
Description
Runway 7/25 joint sealant and miscellaneous pavement repairs.
Project #A3474
Priority Essential (2)
Justification
Pavement repair work required as part of upkeep of airport runways.
Budget Impact/Other
Neutral budget affect to maintain pavement condition.
Useful Life 15 years
Project Name Runway 7/25 Pavement Repairs
Category Airport
Type One Phase
Total Project Cost:$250,000
Contact Michael Tharp
Department AIRPORT
MATCH %10%
GRANTEE FAA
TIF DISTRICT None
PLAN Airport Master Plan
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
200,000200,000CONSTRUCTION
250,000 250,000Total
Total20222023202420252026Funding Sources
25,00025,000AIRPORT FUND
225,000225,000FEDERAL GRANTS
250,000 250,000Total
Description
Runway 12/30 joint sealant and miscellaneous pavement repairs.
Project #A3475
Priority Essential (2)
Justification
Pavement repair work required as part of upkeep of airport runways.
Budget Impact/Other
Neutral budget affect to maintain pavement condition.
Useful Life 15 years
Project Name Runway 12/30 Pavement Repairs
Category Airport
Type One Phase
Total Project Cost:$200,000
Contact Michael Tharp
Department AIRPORT
MATCH %10%
GRANTEE FAA
TIF DISTRICT None
PLAN Airport Master Plan
Status Active
Total20222023202420252026Expenditures
20,00020,000PLANNING/DESIGN
180,000180,000CONSTRUCTION
200,000 200,000Total
Total20222023202420252026Funding Sources
20,00020,000AIRPORT FUND
180,000180,000FEDERAL GRANTS
200,000 200,000Total
541
Description
Install concrete apron/taxilanes for privately funded hangar development south of existing T-hangars.
Project #A3476
Priority Critical (1)
Justification
Airport Commission has sought to jumpstart an effort to get private investment into hangar construction by completing the necessary infrastructure to allow for
hangar construction to take place. This construction lays the work for multiple possible units in the area south of the existing south t-hangar complex.
Budget Impact/Other
Increased revenue from ground leases for new hangar space.
Useful Life 20 years
Project Name South Hanger Development Apron Expansion
Category Airport
Type One Phase
Total Project Cost:$413,750
Contact Michael Tharp
Department AIRPORT
MATCH %10%
GRANTEE FAA
TIF DISTRICT None
PLAN Airport Master Plan
Status Active
Total20222023202420252026Expenditures
70,00070,000PLANNING/DESIGN
343,750343,750CONSTRUCTION
413,750 413,750Total
Total20222023202420252026Funding Sources
62,06362,063AIRPORT FUND
351,687351,687FEDERAL GRANTS
413,750 413,750Total
542
Description
Replacement of Fire Department equipment:
2024 Fire Pumper/Aerial #358
2024 Scotty House
2026 Fire Pumper #352
2027 Fire Pumpers #353 & #354
Project #Z4406
Priority Critical (1)
Justification
The department recommends replacement per the established schedule as it is anticipated Fleet Management Scoring will indicate apparatus exceeding scoring
thresholds. The Fire Safety House is used to promote fire safety education throughout the community.
Budget Impact/Other
The operating expenses for the City should decrease due to the replacement of older equipment with newer equipment. The estimated decrease in operating
expenses is less than $10,000.
Useful Life 16 years
Project Name Fire Apparatus Replacement Program
Category Fire
Type Multi-Phase
Total Project Cost:$7,755,000
Contact John Grier
Department FIRE
MATCH %VARIES
GRANTEE U OF I
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
2,560,0001,360,000 1,200,000EQUIPMENT
1,360,000 1,200,000 2,560,000Total
Prior
2,795,000
Total
Future
2,400,000
Total
Total20222023202420252026Funding Sources
48,00048,000GENERAL FUND
2,000,0001,040,000 960,000GO BONDS-ESSENTIAL
PURPOSE
512,000272,000 240,000UNIVERSITY OF IOWA
1,360,000 1,200,000 2,560,000Total
Prior
2,795,000
Total
Future
2,400,000
Total
543
Description
This project will reconstruct the floor slab in the apparatus bay of Fire Station 1.
Project #Z4409
Priority Essential (2)
Justification
The slab is nearing the end of its useful life and is developing large cracks.
Budget Impact/Other
The impact on the operating budget is negligible.
Useful Life 50 years
Project Name Fire Station #1 Apparatus Bay Slab Reconstruction
Category Fire
Type One Phase
Total Project Cost:$95,000
Contact John Grier
Department FIRE
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
7,5007,500PLANNING/DESIGN
75,00075,000CONSTRUCTION
2,5002,500INSPECTION
2,5002,500ADMINISTRATION
7,5007,500CONTINGENCY
95,000 95,000Total
Total20222023202420252026Funding Sources
95,00095,000GO BONDS-GENERAL
PURPOSE
95,000 95,000Total
544
Description
This project will replace the carpet and tile flooring throughout Fire Station 1.
Project #Z4410
Priority Essential (2)
Justification
The flooring is nearing the end of its useful life and is fade and developing worn/torn spots.
Budget Impact/Other
The impact on the operating budget is negligible.
Useful Life 15 years
Project Name Fire Station #1 Carpet/Tile Flooring Replacement
Category Fire
Type One Phase
Total Project Cost:$62,800
Contact John Grier
Department FIRE
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
5,0005,000PLANNING/DESIGN
48,00048,000CONSTRUCTION
5,0005,000ADMINISTRATION
4,8004,800CONTINGENCY
62,800 62,800Total
Total20222023202420252026Funding Sources
62,80062,800GENERAL FUND
62,800 62,800Total
Description
The project is to construct a new Fire Station #5 and construct a new replacement Fire Station #3.
Project #Z4411
Priority Essential (2)
Justification
The City is continuing to grow and expand which increases to need to add fire stations and reposition them for the changes in the City coverage areas in order to
meet demand and maintain appropriate response times.
Budget Impact/Other
Fire Station #5 will require new staffing, equipment, and facilities which will require considerable additional annual expenditures. The replacement of Fire Station
#3 will most likely also increase annual operating expenditures even though it may be more efficient, it will require more costly insurance coverage and operating
costs. The estimated increase in annual operating expenditures is $600,000 per year.
Useful Life 40 Years
Project Name Fire Station #5 Construction and #3 Replacement
Category Fire
Type One Phase
Total Project Cost:$500,000
Contact John Grier
Department FIRE
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
500,000500,000PLANNING/DESIGN
500,000 500,000Total
Total20222023202420252026Funding Sources
500,000500,000FACILITY REPLACEMENT
RESERVE
500,000 500,000Total
545
Description
A multi-year project to replace carpeting and some furnishings in large areas of the Library. First floor has 31,000 square feet of carpet and second floor has
39,000. Project includes updates for carpet, demo and floor prep, moving, GC, insurance, fees, bonds, and contingency. In addition, some of the original
furnishings, including casual seating and gallery furnishings will be replaced. An emphasis on sustainable, durable materials and flexible space-making will steer
this project.
Project #B4343
Priority Essential (2)
Justification
Since the building opened in 2004, more than 9,500,000 people have come through the doors. The Library is a heavily visited public space in the heart of
downtown; ongoing investment in the building is necessary to ensure a safe and attractive space is maintained. While this project falls under the "Aesthetic
Improvement" priority right now, failure to complete this work in a timely manner will result in safety and efficiency issues in the future, which could lead to more
costly unplanned repairs.
Budget Impact/Other
This project will save minor costs associated with carpet repair but is less than $10,000/year.
Useful Life 15 years
Project Name Carpet and Furnishings Replacement
Category Library
Type Multi-Phase
Total Project Cost:$775,000
Contact Elsworth Carman
Department LIBRARY
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
775,000375,000 400,000EQUIPMENT
375,000 400,000 775,000Total
Total20222023202420252026Funding Sources
775,000375,000 400,000GENERAL FUND
375,000 400,000 775,000Total
546
Description
Design and install an Automated Material Handler; specifically a six-bin sorter with 2 internal patron inlets and 1 staff inlet. Estimated cost includes all shipping,
installation, and staff training.
Project #B4346
Priority Efficiency Improvement (3)
Justification
The Library was built to accommodate an Automated Material Handler (AMH) in the returns area/circulation workroom on the first floor. Our circulation system
includes use of RFID tagging. Adding an AMH to ICPL’s workflow would significantly reduce the number of times a material is handled throughout the circulation
process by automating several parts of check-in and check-out procedures. It would also allow for more accurate data collection related to physical collection use
and allow staff hours to be allocated to other critical services. Combined, this would result in increased access to materials for library users.
Budget Impact/Other
Despite a significant up-front cost, AMH's lead to a reduction in staff hours related to check-in and check-out procedures and increased efficiancy overall (reducing
costs related to manually managing material searching and locating). The estimated annual cost savings is less than $10,000 per year.
Useful Life 30 Years
Project Name Automated Material Handler/Sorter
Category Library
Type One Phase
Total Project Cost:$150,000
Contact Elsworth Carman
Department LIBRARY
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
150,000150,000CONSTRUCTION
150,000 150,000Total
Total20222023202420252026Funding Sources
150,000150,000GENERAL FUND
150,000 150,000Total
547
Description
Construction of sidepath extension along Hwy 6 between Broadway Street and Fairmeadows Blvd and along First Avenue from the south side of Hwy 6 to Lower
Muscatine Road.
Project #R4227
Priority Non-essential (5)
Justification
This project is an extension of the Hwy 6 sidepath and is an integral piece of the planned trail network. The project appears in MPOJC documents as a 'future'
sidewalk and also appears in the adopted 2017 Iowa City Bicycle Master Plan. This project also meets the Council's Strategic Plan goal of 'Enhancing Community
Mobility' by substantially improving the sidewalk network. This is the last major segment of missing Hwy 6 trail and connects to the 2021 CIP funded segment
between Heinz and Fairmeadows.
Budget Impact/Other
This project will add 4,800 feet of sidepath to the Parks & Recreation Department snow plowing, mowing, and general maintenance expenses. Additional operating
expenditures are estimated to be approximately than $10,000 per year.
Useful Life 40 Years
Project Name Hwy 6 Sidepath - Broadway to Fairmeadows
Category Parks Maintenance
Type One Phase
Total Project Cost:$1,700,000
Contact Kent Ralston
Department PARKS & RECREATION
MATCH %VARIES
GRANTEE TRAILS GRANT
TIF DISTRICT None
PLAN Bike Master Plan
Status Active
Total20222023202420252026Expenditures
200,000200,000PLANNING/DESIGN
1,500,0001,500,000CONSTRUCTION
200,000 1,500,000 1,700,000Total
Total20222023202420252026Funding Sources
520,000520,000FEDERAL GRANTS
1,180,0001,180,000GO BONDS-ESSENTIAL
PURPOSE
1,700,000 1,700,000Total
548
Description
Replace City Park Pool with new outdoor swimming pool and bathhouse.
Project #R4229
Priority Efficiency Improvement (3)
Justification
City Park Pool is an Iowa City landmark and tradition. However, due to its advancing age it will need to be replaced with a more modern facility.
Budget Impact/Other
This project will increase annual operating expenditures for insurance and utilities, but will also require lower maintenance and upkeep. The net increase in
operating expenditures is estimated between $15,000 and $25,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 40 Years
Project Name City Park Pool Replacement
Category Recreation
Type One Phase
Total Project Cost:$6,000,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Recreation Master Plan
Status Active
Total20222023202420252026Expenditures
500,000500,000PLANNING/DESIGN
5,000,0005,000,000CONSTRUCTION
500,000500,000CONTINGENCY
500,000 5,500,000 6,000,000Total
Total20222023202420252026Funding Sources
5,300,000500,000 4,800,000FACILITY REPLACEMENT
RESERVE
700,000700,000GO BONDS-GENERAL
PURPOSE
500,000 5,500,000 6,000,000Total
549
Description
Renovate splash pads at Wetherby Park and Fairmeadows Park with new features which will replace the current features, but not change the underground
infrastructure.
Project #R4230
Priority Essential (2)
Justification
Wetherby Park and Fairmeadows Park splash pads have aging equipment and spray features.
Budget Impact/Other
These renovations will have a negligible impact on the operating budget.
Useful Life 20 years
Project Name Splash Pad Improvements
Category Recreation
Type Multi-Phase
Total Project Cost:$100,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Recreation Master Plan
Status Active
Total20222023202420252026Expenditures
10,00010,000PLANNING/DESIGN
90,00090,000CONSTRUCTION
100,000 100,000Total
Total20222023202420252026Funding Sources
100,000100,000GENERAL FUND
100,000 100,000Total
550
Description
Upgrade or add Building Automation Systems (BAS) for multiple municipal structures: Senior Center, and Animal Care and Adoption Center. This will include
panel upgrades to current controls software, field devices to be compatible with new controls, installation of new controllers, VFDs, perimeter heat temp sensors, gas
CO and NO@ compatible sensors, DDC programming and pathways for conduit, cables & wired per current code.
Project #R4332
Priority Efficiency Improvement (3)
Justification
The building controls in the facilities need to be updated to work with the current BAS software system. Systems like Senior Center is dated and no longer
servicable without a technician from out of state.
Budget Impact/Other
This project will significantly reduce operating costs and energy consumption in multiple facilities. Typical average annual energy savings on projects of this type
range 8-12% of the cost of the project. Estimated savings is $30,000 per year.
Useful Life 15 years
Project Name Upgrade Building BAS Controls
Category Government Buildings
Type Multi-Phase
Total Project Cost:$835,000
Contact Kumi Morris
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
10,00010,000PLANNING/DESIGN
180,000180,000CONSTRUCTION
2,0002,000ADMINISTRATION
13,00013,000CONTINGENCY
205,000 205,000Total
Prior
630,000
Total
Total20222023202420252026Funding Sources
205,000205,000GO BONDS-GENERAL
PURPOSE
205,000 205,000Total
Prior
630,000
Total
551
Description
Funding to develop a new neighborhood park in an emerging or underserved location. The City owns several parcels designated for parks and developments are
completed.
Project #R4346
Priority Essential (2)
Justification
The 2017 Park Master plan points to a districts with deficiencies in park land. This project will be designed to develop a new neighborhood park in a growing or
underserved neighborhood as the opportunity becomes available.
Budget Impact/Other
This project will increase operating expenditures due to the addition of new park amenities and finished park land. The estimated increase in operating expenditures
is $20,000 per year.
Useful Life 20 years
Project Name Palisades or Stone Bridge Park Development
Category Parks Maintenance
Type One Phase
Total Project Cost:$700,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
60,00030,000 30,000PLANNING/DESIGN
600,000300,000 300,000CONSTRUCTION
10,0005,000 5,000INSPECTION
10,0005,000 5,000ADMINISTRATION
20,00010,000 10,000CONTINGENCY
350,000 350,000 700,000Total
Total20222023202420252026Funding Sources
700,000350,000 350,000GENERAL FUND
350,000 350,000 700,000Total
552
Description
Build picnic shelter, playground, accessible paths and parking at Chadek Green Park community gardens.
Project #R4350
Priority Essential (2)
Justification
The 2017 Park Master Plan recommends these park improvement projects to address park needs in the community.
Budget Impact/Other
This project will increase the annual operating expenditures due to the additional restroom, shelter and playground. The estimated increase is less than $10,000 per
year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 20 years
Project Name Chadek Green Park Playground & and Shelter
Category Parks Maintenance
Type One Phase
Total Project Cost:$450,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
350,000350,000CONSTRUCTION
10,00010,000INSPECTION
30,00030,000CONTINGENCY
390,000 390,000Total
Prior
60,000
Total
Total20222023202420252026Funding Sources
450,000450,000GO BONDS-ESSENTIAL
PURPOSE
450,000 450,000Total
553
Description
This project is planning for renovations for the City's recreation enters: Robert A. Lee (RALRC) and Mercer Pool/Scanlon Gym.
2023 - Upper Level RALRC: ADA compliant single user public restrooms, ADA compliant offices, door and signage needs. Catering kitchen to be relocated to the
Social Hall. 2024 - RALRC: renovate Lower Level locker rooms; Mercer/Scanlon: renovate lobby, restrooms, and meeting rooms. Future: Renovate
Mercer/Scanlon locker rooms
Project #R4351
Priority Critical (1)
Justification
Presently there are critical and public use areas of the recreation facilities do not meet the current ADA standards. Parts of the facilities are still operating from their
original design. These improvements will update and bring the facilities into closer compliance with ADA requirements and improve operational efficiencies in
their use for both the public and the staff. These recommendations were cited in the 2012 Space Needs Study and Master Plan and the Facility ADA study.
Budget Impact/Other
This project would reduce maintenance and repair expenditures due to the replacement of older infrastructure. The estimated annual reduced operating expenditures
is less than $10,000 per year.
Useful Life 25 years
Project Name Recreation Center Improvements
Category Government Buildings
Type Multi-Phase
Total Project Cost:$950,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Facilities Master Plan
Status Active
Total20222023202420252026Expenditures
70,00020,000 50,000PLANNING/DESIGN
775,000200,000 575,000CONSTRUCTION
40,00015,000 25,000ADMINISTRATION
65,00015,000 50,000CONTINGENCY
250,000 700,000 950,000Total
Total20222023202420252026Funding Sources
950,000250,000 700,000GO BONDS-GENERAL
PURPOSE
250,000 700,000 950,000Total
554
Description
Ecological restoration work in Whispering Meadows Park.
Project #R4357
Priority Essential (2)
Justification
The Natural Areas Master Plan identified public areas and park lands that could provide improved ecological benefit to the City through additional natural
plantings, prairie grass, controlled burns, or other improvements.
Budget Impact/Other
This will be an addition of park natural plantings. Maintenance and operation will need to be absorbed into current park staff duties. Estimated impact on
operating expenditures is less than $10,000 per year.
Useful Life 20 years
Project Name Whispering Meadows Park Ecological Restoration
Category Parks Maintenance
Type One Phase
Total Project Cost:$250,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE REAP
TIF DISTRICT None
PLAN Natural Areas Master Plan
Status Active
Total20222023202420252026Expenditures
10,00010,000PLANNING/DESIGN
125,000125,000CONSTRUCTION
2,5002,500INSPECTION
2,5002,500ADMINISTRATION
10,00010,000CONTINGENCY
150,000 150,000Total
Prior
100,000
Total
Total20222023202420252026Funding Sources
150,000150,000GENERAL FUND
150,000 150,000Total
Prior
100,000
Total
555
Description
This project will demolish six picnic shelters and one restroom in Lower City Park and replace these with one large and two small shelters and restroom facility.
The remaining facilities will be in locations outlined in Lower City Park Master Plan.
Project #R4358
Priority Essential (2)
Justification
The shelters and restrooms in Lower City Park are quickly reaching the end of their serviceable life. Some are in areas that are prone to regular flooding. This
project follows recommendations of the 2016 Lower City Park Master Plan and 2017 Park Master Plan while repositioning and resizing the shelters to meet current
and future use patterns.
Budget Impact/Other
No impact on operating budget as these are replacements for current facilities.
Useful Life 20 years
Project Name Lower City Park Shelters & Restroom Replacement
Category Parks Maintenance
Type One Phase
Total Project Cost:$600,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Lower City Park Master Plan
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
490,000490,000CONSTRUCTION
10,00010,000INSPECTION
50,00050,000CONTINGENCY
600,000 600,000Total
Total20222023202420252026Funding Sources
600,000600,000GO BONDS-ESSENTIAL
PURPOSE
600,000 600,000Total
556
Description
Renovate Nature Play Area, replace shelter, add accessible paths and opportunities for creek access at Kiwanis Park.
Project #R4359
Priority Essential (2)
Justification
Kiwanis playground was installed in 1999. The 2017 Park Master Plan prioritizes renovation of the nature play area, shelter and accessible paths.
Budget Impact/Other
No impact on operating budget as these are replacements for current facilities.
Useful Life 20 years
Project Name Kiwanis Park Playground & Shelter Renovation
Category Parks Maintenance
Type One Phase
Total Project Cost:$425,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
30,00030,000PLANNING/DESIGN
355,000355,000CONSTRUCTION
5,0005,000INSPECTION
5,0005,000ADMINISTRATION
30,00030,000CONTINGENCY
425,000 425,000Total
Total20222023202420252026Funding Sources
425,000425,000GO BONDS-ESSENTIAL
PURPOSE
425,000 425,000Total
557
Description
This project will renovate and enhance fields 5-8 at the Napoleon Park Softball Complex. The project will include the laser grading infields, the addition of
drainage tile, and new outfield turf.
Project #R4362
Priority Efficiency Improvement (3)
Justification
In 2013 we completed this process on fields 1-4 at Napoleon. Fields 5-8 currently have water retention and playbility issues that present maintenance and play
challenges thus limiting their use.
Budget Impact/Other
The operating budget for this facility will remain the same.
Useful Life 10 years
Project Name Napoleon Park Softball Fields 5-8 Renovation
Category Parks Maintenance
Type One Phase
Total Project Cost:$450,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
380,000380,000CONSTRUCTION
5,0005,000INSPECTION
15,00015,000CONTINGENCY
450,000 450,000Total
Total20222023202420252026Funding Sources
450,000450,000GO BONDS-GENERAL
PURPOSE
450,000 450,000Total
558
Description
In 2023, a Upper City Park master plan will be developed. In 2024, Upper City Park improvements will be constructed which may include demolition of four picnic
shelters and one restroom in Upper City Park and replacement with one large and two small shelters and restroom facility.
Project #R4363
Priority Essential (2)
Justification
The shelters and restrooms in Upper City Park are quickly reaching the end of their serviceable life. This project follows recommendations of the 2017 Park Master
Plan while repositioning and resizing the shelters to meet current and future use patterns.
Budget Impact/Other
No impact on operating budget as these are replacements for current facilities.
Useful Life 20 years
Project Name Upper City Park Improvements
Category Parks Maintenance
Type One Phase
Total Project Cost:$600,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
500,000500,000CONSTRUCTION
5,0005,000INSPECTION
5,0005,000ADMINISTRATION
40,00040,000CONTINGENCY
50,000 550,000 600,000Total
Total20222023202420252026Funding Sources
600,000600,000GO BONDS-ESSENTIAL
PURPOSE
600,000 600,000Total
559
Description
Replace picnic shelter and restrooms at Conklin Street entrance to Hickory Hill Park.
Project #R4365
Priority Essential (2)
Justification
The rest rooms and shelter at this location were noted as poor condition with a number of accessibility concerns in the restrooms by the 2017 Park Master Plan. The
plan recommended replacement of these facilties. This also follows recommendations of the 2016 Hickory Hill Park Master Plan.
Budget Impact/Other
No impact on operating budget as these are replacements for current facilities.
Useful Life 20 years
Project Name Hickory Hill Park Conklin St Shelter & Restrooms
Category Parks Maintenance
Type One Phase
Total Project Cost:$245,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
20,00020,000PLANNING/DESIGN
200,000200,000CONSTRUCTION
2,5002,500INSPECTION
2,5002,500ADMINISTRATION
20,00020,000CONTINGENCY
245,000 245,000Total
Total20222023202420252026Funding Sources
245,000245,000GO BONDS-ESSENTIAL
PURPOSE
245,000 245,000Total
560
Description
Replace playground and two picnic shelters at Court Hill Park. Project also adds concrete paths for increased accessibility and additional opportunities for creek
access.
Project #R4368
Priority Essential (2)
Justification
The playground and shelter were installed in 1994 and are nearing the end of their servicable life. The play area lacks accessible paths and safety surface. The 2017
Park Master Plan recommends replacement. This park also presents opportunities to provide access to Ralston Creek for play and exploration.
Budget Impact/Other
This project will sligtly increase park maintenance need through the addition of park amenities. The estimate increase on operating expenditures is less than
$10,000 per year.
Useful Life 20 years
Project Name Court Hill Park Shelter & Playground Replacement
Category Parks Maintenance
Type One Phase
Total Project Cost:$450,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
30,00030,000PLANNING/DESIGN
390,000390,000CONSTRUCTION
10,00010,000INSPECTION
20,00020,000CONTINGENCY
450,000 450,000Total
Total20222023202420252026Funding Sources
450,000450,000GO BONDS-ESSENTIAL
PURPOSE
450,000 450,000Total
561
Description
This project would include the replacement of the existing pool filters, the addition of a UV system, and a new pool dehumidification system at the Robert A. Lee
Recreation Center swimming pool.
Project #R4370
Priority Essential (2)
Justification
The current filters are past there life expectancy and are contributing to water quality issues. The dehumidification system will help with pool comfort level and air
quality. The UV system is an additional disinfectant for pool water and standard for new pools and pool renovations.
Budget Impact/Other
Operating costs should decrease slightly due to better monitoring of pool chemicals and water use from new equipment and software. Expected annual savings is
less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 25 years
Project Name Robert A. Lee Recreation Center Pool Filter & HVAC
Category Government Buildings
Type One Phase
Total Project Cost:$700,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Facilities Master Plan
Status Active
Total20222023202420252026Expenditures
600,000600,000CONSTRUCTION
40,00040,000CONTINGENCY
640,000 640,000Total
Prior
60,000
Total
Total20222023202420252026Funding Sources
700,000700,000GO BONDS-GENERAL
PURPOSE
700,000 700,000Total
562
Description
Playground replacement at Happy Hollow Park.
Project #R4371
Priority Essential (2)
Justification
The playground is scheduled for replacement in the 2017 Park Master Plan due to age and condition.
Budget Impact/Other
No impact on operating budget as these are replacements for current facilities.
Useful Life 20 years
Project Name Happy Hollow Playground Replacement
Category Parks Maintenance
Type One Phase
Total Project Cost:$175,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
5,0005,000PLANNING/DESIGN
155,000155,000CONSTRUCTION
2,5002,500INSPECTION
2,5002,500ADMINISTRATION
10,00010,000CONTINGENCY
175,000 175,000Total
Total20222023202420252026Funding Sources
175,000175,000GO BONDS-ESSENTIAL
PURPOSE
175,000 175,000Total
563
Description
This project renovates the skate park and adds access paths.
Project #R4372
Priority Essential (2)
Justification
The skatepark is nearing an age where replacement is necessary for it to continue to draw skaters as well as for improved maintenance and safety. This project will
nenovate the skateboard park area and expand the facility to include a pump track for BMX bicycle and other roller sport use.
Budget Impact/Other
The budget impact of this project is negligible as it replaces outdated infrastructure and adds a minimal amount of new infrastructure.
Useful Life 20 years
Project Name Terrell Mill Skate Park Redevelopment
Category Parks Maintenance
Type One Phase
Total Project Cost:$1,250,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
100,000100,000PLANNING/DESIGN
1,050,0001,050,000CONSTRUCTION
10,00010,000INSPECTION
10,00010,000ADMINISTRATION
80,00080,000CONTINGENCY
1,250,000 1,250,000Total
Total20222023202420252026Funding Sources
600,000600,000FEDERAL GRANTS
650,000650,000GO BONDS-GENERAL
PURPOSE
1,250,000 1,250,000Total
564
Description
First phase will implement field playability enhancements, safety improvements, and increased accessibility. The second phase will include new fence lines, shade
structures and complex amenities. This includes the concession area, entrance and plaza area.
Project #R4374
Priority Efficiency Improvement (3)
Justification
Hitchcock Design has been contracted to evaluate the complex for draining, safety and access priorities. Mercer Park Ball Diamond 1 is the premier large field in
our system. It is used primarily by City High for varsity baseball and adult baseball league rentals. The proposed improvements will improve field drainage, player
safety, and accessibility limitations.
Budget Impact/Other
The conversion to synthetic turf would decrease continuing maintenance costs and allow for increased play through a longer season. The effect on the operating
budget would be positive, and is expected to be between $10,000 and $20,000 per year.
Useful Life 15 years
Project Name Mercer Park Ball Diamond Improvements
Category Parks Maintenance
Type Multi-Phase
Total Project Cost:$1,050,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %VARIES
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
55,00055,000PLANNING/DESIGN
810,000810,000CONSTRUCTION
45,00045,000ADMINISTRATION
40,00040,000CONTINGENCY
950,000 950,000Total
Prior
100,000
Total
Total20222023202420252026Funding Sources
250,000250,000GENERAL FUND
700,000700,000GO BONDS-GENERAL
PURPOSE
950,000 950,000Total
Prior
100,000
Total
565
Description
Replace playground and one shelter, and adds additional access paths from street and sidewalk.
Project #R4375
Priority Essential (2)
Justification
Project is prioritized in the 2017 Park Master Plan based on age and condition of current structures.
Budget Impact/Other
No impact on operating budget as these are replacements for current facilities.
Useful Life 20 years
Project Name Hunter's Run Park Playground & Shelter
Category Parks Maintenance
Type One Phase
Total Project Cost:$300,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
25,00025,000PLANNING/DESIGN
250,000250,000CONSTRUCTION
2,5002,500INSPECTION
2,5002,500ADMINISTRATION
20,00020,000CONTINGENCY
300,000 300,000Total
Total20222023202420252026Funding Sources
300,000300,000GO BONDS-ESSENTIAL
PURPOSE
300,000 300,000Total
566
Description
On-going repairs and improvements at Terry Trueblood Lodge, Terry Trueblood concession building, Ashton House Event Facility and Riverside Festival stage.
Roof and façade repairs to Riverside Festival Stage, Exterior staining of TTRA Lodge & Concession buildings, BAS replacement Ashton & TTRA, Audio Visio
Equipment Upgrades.
Project #R4381
Priority Essential (2)
Justification
These facilities are maintained for city events and private event rentals. Renovations are needed as they buildings age.
Budget Impact/Other
This project should have a minimal impact on the annual operating budget.
Useful Life 20 years
Project Name Event Facility Improvements
Category Government Buildings
Type One Phase
Total Project Cost:$300,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
30,0005,000 25,000PLANNING/DESIGN
245,00045,000 200,000CONSTRUCTION
5,0005,000ADMINISTRATION
20,00020,000CONTINGENCY
50,000 250,000 300,000Total
Total20222023202420252026Funding Sources
300,00050,000 250,000GENERAL FUND
50,000 250,000 300,000Total
567
Description
Build off-road "single track" trail course for biking on site recently acquired from Elks Golf Course.
Project #R4382
Priority Non-essential (5)
Justification
Bicycling is a growing activity in the area. This course will provide area for new off-road cyclists to learn the sport and more experienced bicyclist to practice and
compete. This supports the 2017 Park Master Plan which has a goal that all Iowa City children learn bicycle skills and add the growing collection of similar
facilities in the region acting as a tourist destination.
Budget Impact/Other
Facility will require maintenance similar to other trails and disc golf areas. No new staff are anticipated. Estimated annual maintenance costs are less than $10,000
per year.
Useful Life 20 years
Project Name Off Road Bike Trail Development
Category Parks Maintenance
Type One Phase
Total Project Cost:$180,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
15,00015,000PLANNING/DESIGN
150,000150,000CONSTRUCTION
5,0005,000INSPECTION
10,00010,000CONTINGENCY
180,000 180,000Total
Total20222023202420252026Funding Sources
180,000180,000GENERAL FUND
180,000 180,000Total
568
Description
This project replaces the playground at Benton HIll Park. Site constraints keep this as a smaller piece of equipment.
Project #R4384
Priority Essential (2)
Justification
Playground replacement following Park Master Plan. Playground reaching end of servicable life.
Budget Impact/Other
No impact on operating budget as this replaces current infrastructure.
Useful Life 20 years
Project Name Benton Hills Playground Replacement
Category Parks Maintenance
Type One Phase
Total Project Cost:$135,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
5,0005,000PLANNING/DESIGN
125,000125,000CONSTRUCTION
5,0005,000CONTINGENCY
135,000 135,000Total
Total20222023202420252026Funding Sources
135,000135,000GENERAL FUND
135,000 135,000Total
Description
This project replaces the playground at College Green Park.
Project #R4385
Priority Essential (2)
Justification
Playground replacement following Park Master Plan. Playground reaching end of servicable life.
Budget Impact/Other
No impact on operating budget as this replaces current infrastructure.
Useful Life 20 years
Project Name College Green Park Playground
Category Parks Maintenance
Type One Phase
Total Project Cost:$350,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
25,00025,000PLANNING/DESIGN
285,000285,000CONSTRUCTION
15,00015,000INSPECTION
25,00025,000CONTINGENCY
350,000 350,000Total
Total20222023202420252026Funding Sources
350,000350,000GO BONDS-ESSENTIAL
PURPOSE
350,000 350,000Total
569
Description
The Willow Creek trail spanning 0.8 miles from Benton St to Willow Creek Dr including a spur of the trail connecting to Aber Ave is in need of replacement.
Project #R4387
Priority Essential (2)
Justification
This trail is crumbling in many locations and will soon be unsafe to use. Patching has occurred as a temporary fix but a complete replacement is necessary. Project
request includes 10 ft wide concrete trail on the same footprint as the existing .8 mile trail. Cost estimate mirrors estimate for construction of Hwy 6 trail section
from Fairmeadows to Heinz because it is the same length.
Budget Impact/Other
This project will slightly lower the operating budget to less maintenance and upkeep from replacing older infrastructure with newer infrastructure. The esimated
annual cost savings is less than $10,000.
Useful Life 20 years
Project Name Willow Creek Trail Replacement
Category Parks Maintenance
Type One Phase
Total Project Cost:$575,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
65,00065,000PLANNING/DESIGN
418,000418,000CONSTRUCTION
21,00021,000INSPECTION
21,00021,000ADMINISTRATION
50,00050,000CONTINGENCY
65,000 510,000 575,000Total
Total20222023202420252026Funding Sources
575,000575,000GO BONDS-GENERAL
PURPOSE
575,000 575,000Total
570
Description
Update elevators in City Hall, Senior Center, Robert A. Lee Recreation Center with ADA operating system improvements including braille and visible and verbal
signals to indicate which elevator car is available, its direction, and when it has reached a designated floor.
Project #R4388
Priority Critical (1)
Justification
Presently these elevators do not meet the current ADA standards. These recommendations were cited in the 2012 Space Needs Study and Master Plan and the
Facility ADA study.
Budget Impact/Other
This project will lower annual operating expenditures due to the replacement of older equipment with new equipment. The estimated annual savings is less than
$10,000 per year.
Useful Life 10 years
Project Name ADA Elevator Improvements
Category Government Buildings
Type One Phase
Total Project Cost:$250,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Facilities Master Plan
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
200,000200,000CONSTRUCTION
50,000 200,000 250,000Total
Total20222023202420252026Funding Sources
250,00050,000 200,000GENERAL FUND
50,000 200,000 250,000Total
571
Description
Replace playground at North Market Square Park. This includes replacing rubber mat surface with engineered wood fiber. Adjacent elementary school playground
has poured in place surfacing.
Project #R4389
Priority Essential (2)
Justification
This replacement follows recommendatation of 2017 Park Master Plan. Playground components are aging and becoming difficult to repair and replace.
Budget Impact/Other
This replaces existing equipment. No increased expenditures.
Useful Life 20 years
Project Name N. Market Square Playground Replacement
Category Parks Maintenance
Type One Phase
Total Project Cost:$300,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
20,00020,000PLANNING/DESIGN
250,000250,000CONSTRUCTION
10,00010,000INSPECTION
20,00020,000CONTINGENCY
300,000 300,000Total
Total20222023202420252026Funding Sources
300,000300,000GO BONDS-ESSENTIAL
PURPOSE
300,000 300,000Total
572
Description
Replace playground at Reno Street Park. Add ADA compliant paths, park furnishings and fence to community garden.
Project #R4390
Priority Essential (2)
Justification
This replacement follows recommendatation of 2017 Park Master Plan. Playground components are aging and becoming difficult to repair and replace. This park
lacks ADA compiant paths.
Budget Impact/Other
There will be slightly less maintenance costs due to the replacement of older equipment. The expected annual savings is less than $5,000 per year.
Useful Life 20 years
Project Name Reno Street Park Renovations
Category Parks Maintenance
Type One Phase
Total Project Cost:$240,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
20,00020,000PLANNING/DESIGN
200,000200,000CONSTRUCTION
5,0005,000INSPECTION
15,00015,000CONTINGENCY
240,000 240,000Total
Total20222023202420252026Funding Sources
240,000240,000GO BONDS-ESSENTIAL
PURPOSE
240,000 240,000Total
573
Description
Tennis Court renovations at City Park and Mercer Park. City Park: resurface courts, replace fences, and add hitting practice wall at both ends. Mercer Park:
resurface courts and add hitting practice wall.
Project #R4391
Priority Non-essential (5)
Justification
The tennis court surfaces, fencing and practice walls are deteriorating and require renovation for continued use.
Budget Impact/Other
The tennis courts are deteriorating to a point in which they will soon not be suitable for play. This project will not have impact on operating budget as the courts do
not require much on-goin maintenance.
Useful Life 15 years
Project Name Tennis Court Renovations
Category Parks Maintenance
Type One Phase
Total Project Cost:$175,000
Contact Juli Seydell-Johnson
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
15,00015,000PLANNING/DESIGN
135,000135,000CONSTRUCTION
15,00015,000INSPECTION
10,00010,000ADMINISTRATION
175,000 175,000Total
Total20222023202420252026Funding Sources
175,000175,000GENERAL FUND
175,000 175,000Total
574
Description
This project is to acquire property in the future growth and annexation areas west of Highway 218 between Rohret Road and Highway 1.
Project #R4392
Priority Essential (2)
Justification
The future growth area west of Highway 218 includes a 196-acre potential annexation which will require ameneties for parks and recreation to serve the anticipated
population growth.
Budget Impact/Other
The future west park would require additional maintenance such as mowing and natural areas management. It also has the potential to include other amenities in the
future such as park shelters, trails, restroom facilities, pavilions, playgrounds, sport fields, etc. The estimated increase in annual operating expenditures due to the
land acquisition not including future amenities is $50,000 per year.
Useful Life 75 years
Project Name Westside Park Land Acquisition
Category Parks Maintenance
Type One Phase
Total Project Cost:$700,000
Contact Geoff Fruin
Department PARKS & RECREATION
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Park Master Plan
Status Active
Total20222023202420252026Expenditures
700,000700,000LAND/ROW ACQUISITION
700,000 700,000Total
Total20222023202420252026Funding Sources
700,000700,000GO BONDS-GENERAL
PURPOSE
700,000 700,000Total
Description
Acquisition and purchase of an Evidence Management System that will enhance the efficiency and acccuracy of submitting, cataloging, retrieving and distributing
digital evidence.
Project #Y4446
Priority Efficiency Improvement (3)
Justification
Currently evidence photographs/videos must be cataloged on paper, transferred to DVD disks and submitted to evidence for storage. Upon request for
viewing/copies to attorneys these disks must be located, replicated and distributed, a very time consuming and antiquated process by today's standards. This new
system that will allow upload directly into the system, create photo logs and associated information and file it under the proper incident number for ease of retrieval
while maintaining high security, making the entire department efficient.
Budget Impact/Other
This system will save much time for the officers submitting evidence to the property room managers retrieving the evidence. This project will also require $3,500
annual license fee. The project is estimated to reduce annual operating expenditures by $5,000 to $10,000 due to reduced staff time.
Useful Life 10 years
Project Name Digital Photo Evidence Management
Category Police
Type One Phase
Total Project Cost:$125,000
Contact Jody Matherly
Department POLICE
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
125,000125,000EQUIPMENT
125,000 125,000Total
Total20222023202420252026Funding Sources
125,000125,000GENERAL FUND
125,000 125,000Total
575
Description
This project provides a natural gas generator at the Animal Shelter which would be able to provide a safe and comfortable enviroment for the animals during any
kind of power outage.
Project #Y4447
Priority Essential (2)
Justification
Currently the Animal Center loses the abliity to provide heat or cooling during any kind of power outage. The Animal Center was built to be climate controlled
which does not allow us to have any possiblity to open any of the windows. Some rooms with animals have no ability to have access to outside air. Extended periods
of time exposed to extreme heat or cold has the potential to cause physical distress and/or death to an animal.
Budget Impact/Other
This project would increase the operating budget due to maintenance and inspection costs of the generator. The estimated annual increase in operating expenditures
is less than $5,000.
Useful Life 25 years
Project Name Animal Shelter Standy Generator
Category Police
Type One Phase
Total Project Cost:$108,500
Contact Denise Brotherton
Department POLICE
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
10,00010,000PLANNING/DESIGN
98,50098,500CONSTRUCTION
108,500 108,500Total
Total20222023202420252026Funding Sources
108,500108,500GENERAL FUND
108,500 108,500Total
576
Description
The project consists of creating a Landfill Master Plan in 2021 and the design and replacement of the landfill equipment storage buildings, currently known as
buildings A and B, in 2022 and 2023. The Master Plan component will determine where on the site the new building will be constructed in addition to assessing
overall traffic flow, potential compost facility changes and potential methane use infrastructure locations.
Project #L3328
Priority Essential (2)
Justification
These buildings are in poor condition and can not currently fit our equipment in them. This leaves our equipment exposed to the elements causing unnecessary wear
and excessive downtime.
Budget Impact/Other
The new building will be more energy efficient, allow for better equipment maintenance and accommodate storing landfill equipment indoors. A potential new
traffic pattern could allow for more customers and quicker, more efficient transactions. The net decrease in estimated annual expenditures is less than $10,000 per
year.
Useful Life 30 Years
Project Name Landfill Equipment Building Replacement
Category Landfill
Type One Phase
Total Project Cost:$1,250,000
Contact Jen Jordan
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Facilities Master Plan
Status Active
Total20222023202420252026Expenditures
100,000100,000PLANNING/DESIGN
950,000950,000CONSTRUCTION
50,00050,000CONTINGENCY
100,000 1,000,000 1,100,000Total
Prior
150,000
Total
Total20222023202420252026Funding Sources
1,100,000100,000 1,000,000LANDFILL FUND
100,000 1,000,000 1,100,000Total
Prior
150,000
Total
577
Description
The landfill six-acre compost pad will be backfilled in multiple areas to fill large pits. An asphalt layer will be added to cover the rock and a seal coat will be
applied to prevent liquids from seeping. A seal coat will be added to cover the raw millings on the eastern half of the pad that has not been sealed in the past.
Project #L3333
Priority Essential (2)
Justification
The landfill six-acre compost pad and wood processing pad is in need of significant repair. Deferred maintenance over many years has resulted in the need for repair
to ensure customer safety and regulatory compliance. The pad must meet the Iowa Department of Natural Resources' requirements for impermeability and for
stormwater control.
Budget Impact/Other
An improved surface will reduce equipment repair costs and reduce customer safety issues/potential liability claims. The estimated annual savings is less than
$10,000 per year.
Useful Life 20 years
Project Name Compost Pad Improvements
Category Landfill
Type One Phase
Total Project Cost:$330,000
Contact Jen Jordan
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
30,00030,000PLANNING/DESIGN
300,000300,000CONSTRUCTION
30,000 300,000 330,000Total
Total20222023202420252026Funding Sources
330,00030,000 300,000LANDFILL FUND
30,000 300,000 330,000Total
578
Description
This project includes the design and installation of an expansion of the Landfill Dual Extraction System, which was originally constructed in 2018. This project will
expand the current system (13 pnuematic pumps and 4 solar pumps) to include pumps in 8-9 additional wells and add SCADA monitoring to the proposed new and
existing pumps.
Project #L3335
Priority Efficiency Improvement (3)
Justification
The expansion of the Landfill's Dual Extraction System will positively impact eight or nine more wells, which have liquid levels that are close to or exceed the
screen within them. Having high liquid levels limits or prevents gas from being able to be pulled from those wells. Expansion of the Dual Extraction System will
allow landfill operators to better control leachate and gas management onsite. This will enhance operator functionality and reduce manual labor time. Adding
SCADA greatly improves monitoring capabilities and efficiencies for landfill staff.
Budget Impact/Other
Adding SCADA monitoring to the new and existing pumps will increase staff efficiency by allowing central monitoring., but but the annual savings are expected to
be less than $10,000 per year.
Useful Life 20 years
Project Name Landfill Dual Extraction System Expansion
Category Landfill
Type One Phase
Total Project Cost:$600,000
Contact Jen Jordan
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
55,00055,000PLANNING/DESIGN
485,000485,000CONSTRUCTION
50,00050,000INSPECTION
10,0005,000 5,000ADMINISTRATION
60,000 540,000 600,000Total
Total20222023202420252026Funding Sources
600,00060,000 540,000LANDFILL FUND
60,000 540,000 600,000Total
579
Description
This project includes the preliminary design and studies, detailed design, construction, construction observation, and regulatory compliance associated with
implementing the next landfill cell.
Project #L3338
Priority Critical (1)
Justification
The current rate of landfilling and compaction allows for approximately 2-3 years in the current cell, Cell FY18. New cells take 2-3 years to design, construct,
permit, and complete the initial landfilling.
Budget Impact/Other
Expediting this project will reduce rock purchases, because operations will allow for using existing interior roads and rainy day pads instead of building new. The
annual estimated reduction of expenditures is $25,000 per year.
Useful Life 10 years
Project Name Future Landfill Cell
Category Landfill
Type One Phase
Total Project Cost:$4,400,000
Contact Jen Jordan
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
300,000200,000 100,000PLANNING/DESIGN
3,600,0003,600,000CONSTRUCTION
40,00015,000 25,000ADMINISTRATION
360,000360,000CONTINGENCY
215,000 4,085,000 4,300,000Total
Prior
100,000
Total
Total20222023202420252026Funding Sources
4,300,000215,000 4,085,000LANDFILL REPLACEMENT
RESERVE
215,000 4,085,000 4,300,000Total
Prior
100,000
Total
580
Description
This project provides for the purchase and installation of a bulk water tank at the landfill.
Project #L3340
Priority Essential (2)
Justification
The tank will help provide the needed volume to ensure the refresh rate of the planned water main and allow for efficient filling of the landfill's tank used for daily
spray cover mixing. In the event of a fire it will also significantly reduce both transportation and fill time for the Fire Department.
Budget Impact/Other
Water costs and maintenance costs will be incurred based on water use. The estimated annual increase in operating expenditures is $10,000 to $15,000.
Useful Life 15 years
Project Name Bulk Water Fill Station
Category Landfill
Type One Phase
Total Project Cost:$175,000
Contact Jen Jordan
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
125,000125,000CONSTRUCTION
175,000 175,000Total
Total20222023202420252026Funding Sources
175,000175,000LANDFILL FUND
175,000 175,000Total
Description
This project will decommission and fill the older of two leachate lagoons and clean and repair the newer of the two lagoons.
Project #L3342
Priority Essential (2)
Justification
The older lagoon has not been utilized since 2012 and is not anticipated to be needed due to the newer lagoon's capacity and the ability to direct pipe to the
Wastewater Treatment Plant. The newer lagoon is in need of a clean-out and minor repairs to the liner.
Budget Impact/Other
While difficult to estimate a dollar amount, the removal of the older lagoon could reduce the amount of clean rainwater currently collected and treated as leachate, at
a cost. The estimated reduction in operating expenditures is less than $10,000 per year.
Useful Life 30 Years
Project Name Leachate Lagoon updates
Category Landfill
Type One Phase
Total Project Cost:$150,000
Contact Jen Jordan
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
150,000150,000CONSTRUCTION
150,000 150,000Total
Total20222023202420252026Funding Sources
150,000150,000LANDFILL FUND
150,000 150,000Total
581
Description
The project consists of installing six leachate extraction pneumatic pumps, air supply lines and leachate drainage lines in gas wells in two old unlined areas of the
landfill which have seen leachate migration impacts.
Project #L3344
Priority Critical (1)
Justification
This project is required to be complete by December 21, 2022, to meet the regulatory requirements with the Corrective Action Plan negotiated with the Iowa
Department of Natural Resources as part of the Assessment of Corrective Measures (ACM). The ACM was negotiated in summer 2021.
Budget Impact/Other
These updates will continue to reduce potential long-term liability for groundwater contamination and reduce long-term groundwater testing expenses. The
estimated decrease in operating expenditures is less than $10,000 per year.
Useful Life 30 Years
Project Name ACM Landfill Gas Infrastructure Expansion
Category Landfill
Type One Phase
Total Project Cost:$198,800
Contact Jen Jordan
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
30,00030,000PLANNING/DESIGN
142,600142,600CONSTRUCTION
6,0006,000INSPECTION
6,0006,000ADMINISTRATION
14,20014,200CONTINGENCY
198,800 198,800Total
Total20222023202420252026Funding Sources
198,800198,800LANDFILL FUND
198,800 198,800Total
582
Description
This machine would be used primarily in the compost and wood chip facility at the landfill to assist in safely grinding incoming materials.
Project #L3345
Priority Essential (2)
Justification
Currently an endloader with a grapple bucket is used to load the grinder. This limits staff's ability to see what is being dumped on the grinder belt and occasionally
includes items not suitable or safe to run through the grinder, such as metal fence posts or large rocks. An excavator with a grapple hook would enable staff to see
what they're picking up and be more selective and safe in loading the grinder.
Budget Impact/Other
Anticipated savings in down time and equipment costs is approximately $50,000 per year. The process change will slow down material throughput and will
therefore require more stafftime. Additional staff time is expected to cost approximately $20,000 per year.
Useful Life 10 years
Project Name Excavator for compost operations
Category Landfill
Type One Phase
Total Project Cost:$280,000
Contact Jen Jordan
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
280,000280,000EQUIPMENT
280,000 280,000Total
Total20222023202420252026Funding Sources
280,000280,000LANDFILL FUND
280,000 280,000Total
583
Description
This project will increase the storm sewer capacity on North Westminster Drive and Washington Street.
Project #M3633
Priority Essential (2)
Justification
The North Westminder Drainage Area was studied in response to reported flash flooding near the intersection of North Westminster Street and Washington Street.
The study confirmed that sections of the storm sewer system are inadequate to convey runoff for the City’s current 5-year design storm criteria. Surface flooding at
these two locations can be deep enough to cover the width of the roadway, overtop the curb and flow on to adjacent properties, creating a potential for property
damage and a public safety concern for vehicles.
Budget Impact/Other
Replacing infrastructure will lower the City's operating expenditures through decreased maintenance costs. The estimated decrease in operating expenses is less
than $10,000 per year.
Useful Life 50 years
Project Name North Westminster Storm Sewer Upgrades
Category Stormwater
Type One Phase
Total Project Cost:$1,775,000
Contact Ben Clark
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
50,00050,000LAND/ROW ACQUISITION
1,300,0001,300,000CONSTRUCTION
50,00050,000INSPECTION
25,00025,000ADMINISTRATION
150,000150,000CONTINGENCY
1,625,000 1,625,000Total
Prior
150,000
Total
Total20222023202420252026Funding Sources
1,625,0001,625,000STORMWATER FUND
1,625,000 1,625,000Total
Prior
150,000
Total
584
Description
This project will modify the top of the vault and hatches in order to accommodate ADA compliant sidewalks. It will also include replacement of the trash rack
screen and other associated pump station components.
Project #M3634
Priority Essential (2)
Justification
The location of the vault and hatches creates a maintenance issue and prohibits the installation of ADA compliant sidewalks. This pump station was installed 36
years ago and some of the components are in need of replacement.
Budget Impact/Other
There is no anticipated impact to the operating budget.
Useful Life 50 years
Project Name Rundell Street Pump Station Vault Modifications
Category Stormwater
Type One Phase
Total Project Cost:$350,000
Contact Ben Clark
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
40,00040,000PLANNING/DESIGN
250,000250,000CONSTRUCTION
25,00025,000INSPECTION
10,00010,000ADMINISTRATION
25,00025,000CONTINGENCY
350,000 350,000Total
Total20222023202420252026Funding Sources
350,000350,000STORMWATER FUND
350,000 350,000Total
585
Description
This project will install storm sewer pipe in an open ditch along the west side of River Street, north of the lower Lincoln School parking lot. A five-foot-wide
compliant sidewalk will replace the existing walk.
Project #M3635
Priority Essential (2)
Justification
The existing open channel storm water drainage ditch is deteriorating and is susceptible to blockage from debris. Utility services have been exposed to the surface
due to erosion along the bottom of the ditch. Further erosion will potentially impact the sidewalk and street. A compliant sidewalk will facilitate pedestrian traffic
to the school.
Budget Impact/Other
There is no anticipated impact to operating budget.
Useful Life 50 years
Project Name River Street Storm Sewer Improvements
Category Stormwater
Type One Phase
Total Project Cost:$850,000
Contact Ben Clark
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
90,00090,000PLANNING/DESIGN
10,00010,000LAND/ROW ACQUISITION
600,000600,000CONSTRUCTION
60,00060,000INSPECTION
30,00030,000ADMINISTRATION
60,00060,000CONTINGENCY
100,000 750,000 850,000Total
Total20222023202420252026Funding Sources
850,000100,000 750,000STORMWATER FUND
100,000 750,000 850,000Total
586
Description
Construct a new Equipment Maintenance Facility on the public works campus to replace the old and dated facility at the corner of Highways 1 & 6.
Project #P3953
Priority Essential (2)
Justification
The current Equipment Maintenance Facility is outdated, inefficient, and a poor working environment for the employees.
Budget Impact/Other
A new facility will be more energy efficient which will save costs on utilities; however, a newer facility will add square footage and increase insurance, cleaning,
and similar expenses. The estimated annual increase in operating expenditures is $50,000 to $100,000 per year.
Useful Life 40 Years
Project Name Equipment Maintenance Facility replacement
Category Equipment
Type One Phase
Total Project Cost:$12,000,000
Contact Ron Knoche
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Facilities Master Plan
Status Active
Total20222023202420252026Expenditures
1,000,0001,000,000PLANNING/DESIGN
11,000,00011,000,000CONSTRUCTION
1,000,000 11,000,000 12,000,000Total
Total20222023202420252026Funding Sources
4,500,0001,000,000 3,500,000EQUIPMENT FUND
4,000,0004,000,000FACILITY REPLACEMENT
RESERVE
700,000700,000GO BONDS-GENERAL
PURPOSE
500,000500,000LANDFILL FUND
250,000250,000REFUSE COLLECTION FUND
250,000250,000STORMWATER FUND
1,000,0001,000,000WASTEWATER FUND
800,000800,000WATER FUND
1,000,000 11,000,000 12,000,000Total
587
Description
The City's non-public safety radio system is nearing the end of the infrastructure's service life and needs updated to ensure radio communications continue.
Project #P3987
Priority Critical (1)
Justification
Divisions within the City rely on radio communication daily and is critical to our operation. Motorola factory service support for our portable and mobile radios
ended in April 2020, the Motorola Connect Plus system we have has reached end of life and end of support will be in early 2023. Future meetings will be held to
determine if we want to continue to own and maintain our own system or possibly join on the JECC P-25 network.
Budget Impact/Other
This project will have a minimal impact on the operating budget, but it will reduce expenditures slightly due to the replacement of aging equipment. The estimated
annual savings is less than $10,000.
Useful Life 10 years
Project Name Non-Public Safety Radio System Upgrade
Category Equipment
Type One Phase
Total Project Cost:$825,000
Contact Dan Striegel
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
825,000825,000CONSTRUCTION
825,000 825,000Total
Total20222023202420252026Funding Sources
825,000825,000EQUIPMENT FUND
825,000 825,000Total
Description
This project improves the landscaping at the City entrance ways on North Dubuque Street and North Dodge Street including entrance signage on North Dubuque.
Project #P3988
Priority Aesthetic Improvement (4)
Justification
The entrance ways to the city provide an important impression of the community to visitors. North Dubuque Street and North Dodge Street are primary entrances to
the City off Highway 80 and serve as the front doors to the city.
Budget Impact/Other
This project will slightly increase the annual operating expenditures due to the additional maintenance required on the landscaping and signage. The estimated
increase in operating expenditures is less than $10,000 per year.
Useful Life 20 years
Project Name Entrance Way Improvements
Category Public Works Administration
Type One Phase
Total Project Cost:$750,000
Contact Ron Knoche
Department PUBLIC WORKS
MATCH %VARIES
GRANTEE U OF I
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
750,000750,000CONSTRUCTION
750,000 750,000Total
Total20222023202420252026Funding Sources
650,000650,000GENERAL FUND
100,000100,000UNIVERSITY OF IOWA
750,000 750,000Total
588
Description
This project is part of the downtown streetscape master plan. This project reconstructs Dubuque Street from Washington to Iowa Avenue. The project also
improves sidewalk pavement, addresses critical utility updates, and enhances the retail environment with streetscape components. Project also includes alley
improvements, lighting, and wayfinding.
Project #S3939
Priority Critical (1)
Justification
Dubuque Street is an important link in Downtown as is often the entry way for visitors into the area. The project will narrow the road creating a more pedestrian
friendly environment and allowing for enhanced retail areas.
Budget Impact/Other
This project should reduce operating expenditures due to the replacement of infrastructure in poor condition. The anticipated annual savings is less than $10,000
per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name Dubuque Street Reconstruction
Category Street Operations
Type One Phase
Total Project Cost:$3,000,000
Contact Geoff Fruin
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT City-University
PLAN Downtown Streetscape Plan
Status Active
Total20222023202420252026Expenditures
300,000300,000PLANNING/DESIGN
2,100,0002,100,000CONSTRUCTION
200,000200,000INSPECTION
400,000400,000CONTINGENCY
300,000 2,700,000 3,000,000Total
Total20222023202420252026Funding Sources
3,000,0003,000,000GO BONDS-ESSENTIAL
PURPOSE
3,000,000 3,000,000Total
589
Description
This project would extend Capitol Street and Kirkwood Avenue as a part of the Riverfront Crossing area improvements. The project also includes replacement of the
12-inch water main on Capitol Street between Benton Street and the railroad to the north, water main improvements at the Benton and Clinton intersection and
removal of the railroad spur across Benton Street.
Project #S3940
Priority Essential (2)
Justification
The extensions of these streets plays an important part in the overall development of the Riverfront Crossings area. It will also improve access and traffic circulation
in this area. This project does not include any costs necessary for property acquisitions.
Budget Impact/Other
Ongoing maintenance of new poles and lighting units. Existing lights are being maintained, and new lights would likely require less maintenance in the future as
compared to the existing lights. Estimated annual operating expenditures are less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name Kirkwood Avenue to Capitol Street Connection
Category Street Operations
Type One Phase
Total Project Cost:$3,100,000
Contact Scott Sovers
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT Riverfront Crossings
PLAN Riverfront Crossings Master Pla
Status Active
Total20222023202420252026Expenditures
100,000100,000PLANNING/DESIGN
100,000 100,000Total
Future
3,000,000
Total
Future
3,100,000
Total
590
Description
This project will reconstruct Court Street from Muscatine Avenue to 1st Avenue.
Project #S3946
Priority Essential (2)
Justification
Court Street is an important collector street that connects the east side of Iowa City to the Downtown area. The project will replace aging street and sidewalk
pavement that is in poor condition and upgrade public utilities as needed.
Budget Impact/Other
Replacing aged infrastructure will lower the City's operating expenditures through decreased maintenance costs. The estimated decrease in operating expenses is
less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name Court Street Reconstruction
Category Street Operations
Type One Phase
Total Project Cost:$7,500,000
Contact Scott Sovers
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
150,000150,000PLANNING/DESIGN
5,600,0005,600,000CONSTRUCTION
200,000200,000INSPECTION
150,000150,000ADMINISTRATION
500,000500,000CONTINGENCY
150,000 6,450,000 6,600,000Total
Prior
900,000
Total
Total20222023202420252026Funding Sources
6,600,0006,600,000GO BONDS-ESSENTIAL
PURPOSE
6,600,000 6,600,000Total
Prior
900,000
Total
591
Description
Reconstruction of Rochester Avenue from First Avenue to the bridge over Ralston Creek. The project will include intersection improvements at First Avenue, new
street paving, sidewalk, utility improvements and other associated work. This project will also include water pressure zoning improvements at First Avenue.
Project #S3950
Priority Essential (2)
Justification
Rochester Avenue is an important arterial within Iowa City, and the street pavement is in poor condition. The project will also provide utility upgrades, sidewalk
infill, ADA curb ramp, and water pressure zone improvements within the project area.
Budget Impact/Other
Replacing aged infrastructure will lower the City's operating expenditures through decreased maintenance costs. The estimated decrease in operating expenses is
less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name Rochester Ave Reconst- First Ave. to Ralston Creek
Category Street Operations
Type One Phase
Total Project Cost:$7,000,000
Contact Jason Havel
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
150,000150,000LAND/ROW ACQUISITION
5,400,0005,400,000CONSTRUCTION
250,000250,000INSPECTION
250,000250,000ADMINISTRATION
250,000250,000CONTINGENCY
6,350,000 6,350,000Total
Prior
650,000
Total
Total20222023202420252026Funding Sources
6,350,0006,350,000GO BONDS-ESSENTIAL
PURPOSE
6,350,000 6,350,000Total
Prior
650,000
Total
592
Description
This project will study the south Hwy 1/Hwy 6 intersection and adjacent City owned properties and provide a functional design for the preferred future
improvements.
Project #S3951
Priority Essential (2)
Justification
This area is likely to redevelop in the future, and it is important to have an understanding of the anticipated roadway improvments/needs when considering possible
changes to the surrounding area. This project will also provide a plan for future trail connections and other associated improvements.
Budget Impact/Other
The proposed study and functional design is not expected to have any operating budget impacts.
Useful Life 50 years
Project Name Hwy 1/Hwy 6 Intersection Improvements Study
Category Street Operations
Type One Phase
Total Project Cost:$150,000
Contact Jason Havel
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT Riverside Drive
PLAN None
Status Active
Total20222023202420252026Expenditures
150,000150,000PLANNING/DESIGN
150,000 150,000Total
Total20222023202420252026Funding Sources
150,000150,000GENERAL FUND
150,000 150,000Total
593
Description
Reconstruction of Dodge Street from Governor Street to Burlington Street. This will be a joint project with the DOT, and will include new street pavement,
sidewalk, utility improvements and other associated work.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Project #S3952
Priority Essential (2)
Justification
This section of Dodge Street is in poor condition and requires significant ongoing maintenance. A functional design is currently underway for the project.
Budget Impact/Other
Replacing aged infrastructure will lower the City's operating expenditures through decreased maintenance costs. The estimated decrease in operating expenses is
less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name Dodge Street Reconstruct - Governor to Burlington
Category Street Operations
Type One Phase
Total Project Cost:$17,117,000
Contact Jason Havel
Department PUBLIC WORKS
MATCH %35%
GRANTEE IDOT
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
50,00050,000LAND/ROW ACQUISITION
13,200,00013,200,000CONSTRUCTION
350,000350,000INSPECTION
350,000350,000ADMINISTRATION
1,800,0001,800,000CONTINGENCY
15,750,000 15,750,000Total
Prior
1,367,000
Total
Total20222023202420252026Funding Sources
3,750,0003,750,000FEDERAL GRANTS
2,400,0002,400,000GO BONDS-ESSENTIAL
PURPOSE
9,850,0009,850,000OTHER STATE GRANTS
16,000,000 16,000,000Total
Prior
1,117,000
Total
594
Description
Reconstruct N. Gilbert Street from Brown Street to the construction limits of the Gateway project just south of Kimball Road. Improvements to include new water
main, sanitary sewer, storm sewer, PCC roadway paving and sidewalks on both sides of the roadway.
Project #S3955
Priority Essential (2)
Justification
Gilbert Street requires full reconstruction at this time. There is no storm sewer between Brown Street and the new intakes installed with the Gateway project.
Sidewalks are located only at the top of the hill, near Brown Street and residents have requested that pedestrian connectivity be provided to them with the roadway
improvements.
Budget Impact/Other
Replacing aged infrastructure will lower the City's operating expenditures through decreased maintenance costs. The estimated decrease in operating expenses is
less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name N. Gilbert Street Reconstruction
Category Street Operations
Type One Phase
Total Project Cost:$1,437,000
Contact Melissa Clow
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
150,000150,000PLANNING/DESIGN
50,00050,000LAND/ROW ACQUISITION
800,000800,000CONSTRUCTION
105,000105,000INSPECTION
32,00032,000ADMINISTRATION
300,000300,000CONTINGENCY
200,000 1,237,000 1,437,000Total
Total20222023202420252026Funding Sources
1,437,0001,437,000GO BONDS-ESSENTIAL
PURPOSE
1,437,000 1,437,000Total
595
Description
This project will replace the existing Gilbert Street bridge over Ralston Creek. In addition, the project will include removal and replacement of slope protection,
sidewalk, storm sewer and street pavement, and other related work.
Project #S3956
Priority Critical (1)
Justification
The 2017 Biennial Bridge Inspection Program identified advanced deterioration of the deck and super structure on the Gilbert Street bridge. The Program
recommended the bridge be scheduled for significant repairs or replacement.
Budget Impact/Other
Replacing aged infrastructure will lower the City's operating expenditures through decreased maintenance costs. The estimated decrease in operating expenses is
less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name Gilbert Street Bridge Replacement
Category Street Operations
Type One Phase
Total Project Cost:$3,300,000
Contact Jason Havel
Department PUBLIC WORKS
MATCH %60%
GRANTEE IDOT
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
2,600,0002,600,000CONSTRUCTION
150,000150,000INSPECTION
75,00075,000ADMINISTRATION
300,000300,000CONTINGENCY
3,125,000 3,125,000Total
Prior
175,000
Total
Total20222023202420252026Funding Sources
1,000,0001,000,000FEDERAL GRANTS
2,300,0002,300,000GO BONDS-ESSENTIAL
PURPOSE
3,300,000 3,300,000Total
596
Description
Reconstruction of Park Road from Rocky Shore Drive to the west project limits of the Gateway Project, approximately Riverside Drive. This project will include
new street pavement, sidewalk, utility improvements and other associated work.
Project #S3958
Priority Essential (2)
Justification
This section of Park Road is in poor condition and is in need of repair. The City has received numerous complaints about its condition.
Budget Impact/Other
Replacing aged infrastructure will lower the City's operating expenditures through decreased maintenance costs. The estimated decrease in operating expenses is
less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name Park Road Reconstruct - Rocky Shore to Riverside
Category Street Operations
Type One Phase
Total Project Cost:$6,700,000
Contact Jason Havel
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
650,000650,000PLANNING/DESIGN
50,00050,000LAND/ROW ACQUISITION
5,250,0005,250,000CONSTRUCTION
250,000250,000INSPECTION
250,000250,000ADMINISTRATION
250,000250,000CONTINGENCY
700,000 6,000,000 6,700,000Total
Total20222023202420252026Funding Sources
6,700,0006,700,000GO BONDS-ESSENTIAL
PURPOSE
6,700,000 6,700,000Total
597
Description
Reconstruction of Taft Avenue from American Legion Road to Lower West Branch. Design of this project would begin in 2022 with construction to begin in 2025.
Project #S3959
Priority Essential (2)
Justification
The properties west of Taft Avenue between Lower West Branch Road and American Legion Road are now fully developed. With the construction of the new
Hoover School and the upcoming American Legion Road and Scott Boulevard trunk sewer extension projects, the area will likely experience growth in the next five
to ten years necessitating improvements to Taft Avenue.
Budget Impact/Other
This project will add infrastructure into the City which will incrementally increase the City's operating costs. The estimated increase in operating expenditures is
less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name Taft Avenue Reconstruct - Am Legion to Lwr West Br
Category Street Operations
Type One Phase
Total Project Cost:$11,000,000
Contact Jason Havel
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
1,000,0001,000,000PLANNING/DESIGN
10,000,00010,000,000CONSTRUCTION
1,000,000 10,000,000 11,000,000Total
Total20222023202420252026Funding Sources
3,500,0003,500,000FEDERAL GRANTS
7,500,0007,500,000GO BONDS-ESSENTIAL
PURPOSE
11,000,000 11,000,000Total
598
Description
Obtain consultant services to perform an alignment study for the Oakdale Boulevard extension east of Highway 1.
Project #S3960
Priority Essential (2)
Justification
This project will conduct an aligment study for the Oakdale Boulevard extension east of Highway 1. The existing alignment study was completed in 2003 and
changes in land use, ownership and travel patterns nessesitate revisting the appropriate alignment for the road extension. This project also meets the Council's
Strategic Plan goal of 'Investing in Public Infrastructure' by initiating a planning effort to prepare for future expansion of a critical public facility.
Budget Impact/Other
This project will not have an impact on the operating budget.
Useful Life 10 years
Project Name Oakdale Blvd Extension - Alignment Study
Category Street Operations
Type Multi-Phase
Total Project Cost:$100,000
Contact Kent Ralston
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT Northgate Corporate Park
PLAN Transportation Plan
Status Active
Total20222023202420252026Expenditures
100,000100,000PLANNING/DESIGN
100,000 100,000Total
Total20222023202420252026Funding Sources
100,000100,000GENERAL FUND
100,000 100,000Total
599
Description
This project will replace both the eastbound and westbound Burlington Street bridges with one new bridge over the Iowa River. In addition, the project will
investigate the feasibililty of eliminating the dam as well as the realignment of Grand Avenue west of Riverside Drive. This project will be a joint project with the
DOT.
Project #S3963
Priority Critical (1)
Justification
The 2019 biennial bridge inspection program identified advanced detorioration of the sub and super structures on the Burlington Street Bridges. The program
recommended the bridge to be scheduled for replacement.
Budget Impact/Other
Operating expenses are expected to be minimal or decrease, as this will be replacing aged infrastructure that has reached the end of its useful life.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Capital Projects fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 75 years
Project Name Burlington Street Bridge Replacement
Category Street Operations
Type One Phase
Total Project Cost:$19,050,000
Contact Scott Sovers
Department PUBLIC WORKS
MATCH %VARIES
GRANTEE STP
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
750,000750,000PLANNING/DESIGN
750,000 750,000Total
Prior
300,000
Total
Future
18,000,000
Total
Prior
300,000
Total
Future
18,750,000
Total
600
Description
This project includes the reconstruction of two blocks of brick street along Fairchild Street from Clinton Street to Linn Street.
Project #S3965
Priority Essential (2)
Justification
The pavement condition in these areas is poor, and several areas have utilities that are in need of repair/replacement, which is contributing to the deterioration of the
street.
Budget Impact/Other
Estimated savings in operating expenses are less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Wastewater fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name Fairchild Street Reconstruction
Category Street Operations
Type One Phase
Total Project Cost:$1,450,000
Contact Jason Havel
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
1,100,0001,100,000CONSTRUCTION
50,00050,000INSPECTION
50,00050,000ADMINISTRATION
100,000100,000CONTINGENCY
1,350,000 1,350,000Total
Prior
100,000
Total
Total20222023202420252026Funding Sources
1,450,0001,450,000GO BONDS-ESSENTIAL
PURPOSE
1,450,000 1,450,000Total
601
Description
This project will be a comprehensive concrete rehabilitation of the Iowa Ave Bridge over the Iowa River. Additional repair items will include sidewalks, approach
pavement, expansion joints, pedestrian handrails and painting.
Project #S3977
Priority Essential (2)
Justification
The Iowa Avenue Bridge was built in 1916 and the most recent reconstruction project was in 1985. The most recent inspection in the summer of 2021 found it to
be in Fair Condition structurally, but noted delamination, cracks and spalls in the concrete on the deck, superstructure and substructure of the bridge. Deterioration
is also noted at the sidewalk approaches and abutments. To extend the longevity of the bridge, it is recommended that a comprehensive rehabilitation project be
completed.
Budget Impact/Other
The project will lower operating costs due to the replacement of aging infrastructure. The reduction in operating expenditures is estimated to be less than $10,000
per year.
Useful Life 20 years
Project Name Iowa Avenue Bridge Rehabilitation
Category Street Operations
Type One Phase
Total Project Cost:$2,250,000
Contact Melissa Clow
Department PUBLIC WORKS
MATCH %60%
GRANTEE IDOT
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
150,000150,000PLANNING/DESIGN
1,500,0001,500,000CONSTRUCTION
150,000150,000INSPECTION
75,00075,000ADMINISTRATION
75,00075,000CONTINGENCY
300,000300,000OTHER
150,000 2,100,000 2,250,000Total
Total20222023202420252026Funding Sources
1,000,0001,000,000FEDERAL GRANTS
1,250,0001,250,000GO BONDS-ESSENTIAL
PURPOSE
2,250,000 2,250,000Total
602
Description
This project will provide repairs to the existing pedestrian overpass, including removal of loose / delaminated material at risk of falling and the application of a
corrosive inhibiting coating to protect the exposed areas and match the appearance of the surrounding concrete.
Project #S3978
Priority Critical (1)
Justification
A condition assessment of the Pedestrian Bridge was completed in the Spring of 2021 and a rehabilitation project was recommended. Loose material and
delaminated concrete was identified. This presents a hazard to vehicles and pedestrians under the structure.
Budget Impact/Other
This project will reduce maintenance costs through the rehabilitation of an older structure. A more complex rehabilitation project is recommended prior to the end
of its current life expectancy and would to further extend the life of the pedestrian bridge by 30 years. The annual savings is less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Wastewater fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 10 years
Project Name Riverside Dr. Pedestrian Bridge at Iowa Ave Rehab
Category Street Operations
Type One Phase
Total Project Cost:$1,300,000
Contact Melissa Clow
Department PUBLIC WORKS
MATCH %25%
GRANTEE IDOT
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
100,000100,000PLANNING/DESIGN
1,025,00075,000 950,000CONSTRUCTION
65,00015,000 50,000INSPECTION
60,00035,000 25,000ADMINISTRATION
50,00050,000CONTINGENCY
225,000 1,075,000 1,300,000Total
Total20222023202420252026Funding Sources
325,000325,000GO BONDS-ESSENTIAL
PURPOSE
650,000650,000OTHER STATE GRANTS
325,000325,000UNIVERSITY OF IOWA
1,300,000 1,300,000Total
603
Description
Reconsturction of South Dubuque Street from Wright St to Benton St. The project will include new street paving, sidewalks, utility improvements and other
associated work.
Project #S3979
Priority Essential (2)
Justification
South Dubuque St is in poor condition and has been indentified as a good candidate for reconstruction by the Pavement Management Program.
Budget Impact/Other
Replacing aged infrastructure will lower the City's operating expenditures through decreased maintenance costs. The estimated decrease in operating expenses is
less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Wastewater fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name South Dubuque St Reconstruction - Wright to Benton
Category Street Operations
Type One Phase
Total Project Cost:$1,850,000
Contact Jason Havel
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
150,000150,000PLANNING/DESIGN
50,00050,000LAND/ROW ACQUISITION
1,300,0001,300,000CONSTRUCTION
100,000100,000INSPECTION
100,00050,000 50,000ADMINISTRATION
150,000150,000CONTINGENCY
250,000 1,600,000 1,850,000Total
Total20222023202420252026Funding Sources
1,850,0001,850,000GO BONDS-ESSENTIAL
PURPOSE
1,850,000 1,850,000Total
604
Description
Conversion of Market Street & Jefferson Streets from one-way to two-way corridors. The project cost includes new traffic signals, pavement markings, buffered
bike lanes, and signage necessary to implement the conversion. The conversion is intended to generally take place between Madison Street and the eastern termini
of the one-way streets - exact limits subject to further evaluation.
Project #S3980
Priority Non-essential (5)
Justification
The feasibility of the project and cost estimate was initially evaluated as part of the Downtown Iowa City Traffic Modeling Study completed in 2015.
Budget Impact/Other
Operating budget impacts are assumed to be negligible as the corridors already exist and require routine maintenance activities. The conversion will only change
how the facilities are used by the traveling public.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Wastewater fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 20 years
Project Name Market & Jefferson Street Two-Way Conversion
Category Street Operations
Type One Phase
Total Project Cost:$2,600,000
Contact Kent Ralston
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Transportation Plan
Status Active
Total20222023202420252026Expenditures
300,000300,000PLANNING/DESIGN
1,900,0001,900,000CONSTRUCTION
100,000100,000INSPECTION
100,000100,000ADMINISTRATION
200,000200,000CONTINGENCY
300,000 2,300,000 2,600,000Total
Total20222023202420252026Funding Sources
2,600,0002,600,000GO BONDS-ESSENTIAL
PURPOSE
2,600,000 2,600,000Total
605
Description
The future project has two parts: 1) Provide process/related structures and equipment removing phosphorous before or during digestion. 2) Replace multiple heat
exchangers (HEX) with internal corrosion and Struvite deposition, renovate digester covers, install wall thimbles in digester wall for inspection and cleaning, replace
internal/external(buried) piping clogging with Struvite, replace (HEX) and sludge recirculation pumps as required and add new piping for the thickened Waste
Activated Sludge.
Project #V3151
Priority Critical (1)
Justification
Biological nutrient removal was part of last ICWWTP project, captured phosphorous (P) reduces Struvite formation and reduces maintenance costs. In addition. the
digester complex was constructed in 1989/2002 and has multiple covers in various stages of wear, along with multiple pumps and HEX’s and multiple valves/pipes
show struvite deposition that have required significant maintenance to keep cleared of struvite or need to be replaced.
Budget Impact/Other
This project will reduce operating and maintenance cost through the rehabilitation of older equipment. The annual savings is less than $10,000 per year.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Wastewater fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 20 years
Project Name Digester Complex Rehabilitation
Category Wastewater Treatment
Type One Phase
Total Project Cost:$12,921,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
880,000880,000PLANNING/DESIGN
10,621,00010,621,000CONSTRUCTION
200,000200,000INSPECTION
100,000100,000ADMINISTRATION
1,000,0001,000,000CONTINGENCY
880,000 11,921,000 12,801,000Total
Prior
120,000
Total
Total20222023202420252026Funding Sources
12,921,00012,921,000REVENUE BONDS
12,921,000 12,921,000Total
606
Description
Rehabilitation includes demolishing the existing building, converting the station to a wet-well valve vault with surface hatches for pump access, basket screening,
new standby generator, replace 20 year old pump, new controls, valve vault with bypass capacity, new security fence, landscaping and access road improvements.
The station would be plumbed for future expansion, but would not include additional pumps.
Project #V3154
Priority Essential (2)
Justification
Hawkeye lift station is 50 years old with an aging building, a generator that can no longer be serviced, a deep drywell requiring an elevator and an existing pump
that is 20 years old and a replacement pump only 2 years old. Major portions of the station have outlived their useful life and need replacement.
Budget Impact/Other
This project will reduce operating and maintenance cost through the rehabilitation of older equipment. The annual savings is less than $10,000 per year.
Useful Life 20 years
Project Name Hawkeye Lift Station Rehabilitation
Category Wastewater Treatment
Type One Phase
Total Project Cost:$1,025,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
25,00025,000PLANNING/DESIGN
1,000,0001,000,000CONSTRUCTION
25,000 1,000,000 1,025,000Total
Total20222023202420252026Funding Sources
1,025,0001,025,000WASTEWATER FUND
1,025,000 1,025,000Total
607
Description
This project would extend the 30-inch sanitary sewer pipe along Abbey Lane from Burry Drive to the west side of US Highway 218.
Project #V3155
Priority Essential (2)
Justification
This project will allow development within the watershed west of US Highway 218 and south of Rohret Road.
Budget Impact/Other
This will bring additional revenue along with additional maintenance costs. The estimated maintenance costs are less than $10,000 per year. The estimated amount
of additional revenue is unknown.
This serves as a declaration of official intent under Treasury Regulation 1.150-2 that it is reasonably expected that capital expenditures will be made in respect of
the above-described project, such expenditures to be advanced from the Wastewater fund, and the City reasonably expects to reimburse all or a portion of the
expenditures with the proceeds of bonds, notes or other indebtedness to be issued or incurred by the City in the future.
Useful Life 50 years
Project Name Rohret South Sewer
Category Wastewater Treatment
Type One Phase
Total Project Cost:$4,750,000
Contact Joe Welter
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
170,000110,000 60,000PLANNING/DESIGN
130,000130,000LAND/ROW ACQUISITION
3,500,0003,500,000CONSTRUCTION
175,000175,000INSPECTION
175,000175,000ADMINISTRATION
350,000350,000CONTINGENCY
110,000 4,390,000 4,500,000Total
Prior
250,000
Total
Total20222023202420252026Funding Sources
4,750,0004,750,000REVENUE BONDS
4,750,000 4,750,000Total
608
Description
Install new high efficiency mixers in aeration basin trains 1-4, Cell 9 to improve mixing and reduce energy usage. Includes four new high efficiency mixers,
electrical improvements and installation.
Project #V3157
Priority Essential (2)
Justification
2010 project made significant improvements to the aeration basin. Cell 9 was not fitted with a mixer but relied on mixing by compressed air. Mixing by compressed
air is not as efficient as using a mechanical mixer. The mixers are high efficiency and a lower horsepower than the current mixers installed in Cells 1, 2, 3, 5, 8, and
10. This will reduce wear and tear on the aeration blowers and reduce our electrical usage and carbon footprint.
Budget Impact/Other
This will reduce wear and tear on the aeration blowers, reduce our electrical usage/cost, and reduce out carbon footprint. The estimated annual savings is less than
$10,000 per year.
Useful Life 20 years
Project Name Wastewater Plant Mixer Improvements
Category Wastewater Treatment
Type One Phase
Total Project Cost:$238,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
15,00015,000PLANNING/DESIGN
200,000200,000CONSTRUCTION
2,0002,000INSPECTION
1,0001,000ADMINISTRATION
20,00020,000CONTINGENCY
238,000 238,000Total
Total20222023202420252026Funding Sources
238,000238,000WASTEWATER FUND
238,000 238,000Total
609
Description
Extend or add new belt conveyor form the end of the existing conveyor to the loading area over the truck bay. Project includes a truck hopper loader so staff can
keep the presses in operation while bumping the truck.
Project #V3158
Priority Essential (2)
Justification
The conveyor currently collects the biosolid from the belt filter press and take to to a shaftless screw auger that lift the biosolids up to discharge over the truck bay. It
has been found that when we operate all three presses, the screw auger cannot keep up with the volume of biosolids delivered by the conveyor. By including the
truck hopper loader, staff can keep the presses in operation while bumping the truck which make the belt filter
presses operation more efficient.
Budget Impact/Other
Current auger conveyor will not keep up with solids generated from more than two belt filter presses which limits out ability to dewater biosolids, and repairs takes
at least one business day to make, which also limits our ability to dewater biosolids. The estimated impact on the operating budget is negligible.
Useful Life 25 years
Project Name Biosolids Conveyor Improvements
Category Wastewater Treatment
Type One Phase
Total Project Cost:$170,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
7,0007,000PLANNING/DESIGN
146,000146,000CONSTRUCTION
2,0002,000INSPECTION
2,0002,000ADMINISTRATION
13,00013,000CONTINGENCY
170,000 170,000Total
Total20222023202420252026Funding Sources
170,000170,000WASTEWATER FUND
170,000 170,000Total
610
Description
Reroute the Benton Street trunk sewer through green space and a parking lot to allow access for maintenance. Upsize the sewer main to Emerald Street to increase
capacity.
Project #V3162
Priority Critical (1)
Justification
Previous rerouting of the trunk and upstream sanitary sewer left a undersized pipe creating a bottle neck and limited maintenance access to the sanitary sewer on
private property. The bottle neck has caused potential project to be routed to the west or not pursued. Making improvements will allow better access and not be a
bottleneck, which limits future growth north of Melrose Avenue.
Budget Impact/Other
This project will have a minimal impact on the operating budget.
Useful Life 50 years
Project Name Benton Street Trunk Sewer Improvements
Category Wastewater Treatment
Type One Phase
Total Project Cost:$580,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
63,00063,000PLANNING/DESIGN
55,00055,000LAND/ROW ACQUISITION
350,000350,000CONSTRUCTION
21,00021,000INSPECTION
21,00021,000ADMINISTRATION
70,00070,000CONTINGENCY
580,000 580,000Total
Total20222023202420252026Funding Sources
580,000580,000WASTEWATER FUND
580,000 580,000Total
611
Description
Install cable tray and hanger system along the aeration basin walkways to move the existing wiring/conduits from the hand rails and provide for future expansion
Project #V3163
Priority Efficiency Improvement (3)
Justification
Existing power and instrument wiring/conduits are currently placed on the hand rails. The hand rails were not designed to carry the extra weight of the current and
future wiring/conduits that will be required to supply/support the operation of the aeration basins. The cable tray and hanger system will move existing conduits and
wiring from the handrails and allow for future expansion of power and control wiring.
Budget Impact/Other
These projects should lower operating expenditures through the replacement of aging infrastructure. The estimated annual savings is less than $10,000 per year.
Useful Life 40 Years
Project Name Aeration Basin Electric & Instrument Improvements
Category Wastewater Treatment
Type One Phase
Total Project Cost:$300,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
10,00010,000PLANNING/DESIGN
259,000259,000CONSTRUCTION
2,0002,000INSPECTION
2,0002,000ADMINISTRATION
27,00027,000CONTINGENCY
300,000 300,000Total
Total20222023202420252026Funding Sources
300,000300,000WASTEWATER FUND
300,000 300,000Total
612
Description
The project would include the replacement of return activated sludge pumps. This includes all pumps and any piping/structural modifications required to fit the
pumps.
Project #V3164
Priority Essential (2)
Justification
These pumps have been in service since 2002 and are nearing the end of their useful working life. The maintenance repair frequency for these pumps has been
increasing in the past year. Failure to replace these pumps in a timely manner could cause diminished operation and treatment of the wastewater resulting in
violations of our NPDES discharge permit.
Budget Impact/Other
New pumps would increase pump efficiency, but lower energy consumption and maintenance costs. The estimated reduction in operating expenditures is less than
$10,000 per year.
Useful Life 20 years
Project Name Return Activated Sludge Pump Replacement
Category Wastewater Treatment
Type Multi-Phase
Total Project Cost:$1,009,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
80,00080,000PLANNING/DESIGN
823,000823,000CONSTRUCTION
16,00016,000INSPECTION
8,0008,000ADMINISTRATION
82,00082,000CONTINGENCY
1,009,000 1,009,000Total
Total20222023202420252026Funding Sources
1,009,0001,009,000WASTEWATER FUND
1,009,000 1,009,000Total
613
Description
Replacement of the influent pump station pumps 1301A, 1302A, and 1303A and any piping/electrical modifications that will be required.
Project #V3165
Priority Essential (2)
Justification
There are 6 influent pumps currently installed. The three discussed above were installed in 2002 and are nearing the end of their design life. These pumps have had
significant repairs over the past 5 years but those repairs have not extended their design life. These pumps are close coupled centrifugal style pumps and will be
replaced with dry pit submersible pumps to match the existing style of the three remaining pumps. There will be piping modifications, upgrading of controls and
includes installation. The current pumps are rated at 10 milllion gallons per day (MGD), the newer pumps will be 12 MGD.
Budget Impact/Other
The existing pumps have increasing maintenance cost and operation costs when they are OOS. New pumps will improve pump efficiency, lower power cost and
reduced maintenance cost. The estimated reduction in operating expenditures is less than $10,000 per year.
Useful Life 20 years
Project Name Replacement of Influent Pump Station Pumps
Category Wastewater Treatment
Type One Phase
Total Project Cost:$605,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
25,00025,000PLANNING/DESIGN
521,000521,000CONSTRUCTION
4,0004,000INSPECTION
2,0002,000ADMINISTRATION
53,00053,000CONTINGENCY
605,000 605,000Total
Total20222023202420252026Funding Sources
605,000605,000WASTEWATER FUND
605,000 605,000Total
614
Description
Replace the Grit Classifiers located in the Grit Building including any required piping and bunker modifications. Project includes installing a bagging system and
roll-off to move away from having to install a liming system to meet IDNR grit disposal requirements. This cost includes the 2 roll-off containers.
Project #V3167
Priority Essential (2)
Justification
The grit classifiers were installed in 2002 and have requiried a major frame repair in 2015 and multiple rotating parts replacment over the past 5 years. The
equipment is at the end of it's useful design life. IDNR rules require raising the grit pH to 12 for 2 hours, by installing a bagging system and roll-off, we can apply
for a waiver for liming and the roll-off will reduce staff handling the grit. With improvements in technology, the new classifiers are more effective at dewatering and
will produce a drier grit.
Budget Impact/Other
Grit removal is critical in WWTP operations in meeting its NPDES permit and reduces wear and tear on down steam pumping. Scheduled replacement is is more
cost ffective than an emergency replacement project. This project repairs existing equipment which should reduce maintenance and repairs costs. The estimated
impact on the operating budget is less than $10,000.
Useful Life 20 years
Project Name Replace Grit Classifiers
Category Wastewater Treatment
Type One Phase
Total Project Cost:$394,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
30,00030,000PLANNING/DESIGN
325,000325,000CONSTRUCTION
6,0006,000INSPECTION
3,0003,000ADMINISTRATION
30,00030,000CONTINGENCY
394,000 394,000Total
Total20222023202420252026Funding Sources
394,000394,000WASTEWATER FUND
394,000 394,000Total
615
Description
Rehabilitate selected equipment at the Napoleon Lift Station including the bar screen crawler assemblies with drive unit, the air handling system and rebuilding of
the NPPS Pumps #1 and #6 pumping assembly’s and replacing associated electrical or mechanical appurtenances as necessary.
Project #V3169
Priority Critical (1)
Justification
Napoleon lift station was constructed in 2000 and is the primary lift station for approximately 2/3 of the wastewater flow to the WWTP. The Bar screen crawler,
pumps #1 and #6 and air handling system have operated consistently since its coming into operations and show wear and tear consistent with 20 years of operations
and are nearing the end of their useful design life. Improvements in crawler and pump design will offer operation and efficiency improvements. Napoleon Lift
Station is the City's primary lift station conveying 2/3 of the daily total flow to the WWTP. If any of this equipment were to fail it would limit the operation of the
lift station until repairs could be made.
Budget Impact/Other
These projects should lower operating expenditures through the replacement of aging infrastructure. The estimated annual savings is less than $10,000 per year.
Useful Life 20 years
Project Name Napoleon Lift Station Improvements
Category Wastewater Treatment
Type One Phase
Total Project Cost:$1,475,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
120,000120,000PLANNING/DESIGN
1,200,0001,200,000CONSTRUCTION
25,00025,000INSPECTION
10,00010,000ADMINISTRATION
120,000120,000CONTINGENCY
1,475,000 1,475,000Total
Total20222023202420252026Funding Sources
1,475,0001,475,000WASTEWATER FUND
1,475,000 1,475,000Total
616
Description
Replace roofs on buildings at wastewater treatment plant.
Project #V3170
Priority Critical (1)
Justification
City staff has identified various plant building roofs as being deficient. The bulk of these buildings are part of the original WWTP project from 1988 with the others
from the 2000 project. They have outlived any warranty’s given at the time of construction and are in need of replacement. These roof's cover multiple buildings
with critical infrastructure in them. Should any building suffer water damage that impedes the division staff from performing their job function or causes equipment
failure, that could cause the WWTP to not meet its NPDES permit required discharge limits and put the City in environmental liability.
Budget Impact/Other
These projects should lower operating expenditures through the replacement of aging infrastructure. The estimated annual savings is less than $10,000 per year.
Useful Life 25 years
Project Name WWTP Roof Replacements
Category Wastewater Treatment
Type Multi-Phase
Total Project Cost:$1,200,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
60,00020,000 20,000 20,000PLANNING/DESIGN
750,000250,000 250,000 250,000CONSTRUCTION
15,0005,000 5,000 5,000INSPECTION
15,0005,000 5,000 5,000ADMINISTRATION
60,00020,000 20,000 20,000CONTINGENCY
300,000 300,000 300,000 900,000Total
Future
300,000
Total
Total20222023202420252026Funding Sources
900,000300,000 300,000 300,000WASTEWATER FUND
300,000 300,000 300,000 900,000Total
Future
300,000
Total
617
Description
Replace and rehabilitate the pumps, power and electrical controls, and mechanical appurtenances. The project includes replacing the pump with an upsized capacity,
change out the controls for PLC/ VFD's , replace all mechanical equipment and install a standby genset. The 2018 pump will be repurposed.
Project #V3172
Priority Essential (2)
Justification
The Highlander lift station has been in place since 1984 with a one original pump and one replacement pump(2018), mostly original controls and mechanical
appurtenances. The area serviced by the lift station has grown considerably and is projected to continue to grow with the installed pumps nearing their max pumping
capacity. With the past and potential growth in the area, capacity and reliability is becoming an issue. Rebuilding and increasing the pumping capacity will add
longevity to the station to meet future needs.
Budget Impact/Other
This project will increase the operating budget due to expanding system capacity. The estimated annual increase in expenditures is less than $5,000 per year.
Useful Life 20 years
Project Name Highlander Lift Station Improvements
Category Wastewater Treatment
Type One Phase
Total Project Cost:$150,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
7,0007,000PLANNING/DESIGN
121,000121,000CONSTRUCTION
1,0001,000INSPECTION
1,0001,000ADMINISTRATION
20,00020,000CONTINGENCY
150,000 150,000Total
Total20222023202420252026Funding Sources
150,000150,000WASTEWATER FUND
150,000 150,000Total
618
Description
Moving the replacement schedule to 12 years from 15. These are additional funds supplementing the City Equipment Replacement funds required to complete the
purchase.
Project #V3173
Priority Critical (1)
Justification
The jet truck was purchased in 2011 and was scheduled for a 15 years replacement. The jet-vac has been having frequent mechanical and electrical issues for the
past 2 years which has caused our cleaning activities to cease while repairs are made. We do not anticipate that this maintenance history will change and will likely
increase. We want to move up the replacement to 2023, this will make for a 12 year replacement. Monthly replacement fees would be increased to reflect a 12 year
replacement in the future.The jet truck is vital in the WWD's collection system maintenance cleaning program. Cleaning the sewer helps to reduce backups, Sanitary
Sewer Overflows (SSO's) and limits the City's liability. By moving up the replacement date, we can stay on schedule with cleaning program and avoid increased
liability.
Budget Impact/Other
These projects should lower operating expenditures through the earlier replacement of equipment, but it will increase operating expenditures through increased
replacement charges. The estimated net increase in annual operating expenditures is $25,000 per year.
Useful Life 12 years
Project Name Jet Truck Replacement
Category Wastewater Treatment
Type One Phase
Total Project Cost:$175,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
175,000175,000EQUIPMENT
175,000 175,000Total
Total20222023202420252026Funding Sources
175,000175,000WASTEWATER FUND
175,000 175,000Total
619
Description
Phase 1: Replace the remaining mixers in the aeration trains 1 - 4 with high efficiency mixers matching those placed in Cell 9 of trains 1-4 and replace mixers in the
high strength tank. This would be total of 30 mixers. Phase 2: Replace Lamson 300 HP Centrifugal Blower with a High Speed Turbo Blower including any ancillary
equipment, pipe modifications and PLC programing.
Project #V3174
Priority Efficiency Improvement (3)
Justification
Phase 1: Most of these mixers are original to the 2002/2014 construction and have been rebuilt at least once at a cost of $7,000 to almost $10,000 apiece. They
typically operate 24hs/7 days a week when the trains are in service. Replacement with the higher efficiency mixer with lower horsepower will decrease energy usage
and continue to reduce our carbon footprint. Estimated cost savings over a 20-year period were estimated to be in excess of $600,000 when all 30 mixers in
operation. Phase 2: The existing Lamson Blowers were placed in service in 2002 as part of the first iteration of the activated sludge process units. The blower is a
"starts across the line", meaning that it's either on or off and cannot be regulated with Variable frequency drives. Because of this and it's HP capacity, it has high
starting amps that affect our electrical peak loading billing with REC. The New High Speed turbo blower uses a VFD which eliminates the inrush of power,
allowing us to regulate our peak loading and work at a lower operating amperage.
Budget Impact/Other
By replacing the Lamson blower with a high speed turbo blower, we anticipate a 10% reduction in power cost for the foreseeable future. The estimated annual
savings is less than $10,000 per year.
Useful Life 20 years
Project Name Aeration Equipment Improvements
Category Wastewater Treatment
Type One Phase
Total Project Cost:$3,506,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
10,00010,000PLANNING/DESIGN
2,000,0002,000,000CONSTRUCTION
4,0004,000INSPECTION
2,0002,000ADMINISTRATION
20,00020,000CONTINGENCY
2,036,000 2,036,000Total
Future
1,470,000
Total
Total20222023202420252026Funding Sources
2,036,0002,036,000WASTEWATER FUND
2,036,000 2,036,000Total
Future
1,470,000
Total
620
Description
Place Parshall flume(s) directly downstream of the grit tank channel isolation valves including ultrasonic measuring. This will require channel modifications, flume
and sensor installation and programming into the headworks PLC.
Project #V3175
Priority Critical (1)
Justification
Flow measuring was changed from a Parshall flume to an in-channel area velocity sensor/meter in the last plant upgrade. That sensor/meter failed and subsequent
efforts at flow measurement lack staff confidence in being greater than 80% accurate. Parshall flumes have been used in the wastewater industry for decades with
99+% accuracy and confidence.
Budget Impact/Other
This project will reduce operating and maintenance cost through the rehabilitation of older equipment. The annual savings is less than $10,000 per year.
Useful Life 20 years
Project Name Influent Flow Monitoring
Category Wastewater Treatment
Type One Phase
Total Project Cost:$251,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
25,00025,000PLANNING/DESIGN
200,000200,000CONSTRUCTION
4,0004,000INSPECTION
2,0002,000ADMINISTRATION
20,00020,000CONTINGENCY
251,000 251,000Total
Total20222023202420252026Funding Sources
251,000251,000WASTEWATER FUND
251,000 251,000Total
621
Description
Replace multiple paving panels at various locations in the main drive and mill a portion of the existing paving to improve ride and life of that paving.
Project #V3176
Priority Essential (2)
Justification
Multiple panels have degraded and exhibit severe fracturing. The main drive was hand laid in the last plant upgrade and create vehicle rocking which over time will
cause paving degradation and failure.
Budget Impact/Other
This project repairs existing pavement which should reduce maintenance and future repairs costs. The estimated impact on the operating budget is less than $10,000.
Useful Life 15 years
Project Name Treatment Plant Paving Improvements
Category Wastewater Treatment
Type One Phase
Total Project Cost:$71,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
2,0002,000PLANNING/DESIGN
60,00060,000CONSTRUCTION
2,0002,000INSPECTION
1,0001,000ADMINISTRATION
6,0006,000CONTINGENCY
71,000 71,000Total
Total20222023202420252026Funding Sources
71,00071,000WASTEWATER FUND
71,000 71,000Total
622
Description
Replace the heating/ventilation/air conditioning (HVAC) for the Influent Pump Station (IPS), Sludge Processing Building (SSPRS), Motor Vehicle Storage Building
(MVSB), Administration Building (ADMIN), and Grit Building (GRIT).
Project #V3177
Priority Essential (2)
Justification
The HVAC systems for the buildings listed above are all original to them. They age from 20 to 35 years old and have had significant repair work in the past 5 years
but that has not extended the useful life of these systems. Due to the nature of the facility, building ventilation is critical to the work that is being performed and
provides a safe work environment for the employees.
Budget Impact/Other
The estimated impact on the operating budget is less than $10,000.
Useful Life 20 years
Project Name HVAC Replacement
Category Wastewater Treatment
Type One Phase
Total Project Cost:$371,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
35,00035,000PLANNING/DESIGN
300,000300,000CONSTRUCTION
4,0004,000INSPECTION
2,0002,000ADMINISTRATION
30,00030,000CONTINGENCY
35,000 336,000 371,000Total
Total20222023202420252026Funding Sources
371,00035,000 336,000WASTEWATER FUND
35,000 336,000 371,000Total
623
Description
This project will replace the rake mechanisms for Calrifiers C3300 and 3400 that were new in 2002 and part of WWTP upgrades.
Project #V3178
Priority Essential (2)
Justification
They both have the original zinc plated carbon steel mechanisms that are severly corroded and are in need of replacement and/or repair. These repairs were
identified during recent inspections of the clarifiers. These repairs are necessary to avoid untimely equipment failure.
Budget Impact/Other
This project repairs existing equipment which should reduce maintenance and repairs costs. The estimated impact on the operating budget is less than $10,000.
Useful Life 20 years
Project Name Primary Clarifier Repairs
Category Wastewater Treatment
Type One Phase
Total Project Cost:$526,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
25,00025,000PLANNING/DESIGN
450,000450,000CONSTRUCTION
4,0004,000INSPECTION
2,0002,000ADMINISTRATION
45,00045,000CONTINGENCY
526,000 526,000Total
Total20222023202420252026Funding Sources
526,000526,000WASTEWATER FUND
526,000 526,000Total
624
Description
Replace Rotating Drum Thinckeners (RDTs) 1 and 2 with in-kind process equipment or a more efficient process equipment. This will include all ancillary
equipment required to make this an operational and a direct replacement for the existing RDTs 1 and 2 and all of their ancillary equipment.
Project #V3179
Priority Essential (2)
Justification
The existing RDT 1 and 2 were put in place as part of the 2002 WWTP renovation and have reached the end of their design life. Both machines have had significant
repairs in the past 5 years but these repairs will not significantly extend the useful design life.
Budget Impact/Other
The estimated impact on the operating budget is less than $10,000.
Useful Life 20 years
Project Name Rotating Drum Thickener Replacement
Category Wastewater Treatment
Type One Phase
Total Project Cost:$1,210,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
80,00080,000PLANNING/DESIGN
1,000,0001,000,000CONSTRUCTION
20,00020,000INSPECTION
10,00010,000ADMINISTRATION
100,000100,000CONTINGENCY
1,210,000 1,210,000Total
Total20222023202420252026Funding Sources
1,210,0001,210,000WASTEWATER FUND
1,210,000 1,210,000Total
625
Description
The project includes the replacement of the control panel and aquisistion of a redundent pump.
Project #V3180
Priority Essential (2)
Justification
This station was placed in service in 2005 and existing deficiencies in the control panel have caused operational and communication problems.
Budget Impact/Other
The estimated impact on the operating budget is less than $10,000.
Useful Life 20 years
Project Name Peninsula Control Panel and Pump Improvement
Category Wastewater Treatment
Type One Phase
Total Project Cost:$97,500
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
2,0002,000PLANNING/DESIGN
85,00085,000CONSTRUCTION
1,0001,000INSPECTION
1,0001,000ADMINISTRATION
8,5008,500CONTINGENCY
97,500 97,500Total
Total20222023202420252026Funding Sources
97,50097,500WASTEWATER FUND
97,500 97,500Total
626
Description
Perform a master plan for the Wastewater Division looking forward for the next 20 years. The study will include the wastewater treatment plant, all sanitary lift
stations, and the sanitary sewer collection system.
Project #V3181
Priority Essential (2)
Justification
The last Master Planning was completed in 2010 and 2011. With changing City development patterns and environmental regulation, updating the master planning
documents is critical for future Division needs.
Budget Impact/Other
Guidance provided by the update planning documents will help with future project to maximize City investments.
Useful Life 15 years
Project Name Wastewater Division Master Plan
Category Wastewater Treatment
Type One Phase
Total Project Cost:$212,000
Contact Tim Wilkey
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
10,00010,000ADMINISTRATION
2,0002,000CONTINGENCY
200,000200,000OTHER
212,000 212,000Total
Total20222023202420252026Funding Sources
212,000212,000WASTEWATER FUND
212,000 212,000Total
627
Description
This is a water main replacement project on Bradford Dr, Louise St, and Wayne Ave. Approximately 1950 feet of 6-inch cast-iron pipe (vintage 1956) will be
replaced with 2,500 feet of 8-inch PVC. The scope of the project will replace or install water main on Bradford Dr from Arthur St to 1st Ave, on Louise St from
Bradford Dr to Wayne Ave, and on Wayne Ave from Wade St to Arthur St.
Project #W3300
Priority Efficiency Improvement (3)
Justification
The existing water main has been subject to 18 water main breaks and has reached the end of its useful life. This project would also make the distribution system
more robust by adding an additional looped feed to the system. This water main feeds Southeast Junior High School, and ranks in the top ten of the water main
replacement matrix.
Budget Impact/Other
This water main replacement project will reduce operations and maintenance cost associated with emergency/after hours repairs. The estimated decrease in
operating expenditures is less than $10,000 per year.
Useful Life 70 years
Project Name Bradford Drive Water Main Replacement
Category Water Operations
Type One Phase
Total Project Cost:$650,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
600,000600,000CONSTRUCTION
50,000 600,000 650,000Total
Total20222023202420252026Funding Sources
650,00050,000 600,000WATER FUND
50,000 600,000 650,000Total
628
Description
Replace approximately 1,600 feet of 12-inch water main (1990 vintage) along Highway 1 from the Hawk Ridge apartments to the north side of Highway 1 across
from the WalMart entrance.
Project #W3313
Priority Essential (2)
Justification
This water main is situated within corrosive soils and has experienced multiple main breaks. Due to being a transmission main, breaks cause very large pressure
losses and disruptions within the distribution system. Replacement of this main with new materials installed to mitigate the corrosive effects of the soils will
provide more reliable service to our customers.
Budget Impact/Other
This project will have a neutral impact on the operating budget as it is the replacement of existing infrastructure.
Useful Life 50 years
Project Name Hwy 1 (Hawk Ridge to WalMart) Water Main Repl
Category Water Operations
Type One Phase
Total Project Cost:$690,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
460,000460,000CONSTRUCTION
20,00020,000INSPECTION
15,00015,000ADMINISTRATION
31,00031,000CONTINGENCY
526,000 526,000Total
Prior
164,000
Total
Total20222023202420252026Funding Sources
626,000626,000WATER FUND
626,000 626,000Total
Prior
64,000
Total
629
Description
Replace the (4) four variable frequency drives (VFDs) on our high service pumps.
Project #W3314
Priority Essential (2)
Justification
The VFD's servicing our high service pumps will have been in operation for approximately 21 years when this project reaches construction. This is a typical life
span for VFD's. The VFD's have begun to show signs of deterioration with the loss of communications due to worn electronics components and the new SCADA
system was modified to accommodate the out-moded communications protocols utilized by these drives. We anticipate continued and more frequent repair
activities as these drives reach the end of their useful life.
Budget Impact/Other
Potential cost savings derived from decreased power usage, less wear on the pumps, and less repair or reactive maintenance.
Useful Life 20 years
Project Name High Service Pump VFD Replacement
Category Water Operations
Type One Phase
Total Project Cost:$650,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
600,000600,000CONSTRUCTION
50,000 600,000 650,000Total
Total20222023202420252026Funding Sources
650,00050,000 600,000WATER FUND
50,000 600,000 650,000Total
Description
Design and install new chlorine feed equipment with associated computer system integration and repairs to the CSI Scrubber system.
Project #W3316
Priority Essential (2)
Justification
The existing automatic chlorine feeders are reaching their designed end-of-life and are no longer supported by the manufacturer. Updating the system components
with current models will allow for more precise control of the chlorine feed system and reduce maintenance time.
Budget Impact/Other
Reduced maintenance time and spare parts load - return-on-investment in approximately 8 years. The chlorine system is a high hazard system that includes a
number of process controls to keep City staff and the surrounding area safe from a release of chemical.
Useful Life 20 years
Project Name Chlorine Feeder System Upgrade
Category Water Operations
Type One Phase
Total Project Cost:$315,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
200,000200,000CONSTRUCTION
200,000 200,000Total
Prior
115,000
Total
Total20222023202420252026Funding Sources
200,000200,000WATER FUND
200,000 200,000Total
Prior
115,000
Total
630
Description
Upgrade the audio and visual equipment in the Water Front Meeting Room with new flat panel screens, associated computer controls, and audio for the use by City
Staff to conduct training events and meetings. Upgrade room lighting with LED lights.
Project #W3317
Priority Efficiency Improvement (3)
Justification
The Water Front Meeting Room has two broken overhead screens, no mounted projector, and an antiquated audio system. The room was originally designed to be
able to host two separate meetings, but has since been adapted to use a large front projector screen that impedes the use of the divider wall and a projector set upon a
collapsable table in the middle of the aisle. This setup has proved to be adequate and cumbersome. The goal is to update the room to include better room usage and
data display functionality.
Budget Impact/Other
The operational budget will be impacted by increased internal service chargebacks for the ITS equipment program. Estimated annual impact is less than $5,000 per
year.
Useful Life 20 years
Project Name Water Front Meeting Room A/V Upgrades
Category Water Operations
Type One Phase
Total Project Cost:$110,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
65,00065,000EQUIPMENT
65,000 65,000Total
Prior
45,000
Total
Total20222023202420252026Funding Sources
65,00065,000WATER FUND
65,000 65,000Total
Prior
45,000
Total
Description
Replace the metal housings enclosing the ground storage reservoir (GSR) back up power generators at the Rochester, Sycamore, and Emerald GSR's.
Project #W3318
Priority Essential (2)
Justification
The ground storage reserviors (GSR's) are provided with backup power generation by diesel generators. These generators are external to the building and enclosed
within metal housings. These housings have deteriorated and are beginning to allow the weather to damage internal components.
Budget Impact/Other
Reduced operational costs associated with annual generator preventative maintenance contract costs. Estimated annual savings is less than $10,000 per year.
Useful Life 20 years
Project Name GSR Generator Enclosure Replacement
Category Water Operations
Type One Phase
Total Project Cost:$40,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
40,00040,000CONSTRUCTION
40,000 40,000Total
Total20222023202420252026Funding Sources
40,00040,000WATER FUND
40,000 40,000Total
631
Description
Replace approximately 2,000 feet of 1964 16-inch ductile iron water main along the north side of Highway 6 from Fairmeadows Blvd. to Industrial Park Rd. with
16-inch PVC water main.
Project #W3320
Priority Critical (1)
Justification
This water main has had five (5) water main breaks since the year 2000, four (4) of which have happened in 2018/2019. The type of break have been majority
corrosion related and it is expected to continue to have main breaks on this main until it is replaced due to corrosive soils. Due to the size and relative location of
the water main in the distribution system the breaks on this line are very disruptive - large pressure swings that cause other water quality and integrity issues as well
as loss of service to critical customers.
Budget Impact/Other
Main breaks on average cost approximately $10,000 each to repair. The main breaks on this stretch of Hwy 6 are significant enough to cause cascading effects such
as more main breaks or the need to flush the distribution system which increases costs. Therefore the replacement of this main will have a direct impact on the
operational budget lessening main break repairs and indirectly by increasing system integrity overall. Savings is anticipated to average $10,000 to $20,000 per year.
Useful Life 70 years
Project Name Hwy 6 (Fairmeadows to Ind Park Rd) Water Main Repl
Category Water Operations
Type One Phase
Total Project Cost:$661,500
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT Lower Muscatine/Ind Park Rd
PLAN None
Status Active
Total20222023202420252026Expenditures
67,50067,500PLANNING/DESIGN
540,000540,000CONSTRUCTION
54,00054,000INSPECTION
67,500 594,000 661,500Total
Total20222023202420252026Funding Sources
661,50067,500 594,000WATER FUND
67,500 594,000 661,500Total
632
Description
An engineering study of dissolved nutrient removal from source water (nitrates, polyfluoroalkyl compounds, mycrositins, etc...), the long-term financial and
environmental sustainability of lime softening, and filter system valving and build-out based on the study results.
Project #W3321
Priority Essential (2)
Justification
Regulations on dissolved ions in source and finished water are changing with federal administrations and increasing evidence of chemcial toxicity which will result
in a need to have treatment technologies capable of ionic removal. Further quicklime and lime solids management costs have continued to increase yearly and a
cost/benefite analysis of lime softening is warranted while investigating treatment technologies. The filters may need modification to accommodate new
technologies. This is a study and will inform future CIP, including five projects on the unfunded list - Nutrient Removal, WTP Filter #6 Buildout, Water Plant
Softener Improvements, Soda Ash Replacement, and Lime Lagoon Outlet Structure Modifications.
Budget Impact/Other
The impact on the operating budget will be negligible.
Useful Life 10 years
Project Name Treatment Technology Study
Category Water Operations
Type Multi-Phase
Total Project Cost:$150,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
150,000150,000PLANNING/DESIGN
150,000 150,000Total
Total20222023202420252026Funding Sources
150,000150,000WATER FUND
150,000 150,000Total
633
Description
Clean and cap portions on the existing laterals of Collector Well #2 and install new 12-inch laterals to increase the production capacity of this raw water well.
Project #W3322
Priority Critical (1)
Justification
Collector Well #2 has degraded specific capacity (amount of water yield per foot of well height) and will continue to decline as the pore spaces in the surrounding
geologic formations plug with fines. Therefore to maintain the usefulness of this high quality water source and to increase its yield capacity lateral cleaning and
lateral installation are necessary.
Budget Impact/Other
Useful Life 70 years
Project Name Collector Well #2 Cleaning and Upgrade
Category Water Operations
Type One Phase
Total Project Cost:$1,000,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
100,000100,000PLANNING/DESIGN
900,000900,000CONSTRUCTION
100,000 900,000 1,000,000Total
Total20222023202420252026Funding Sources
1,000,000100,000 900,000WATER FUND
100,000 900,000 1,000,000Total
Description
Locate with survey grade accuracy all hydrants, valves, tanks, and other above ground accessible water distribution appertenances and deliver in a geographic
information system geometric network with associated metadata for asset management functions.
Project #W3323
Priority Essential (2)
Justification
Asset management requires an accurate asset inventory to reliably know the number, location, and information regarding above and below ground assets. The
budget provided is based on an $18 per structure cost with about 10,000 structures (hydrants, valves, etc.).
Budget Impact/Other
This project will have a negligible impact on the operating budget.
Useful Life 10 years
Project Name Water Distribution Asset Inventory
Category Water Operations
Type One Phase
Total Project Cost:$250,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
20,00020,000PLANNING/DESIGN
230,000230,000CONSTRUCTION
250,000 250,000Total
Total20222023202420252026Funding Sources
250,000250,000WATER FUND
250,000 250,000Total
634
Description
Evaluate and make recommendations to include cost estimates for the removal, repair, and upgrade of environmental systems at the Water Treatment Facility.
[Would precede unfunded project #75]
Project #W3324
Priority Efficiency Improvement (3)
Justification
The Water Treatment Facility was originally designed to have a heated process area and basement storage. Heating the building in the winter or cooling in the
summer is not practical with the existing systems due to the volume of water passing through the processes. Providing for this is not the intent of the project but to
remove unused dilapidated systems and to improve existing air handing to better conform to reality. Additionally the administrative spaces suffer from humidity
intrusion and malfunctioning controls due to improperly situated and sized equipment, and obsolete building controls systems.
Budget Impact/Other
The impact to the operating budget is negligible.
Useful Life 10 years
Project Name Water Plant HVAC Study
Category Water Operations
Type One Phase
Total Project Cost:$75,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
75,00075,000PLANNING/DESIGN
75,000 75,000Total
Total20222023202420252026Funding Sources
75,00075,000WATER FUND
75,000 75,000Total
Description
Replace the roofs on the Water Plant garage, chemical storage rooms, 5 collector wells, 3 deep wells, and emergency generator building.
Project #W3325
Priority Essential (2)
Justification
The existing roofs are showing signs of failure due to age. The roof material is degrading causing leaks inside the buildings. The roofs will need replacement.
Budget Impact/Other
The operating impact of these improvements will be negligible.
Useful Life 20 years
Project Name Roof Replacements
Category Water Operations
Type One Phase
Total Project Cost:$900,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
100,000100,000PLANNING/DESIGN
100,000 100,000Total
Future
800,000
Total
Total20222023202420252026Funding Sources
100,000100,000WATER FUND
100,000 100,000Total
Future
800,000
Total
635
Description
Update treatment processes to better conform with pending regulation. The scope of this project will be informed by the Treatment Study (CIP W3321)
Project #W3326
Priority Essential (2)
Justification
Forecasted regulations include PFAS, Magenese, stricter lead and copper rules, continued intrusion of nutrient runoff, and heavy metal reductions. Climate change
will also continue to cause carbon producing processes to increase operating costs. Due to these factors a treatment study will be commissioned in 2024 to evaluate
the existing unit processes employed by the treatment plant and make recommendations for changes to better conform with climate change and new regulation. Our
expectation is to move away from lime softening and employ membrane filtration.
Budget Impact/Other
The impact to the operating budget may increase or decrease depending on the results of the Treatment Study.
Useful Life 20 years
Project Name Treatment Process Update
Category Water Operations
Type One Phase
Total Project Cost:$600,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
100,000100,000PLANNING/DESIGN
500,000500,000CONSTRUCTION
600,000 600,000Total
Total20222023202420252026Funding Sources
600,000600,000WATER FUND
600,000 600,000Total
Description
Replace approximately 1,900 feet of 12-inch, 1984 ductile iron water main with 16-inch PVC water main.
Project #W3327
Priority Essential (2)
Justification
The existing water main has four corrosion-related water main breaks and signs of continued corrosion within the surrounding wet soils. Replacing the existing with
16-inch PVC will remove the corrosion hazard and mitigate velocity headloss identified during the 2018 water distribution system future growth study.
Budget Impact/Other
This project has minimal impact on the operating budget.
Useful Life 70 years
Project Name Melrose Water Main Camp Cardinal to 218
Category Water Operations
Type One Phase
Total Project Cost:$600,000
Contact Jonathan Durst
Department PUBLIC WORKS
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
600,000600,000CONSTRUCTION
600,000 600,000Total
Total20222023202420252026Funding Sources
600,000600,000WATER FUND
600,000 600,000Total
636
Description
INecessary building envelope repairs include rebuilding the stone parapets and cornices, roof flashing improvements, stone façade pointing and sealing, painting
and sealing exterior wood, and refurbishing historic wood framed windows. The Improvements are based on recommendations from the 2020 Accessibility Study
and the 2021 Master Plan.
Project #K1001
Priority Aesthetic Improvement (4)
Justification
The building is in dire need of tuckpointing and the entrances historically restored. The Senior Center will require a full building assessment to determine the scope
of work and facility master plan over the next ten years.
Budget Impact/Other
There are no additional operating impacts at this time. There are cost savings for reducing building maintenance and repairs. The estimated operating expenditure
savings is less than $10,000 per year.
Useful Life 15 years
Project Name Senior Center Facility Exterior Improvements
Category Senior Center
Type Multi-Phase
Total Project Cost:$3,515,000
Contact LaTasha DeLoach
Department SENIOR CENTER
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
150,000150,000PLANNING/DESIGN
2,420,0002,420,000CONSTRUCTION
50,00050,000ADMINISTRATION
100,000100,000CONTINGENCY
2,720,000 2,720,000Total
Prior
795,000
Total
Total20222023202420252026Funding Sources
700,000700,000GO BONDS-GENERAL
PURPOSE
2,000,0002,000,000TAX INCREMENT FINANCING
2,700,000 2,700,000Total
Prior
815,000
Total
637
Description
This project will include American Disabilities Act (ADA), code, architectural, mechanical, electrical, cosmetic, wayfinding, kitchen, and signage improvements to
all floors of The Center, including a new (ADA) accessible vestibule on East Washington Street. The interior building improvement projects will focus on
sustainable and life cycle cost improvements, with a goal to reduce The Center's carbon foot print. The Improvements are based on recommendations from the 2020
Accessibly Study and the 2021 Master Plan. Lower level fitness rooms will be realigned to better accommodate equipment and to provide adequate space for
classes. The first floor will be converted to a social floor that can be used for public events. Offices will be centrally relocated on the second floor for better
collaboration. The third floor includes a reception area for patrons that park in the ramp and includes realigning classrooms to better accommodate lifelong learning
activities. Energy efficiency improvements and building code upgrades be incorporated into the project.
Project #K1002
Priority Efficiency Improvement (3)
Justification
This project will allow for program and event needs to continue mission work of lifelong learning, connection and community engagement of residents 50 plus. This
will provide adequate office space and classrooms, increase customer service capacity, improve wayfinding, provide improved lighting and design for older adults,
aging eyes and decreased capacity which occurs when serving older adults. This project will address sustainability needs, and provide more access to community
members for rental space. It will also address aging infrastructure, sustainability needs, and provide more access to community members for rental space.
Budget Impact/Other
Renovating the Senior Center will increase revenue by creating a space where more community members will have events for weddings, small conferences,
retirement events, etc. Improved wayfinding and tailored design for older adults will allow for longevity of The Center for older adults for generations to come.
There will be a need for a new staff to assist with additional programs needed. The estimated net additiona cost to the operating budget is approximately $75,000
per year.
Useful Life 30 Years
Project Name Senior Center Interior Improvements Project
Category Senior Center
Type Multi-Phase
Total Project Cost:$3,400,000
Contact LaTasha DeLoach
Department SENIOR CENTER
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN Senior Center Facility Study
Status Active
Total20222023202420252026Expenditures
395,000245,000 150,000PLANNING/DESIGN
2,715,0001,270,000 1,445,000CONSTRUCTION
90,00040,000 50,000ADMINISTRATION
200,000100,000 100,000CONTINGENCY
1,655,000 1,745,000 3,400,000Total
Total20222023202420252026Funding Sources
2,000,0001,000,000 1,000,000FACILITY REPLACEMENT
RESERVE
1,400,000700,000 700,000GO BONDS-GENERAL
PURPOSE
1,700,000 1,700,000 3,400,000Total
638
Description
This project involves the installation of additional high-definition cameras in parking facilities.
Project #T3021
Priority Efficiency Improvement (3)
Justification
The cameras will aid in securing facilities, following up on incidents, and evaluating parking demand. Several windows have been damaged on the rooftop
stairwells during 2021.
Budget Impact/Other
This project will increase the operating expenditures due to the maintenance of the new equipment. The estimated impact on the operating budget is less than
$10,000 per year.
Useful Life 10 years
Project Name Video Cameras for Parking Facilities
Category Parking Operations
Type Multi-Phase
Total Project Cost:$200,000
Contact Darian Nagle-Gamm
Department TRANSPORTATION SERVIC
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
100,000100,000EQUIPMENT
100,000 100,000Total
Prior
100,000
Total
Total20222023202420252026Funding Sources
100,000100,000PARKING FUND
100,000 100,000Total
Prior
100,000
Total
Description
Purchase of a new vehicle with license plate reader techonolgy to aid in parking enforcement in 2019, and the purchase of a replacement license plate reader for
existing vehicle that is scheduled for replacement in 2020.
Project #T3022
Priority Efficiency Improvement (3)
Justification
The new vehicle and license plate recognition equipment would be dedicated to the enforcement of the Chauncey Swan and Harrison Street parking facilties and
would also be used for enforcing loading zones, street storage, and identification of vehicles on the tow-list.
Budget Impact/Other
The additional vehicle will increase fuel, insurance, maintenance, and replacement charges. By adding another enforcement vehicle, parking fine revenue should
increase as well. The estimate increase in expenditures is $15,000 to $20,000 per year and the estimated increase in revenue is $25,000.
Useful Life 10 years
Project Name Parking Enforcement Vehicles
Category Parking Operations
Type Multi-Phase
Total Project Cost:$180,000
Contact Darian Nagle-Gamm
Department TRANSPORTATION SERVIC
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
90,00090,000EQUIPMENT
90,000 90,000Total
Prior
90,000
Total
Total20222023202420252026Funding Sources
90,00090,000PARKING FUND
90,000 90,000Total
Prior
90,000
Total
639
Description
Replacement automated parking equipment in parking ramps.
Project #T3023
Priority Essential (2)
Justification
Original equipment installed beginning in 2009. Performance is degrading as equipment is reaching the end of its useful life requiring an increasing amount of staff
time to address issues.
Budget Impact/Other
Installing new automated parking equipment at all gated facilities will have a positive effect on the operating budget, reducing the amount of staff time required to
attend to malfunctioning equipment. The estimated decrease in operating expenditurs is less than $40,000 per year. Loan payments to the Landfill Replacement
Reserve will be approxiamtely $60,000 per year including interest expense for 20 years for a $1 million internal loan.
Useful Life 10 years
Project Name Parking Ramp Automated Parking Equipment
Category Parking Operations
Type Multi-Phase
Total Project Cost:$1,275,000
Contact Darian Nagle-Gamm
Department TRANSPORTATION SERVIC
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
1,000,0001,000,000EQUIPMENT
1,000,000 1,000,000Total
Prior
275,000
Total
Total20222023202420252026Funding Sources
1,000,0001,000,000LANDFILL REPLACEMENT
RESERVE
1,000,000 1,000,000Total
Prior
275,000
Total
Description
Project to replace all LED fixtures in the Court Street Transportation Center, Capitol Street ramp, Dubuque Street ramp, Tower Place ramp, Chauncey Swan Ramp,
and fixtures in other facilities as they age out of production.
Project #T3025
Priority Essential (2)
Justification
LED technologies have evolved since our early adoption in our parking facilities nearly a decade ago. Many of the early-style fixtures need to be replaced. During
2021 the fixtures in the Court Street Transportation Center were replaced. This project will allow the replacements of the Capitol Street and Dubuque Street
facilities in 2022, and Tower Place and Chauncey Swan facilities in 2023.
Budget Impact/Other
It will cost approximately $10,000 in staff time to replace all fixtures in the Capitol Street facility. The impact on the operating budget is negligible.
Useful Life 10 years
Project Name Replacement of LED fixtures in Parking Facilities
Category Parking Operations
Type One Phase
Total Project Cost:$400,000
Contact Darian Nagle-Gamm
Department TRANSPORTATION SERVIC
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
400,000200,000 200,000CONSTRUCTION
200,000 200,000 400,000Total
Total20222023202420252026Funding Sources
400,000200,000 200,000PARKING FUND
200,000 200,000 400,000Total
640
Description
This project will modify the existing drainage pipe network and divert storm water from the upper decks to the exterior of the structure rather than routing it through
the lower level.
Project #T3026
Priority Critical (1)
Justification
The lower level of Tower Place Parking Ramp repeatedly floods during high intensity rain events causing significant property damage.
Budget Impact/Other
There is no anticipated impact to the operating budget.
Useful Life 50 years
Project Name Tower Place Drainage Modifications
Category Parking Operations
Type One Phase
Total Project Cost:$237,500
Contact Darian Nagle-Gamm
Department TRANSPORTATION SERVIC
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
50,00050,000PLANNING/DESIGN
150,000150,000CONSTRUCTION
15,00015,000INSPECTION
7,5007,500ADMINISTRATION
15,00015,000CONTINGENCY
237,500 237,500Total
Total20222023202420252026Funding Sources
237,500237,500PARKING FUND
237,500 237,500Total
641
Description
Repair/replacement of the stairwell rooftops for the Capitol Street Ramp and Dubuque Street Ramp.
Project #T3027
Priority Critical (1)
Justification
The roofs of two stairwells located at the Capitol Street Parking Ramp and the two stairwells at the Dubuque Street Parking Ramp need repaired or replaced. These
have reached the end of their useful life and will begin to cause structure damaged if not addressed.
Budget Impact/Other
This project will greatly reduce future structural maintenance and repair costs. The impact on the current operating budget is a reduction of expenditures due to
decreased repair and maintenance costs. The estimated decrease in operating expendtires is less than $15,000 per year.
Useful Life 40 Years
Project Name Parking Ramp Stairwell Roof Replacement
Category Parking Operations
Type One Phase
Total Project Cost:$50,000
Contact Darian Nagle-Gamm
Department TRANSPORTATION SERVIC
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
10,00010,000PLANNING/DESIGN
40,00040,000CONSTRUCTION
50,000 50,000Total
Total20222023202420252026Funding Sources
50,00050,000PARKING FUND
50,000 50,000Total
Description
Design and remodel of Customer Service and Administrative Support office areas of the Tower Place parking ramp.
Project #T3028
Priority Efficiency Improvement (3)
Justification
Administrative office space demand has greatly changed at our Tower Place location. This remodel will provide dedicated workspaces for three Customer Services
Representatives who currently share two work stations in an open office space. The remodel will also provide dedicated office space for Supervisory staff including
Operations Supervisors, Director, Associate Director, and a Data Analyst. Currently the Supervisory staff operate in an open workspace room with very limited
privacy. Upgraded funiture will also be part of this project.
Budget Impact/Other
There is no anticipated impact to the operating budget.
Useful Life 20 years
Project Name Tower Place Office Remodel
Category Parking Operations
Type One Phase
Total Project Cost:$132,000
Contact Darian Nagle-Gamm
Department TRANSPORTATION SERVIC
MATCH %NONE
GRANTEE NONE
TIF DISTRICT None
PLAN None
Status Active
Total20222023202420252026Expenditures
12,00012,000PLANNING/DESIGN
120,000120,000CONSTRUCTION
132,000 132,000Total
Total20222023202420252026Funding Sources
132,000132,000PARKING FUND
132,000 132,000Total
642
Description
This project involves the construction of a new transit facility for maintenance operations and storage. As part of this project, the storage area will be expanded
allowing for an increase in fleet size and the maintenance facility will be upgraded. The relocation will address the environmental issues that exist at the current
facility and allow for the redevelopment of a major commercial site at the corner of Highway 6 and Riverside Drive.
Project #T3055
Priority Essential (2)
Justification
The current tranist maintenance facility has outlived its useful life and is in need of replacement. The facility has structural issues from the surrounding area, and a
new facility will improve the delivery of service. The new facility would be eventually be consolidated with Equipment Services into one facility to better utilize
space and be more cost effective. Grants are being sought to assist in the construction.
Budget Impact/Other
The replacement of transit maintenance facility should be to a newer and more energy efficient facility, however, the new facility will be larger and contain more
operational functionality. The additional size and capability of the facility will most likely offset the potential savings from a newer and more efficient facility.
Additional savings/cost from this facility has not been determined.
Useful Life 40 Years
Project Name Transit Maintenance Facility Relocation
Category Transit Operations
Type One Phase
Total Project Cost:$20,200,000
Contact Darian Nagle-Gamm
Department TRANSPORTATION SERVIC
MATCH %20%
GRANTEE FTA
TIF DISTRICT None
PLAN Transportation Plan
Status Active
Total20222023202420252026Expenditures
20,000,00020,000,000CONSTRUCTION
20,000,000 20,000,000Total
Prior
200,000
Total
Total20222023202420252026Funding Sources
15,000,00015,000,000FEDERAL GRANTS
5,000,0005,000,000TRANSIT FUND
20,000,000 20,000,000Total
Prior
200,000
Total
643
Project Name Description Unfunded Amt
1 - Bridges
1 Iowa Avenue Culvert This project will include the removal and replacement of the
existing reinforced concrete box culvert with a new three-
sided arch culvert. The project will also include removal and
replacement of slope protection adjacent to the bridge on
Ralston Creek, removal and replacement of street pavement
and sidewalk, and site restoration.
$3,500,000
2 F Street Bridge This project involves the removal and replacement of the
existing corrugated metal arch bridge with a larger bridge.
$773,000
3 Fourth Avenue Bridge This project will replace the bridge over the South Branch of
Ralston Creek at Fourth Avenue and will include sidewalks.
Possibility of approximately $75,000 state funding.
$773,000
4 Sixth Avenue Bridge This project involves the removal and replacement of the
existing twin box culvert with a larger bridge.
$773,000
5 Third Avenue Bridge This project will include the removal and replacement of the
existing concrete bridge with a new single-span reinforced
concrete box culvert. The project will also include removal
and replacement of slope protection adjacent to the bridge on
Ralston Creek South Branch, removal and replacement of
street pavement, and storm sewer improvements.
$650,000
2 - Streets
6 Benton Street - Orchard To
Oaknoll
This is a capacity related improvement identified by the
Arterial Street Plan.
$5,150,000
7 Brookland Park Drive
Rehabilitation
This project will include reconstruction of Brookland Park
Drive and updates to utilities.
$1,450,000
8 Dodge St - Burlington To Bowery Street reconstruction and storm sewer improvements. This is
a joint project with the IDOT.
$13,250,000
9 Dubuque Rd Paving - Bristol To
Dodge
Reconstruct and upgrade to urban cross sections. $1,339,000
10 Dubuque Street Access Road And
Traffic Signal
This project will construct an access drive from the north end
of Laura Dr to Dubuque Street, south of the Interstate 80 /
Dubuque St interchange. May also facilitate a second means
of access from the Peninsula area to Dubuque St.
$2,000,000
11 Emerald Street Diamond Grinding This project will diamond grind all of Emerald Street to
remove the slab warping that interferes with the use of this
street by fire trucks.
$212,000
12 Gilbert / Us 6 Intersection Left
Turn Lanes
Reconstruct the intersection of Gilbert & US 6 to include dual
left turn lanes on Gilbert St.
$4,840,000
13 Gilbert St Iais Underpass This project relocates the sidewalks of the Gilbert St.
underpass at the IAIS Railroad. The sidewalks are moved
further from the street and existing erosion problems are
addressed.
$327,000
14 Old Hwy 218 Streetscape Streetscape improvements on Old Hwy 218 entrance -
Sturgis Ferry Park to US Hwy 6. This project includes
landscaping, lighting and sidewalk improvements. The
project should be coordinated with Sturgis Ferry Park
upgrade and /or Riverside Drive Redevelopment project.
$812,000
15 Highway 965 Extension This project will be initial phase of constructing Hwy 965
extended from the south side of Hwy 218 to Melrose Avenue
to arterial standards.
$9,167,000
City of Iowa City
Capital Improvement Program
Unfunded Projects
644
Project Name Description Unfunded Amt
City of Iowa City
Capital Improvement Program
Unfunded Projects
16 Mccollister - Sycamore St To Scott
Blvd
Extend proposed McCollister Boulevard from Sycamore
Street to Scott Boulevard.
$9,088,000
17 Muscatine Avenue
Reconstruction, Iowa To First Ave
This project will reconstruct Muscatine Avenue from Iowa
Avenue to 1st Avenue.
$10,510,000
18 Oakdale Blvd This project would construct an extension north across I-80 to
a new intersection with Iowa Hwy 1.
$15,000,000
19 Oakdale Blvd-Hwy 1 To Prairie Du
Chien Rd
This project would construct Oakdale Blvd from Hwy 1, west
to Prairie Du Chien Road.
$8,240,000
20 Peninsula Secondary Access
Road
This project will establish a more reliable access to the
Peninsula neighborhood by either elevating Foster Rd from
Laura Dr to No Name road by creating a secondary access to
the area. This project will not be necessary if the Taft
Speedway Levee Project is constructed.
$2,883,000
21 Riverside Drive Streetscape Phases II to V of the South Riverside Drive Streetscape
Master Plan, which includes improvements to the west side of
Riverside Drive from Benton to Hwy 6 and the east side of
Riverside from Myrtle to Hwy 6. Project includes
consolidation of driveways, undergrounding of utilities, and
installation of sidewalks and landscaping.
$2,650,000
22 Rohret Rd Improvements-
Lakeshore To Limits
Project will reconstruct Rohret Rd to urban standards. $1,813,000
23 South Gilbert Street Improvements Reconstruction from Benton Street to Stevens Drive. This
project does not include improvements to the Gilbert St. /
Highway 6 intersection.
$4,326,000
24 South Arterial And Bridge, Us218
To Gilbert Street
Construction of a south arterial street and bridge over the
Iowa River, connecting from Old Hwy 218/US 218
interchange on the west side of the Iowa River to Gilbert
Street/Sycamore 'L' intersection .
$15,987,000
25 Sycamore-Hwy 6 To Highland This project involves additional lanes to improve capacity and
storm sewer improvements.
$750,000
26 Sycamore Street - East-West Leg
From "L" To South Gilbert
This project will reconstruct Sycamore Street to arterial
standards using the Complete Streets Policy. This phase will
be the east-west leg of Sycamore Street.
$3,040,000
27 Taft Avenue – Herbert Hoover
Hwy To Lower West Branch
Reconstruct Taft Avenue from Herbert Hoover Hwy to Court
Street.
$3,300,000
28 Taft Avenue – American Legion
Road To 420th Street
Reconstruct Taft Avenue from American Legion Road to
Herbert Hoover Hwy.
$8,200,000
29 Laura Drive Reconstruction Reconstruction of entire length of Laura Drive to standard two
lane width with curb, storm sewer and sidewalk.
$2,000,000
30 Linn Street Reconstruction,
Burlington To Iowa
This project is part of the downtown streetscape master plan.
This project reconstructs Linn Street from Burlington Street to
Iowa Avenue. Project also improves sidewalk pavement,
addresses critical update to water main, replaces and
relocates storm sewer between Washington & Iowa.
$1,935,000
31 Clinton Street Streetscape Improve Clinton Street Streetscape south of Burlington Street
consistent with the Riverfront Crossings Plan. Minor
pavement improvements and lane striping a part of project.
$1,500,000
32 Kimball Road Reconstruction Reconstruct Kimball road from N. Gilbert Street to N.
Governor Street. Project includes 22 foot wide PCC street
and a 5 foot wide sidewalk on one side of the street, new 8"
DIP water main, new storm sewer, and sanitary service
improvements.
$3,480,000
645
Project Name Description Unfunded Amt
City of Iowa City
Capital Improvement Program
Unfunded Projects
33 Interstate 80 Aesthetic
Improvements
Landscaping and aesthetic treatments in the Interstate 80
corridor. The objective of this project is to mitigate the visual
impact of the addition of a third lane to I-80 and to provide
cohesive and pleasing feel to the Iowa City corridor.
$300,000
34 Towncrest Drive Reconstruction A private street that the property owners would dedicate the
right of way to the City, and the City will reconstruct. Parking
along and adjacent to the right of way will be reconfigured to
better facilitate vehicle movement and pedestrian safety.
$600,000
35 Gilbert Street Functional Design -
Hwy 6 To Kirkwood
Obtain consulting services to provide a functional design of
Gilbert Street between Hwy 6 & Kirkwood Avenue. The
functional design should take into account all previous design
work completed for the corridor.
$60,000
3 - Transportation Services
36 Rock Island Railroad Depot
Restoration
Preparation of Old Rock Island Railroad Depot for Amtrak
service, including platform construction, lighting, utilities,
passenger information display, ticketing kiosks, canopy,
warming shelter, signage, parking, and accessibility
improvements.
$5,381,000
37 Capitol & Dubuque Street Parking
Ramp Façade Improvements
To construct façade improvements on the Capitol Street and
Dubuque Street parking ramps to improve their aesthetic
appearance in these high profile, high traffic areas.
$1,000,000
4 - Ped & Bike Trails
38 Iowa River Trail, Highway 6 To
Sturgis Ferry Park
This project will extend the Iowa River Trail from just north of
Highway 6 to Sturgis Ferry Park on the west side of the Iowa
River.
$1,180,000
39 Iowa River Trail, Gateway
Segment
Construction of a trail extension adjacent to (east) of the Iowa
River between Park Road and the University of Iowa
pedestrian bridge.
$500,000
40 Windsor Ridge Trail Extension The project includes the extension of a 10' wide trail along
north Branch of Snyder Creek from Scott Boulevard to
American Legion Road.
$1,200,000
41 Old Highway 218 Trail/Wide
Sidewalk
This project will construct an 8' wide sidewalk adjacent to Old
Highway 218 between Sturgis Ferry Park and McCollister
Boulevard.
$550,000
42 Crandic Railroad Rails-To-Trails
Project
The project removes the existing Crandic tracks and
repurposes the existing corridor for a 10' multi-use trail
approximately between Oakdale Boulevard in Coralville to
Gilbert Street in Iowa City (approximately 6.1 miles). Iowa
City's portion of the project is approximately 1.75 miles.
$1,575,000
43 Myrtle Ave Sidewalk Infill The project will construct sidewalk along the north side of
Myrtle Avenue between Greenwood Drive and Olive in order
to fill in a gap in the City’s sidewalk network.
$155,000
44 Southgate Ave Iowa River Trail
Connector
This project will construct a trail connection along Southgate
Avenue from Gilbert Street to the Iowa River Trail.
$250,000
45 Willow Creek Trail - Phase Iii Construct a trail from Willow Creek Drive, under Highway
One, around perimeter of airport, to connect with Iowa River
Corridor (IRC) Trail.
$870,000
46 Willow Creek Trail-West Connect Willow Creek Trail from its current west terminus via
a tunnel under Highway 218, to connect with the trail in
Hunters Run Park and further west.
$2,814,000
646
Project Name Description Unfunded Amt
City of Iowa City
Capital Improvement Program
Unfunded Projects
5 - Wastewater
47 North Branch Dam Trunk Sewer This project extends easterly along Ralston Creek from the
North Branch Dam to Scott Boulevard.
$3,860,000
48 Northeast Trunk Sewer Reconstruction of an under-sized sewer through the northeast
neighborhoods.
$5,221,000
49 Sanitary Sewer Extension - Scott
To Hickory Trail
This project includes the design and construction of a sanitary
sewer trunk extension between Scott Boulevard and Hickory
Trail.
$790,000
50 New Cold Storage Building Construct 90' by 40' covered roof area with open side similar
to the Sludge Storage area. Building to be the same
dimension of the existing cold storage building.
$340,000
51 Geo-Thermal Hvac Conversion Project would include the conversion of the HVAC system to
Geo-Thermal. Installation of Geo-thermal loops, new pump
systems, new chiller, and improved controllers required to
operate the system.
$300,000
6 - Water
52 West Side Ground Storage
Reservoir
Construction of a two million gallon ground or elevated
storage reservoir with associated pumping station and
generator west of US-218. Current land acquired for this
reservoir is southeast of the Slothower Rd at Hebl Ave
$4,000,000
53 Nutrient Removal Project This project will be for the reduction of dissolved nutrients (i.e.
nitrates) in the source water. The project is preceded by a
study. The study will review treatment technology options
(i.e. reverse osmosis, biological treatment) and the long-term
viability of continued lime softening.
$700,000
54 Collector Well #1 Rehabilitation Clean two of the existing laterals and cap one existing lateral
of Collector Well #1. Install two new 12-inch laterals to
increase the production capacity of this raw water well.
$1,000,000
55 Water Treatment Plant Filter #6
Buildout
Add underdrains, granular media, controls, and
instrumentation to filter bay #6. This bay was left unfinished
to allow for future expanded production. The project will also
repair or replace a number of filter control valves. The project
will be informed by the Treatment Study.
$1,500,000
56 Well Field Electrical Cable
Replacement
Replace aging medium voltage (13,200V) cabling and install
communication fiber to wells at the Water Plant and
Peninsula sites.
$1,000,000
57 Lee/Highwood Street Water Main
Replacement
This is a water main replacement project with respective
street and sidewalk replacement at Lee Street and Highwood
Street. Approximately 550 feet of 6" cast-iron pipe (vintage
1951) will be replaced with 6" PVC pipe. Approximately 300
feet of PVC will be installed where no pipe has existed
previously.
$195,500
58 Deforest Ave Water Main
Replacement
Approximately 500 feet of 6-inch cast-iron pipe (vintage 1958)
will be replaced with 500 feet of 8-inch PVC on the 900 block
of Deforest Avenue.
$350,000
59 Giblin Drive Water Main
Replacement
This is a water main replacement project with respective
street and sidewalk replacement. Approximately 620 feet of 6-
inch cast-iron pipe (vintage 1953) will be replaced with 8"
PVC.
$246,350
647
Project Name Description Unfunded Amt
City of Iowa City
Capital Improvement Program
Unfunded Projects
60 Sixth Avenue Water Main
Replacement
This is a water main replacement project with respective
street and sidewalk replacement. Approximately 650 feet of 6-
inch cast-iron pipe (vintage 1974) will be replaced with 8"
PVC.
$340,000
61 Water Plant Softener
Improvements
Automate manual operating procedures, motorize
concentrator adjustment and motorized valve adjustor for the
small influent valve. This project will be informed by the
Treatment Study
$75,000
62 Well House & Generator Building
Roof Replacement
Replace the roofs on the 5 collector wells, 3 deep wells, and
emergency generator building.
$500,000
63 Lime Lagoon Outlet Structure
Modifications
Modify the lagoon outlet structure to an open channel design.
This project will be informed by the Treatment Study.
$500,000
64 Market Street Water Main -
Madison To Clinton
Extend 20-inch water main from Madison to Clinton on Market
St. Tie in 12-inch on Clinton St. to 16-inch at Bloomington St.
This project will be preceded by the abandonment of the 20-
inch main along the old Davenport St right-of-way between
dormitories.
$1,400,000
65 Bloomington Gsr
Decommissioning
Decommission the Bloomington ground storage reservoir
within the University of Iowa Campus Parking Ramp and
return the space to the University of Iowa per the associated
28E agreement. The 28E agreement expires on December
31, 2038. (Resolution No. 88-176)
250,000$
66 Soda Ash Replacement Remove the existing soda ash and ammonia chemical feed
systems. Replace the existing powdered soda ash feed
system with a liquid soda ash feed. The use of soda ash is
to increase alkalinity of the source water for lime softening
purposes. This is necessary if drawing from the river. This
project will be informed by the Nutrient Study.
1,000,000$
67 Sand Pit Pumping Station
Rehabilitation
Clean and inspect the laterals of the Sand Pit Pumping
Station. Replace and repair the lateral isolation valves and
t
250,000$
68 East Side Water Tower Construct a two million gallon ground or elevated storage
reservoir within the East Pressure Zone.
4,000,000$
69 Sycamore Gsr Replacement Replace the two million gallon ground storage reservoir
located on Sycamore Street with a ground or elevated two
million gallon storage tank along McCollister Blvd.
4,000,000$
70 Emerald And Rochester Gsr
Improvements
Upgrade or expand the buildings at the Emerald and
Rochester ground storage reservoirs. Add a third pump to
both ground storage reservoirs. Replace the backup
generators at both ground storage reservoirs.
1,500,000$
71 Melrose & Westgate 16-Inch
Water Main
Install 16-inch water main parallel to the existing water main
on Melrose Ave from Dublin Rd to Westgate St and on
Westgate St from Melrose Ave to Benton St. This project
would reduce velocity headloss from the Emerald ground
storage reservoir to customers west of US-218, increasing
service pressure. This project will be evaluated by hydraulic
modeling after the West Side GSR project is completed.
4,000,000$
72 Bulk Water Station At Public
Works Facility
Construct a new bulk water filling station on the Public Works
Campus to replace the station to be demolished at the
existing Equipment / Transit site.
150,000$
73 Lighting Upgrades To Led Upgrade aging water treatment facility lighting to LED's 250,000$
648
Project Name Description Unfunded Amt
City of Iowa City
Capital Improvement Program
Unfunded Projects
74 Construct New Collector Well #3 Add an additional radial collector well for high quality source
water production. The project will need to be a hydrogeologic
study and cost/benefit analysis between adding collector
laterals to existing collector wells or constructing a new
collector well.
4,000,000$
75 Hvac System Replacement &
Remove Process Area Heaters
Replace and upgrade aging HVAC equipment and controls at
the water treatment facility. Remove gas overhead heaters
and associated gas lines, electrical, and exhaust piping. The
heaters are not used and in time pose a safety hazard.
1,000,000$
76 Shop And Chemical Storage Roof
Replacements
Replace the adhered membrane roof on the water treatment
facility garage and chemical storage sections.
300,000$
77 Teeters Ct Water Main
Replacement
Replace approximately 410 linear feet of 6-inch 1950 cast iron
water main on Teeters Ct. The water main has experienced
three main breaks and services Lincoln Elementary.
125,000$
78 Hwy 6 (Industrial Park Rd To
Riveria)
Replace approximately 1,400 linear feet of 12-inch 1971
ductile iron water main on Highway 6. The water main has
experienced two water main breaks. Due to the size of the
water main, it's proximity to the Sycamore reservoir, and 16-
inch water main on the north side of Highway 6, breaks tend
to cause large system disruptions.
450,000$
79 Reseal Water Treatment Plant
Exterior
Reseal the concrete exterior of the water treatment plant
facility.
100,000$
80 Southlawn Dr Water Main
Replacement
Replace approximately 1,100 linear feet of 6-inch 1962 cast
iron water main on Southlawn Dr (800-900 blk). The water
main has experienced 10 main breaks and services Lucas
Elementary.
400,000$
81 Melrose Water Main Camp
Cardinal To Us-218
Replace approximately 1,900 feet of 12-inch, 1984 ductile iron
water main with 16-inch PVC water main.
600,000$
82 Pwf Water Material Outdoor
Covered Storage
Installation of paving and covered outdoor material storage
structures to protect water distribution materials from the
elements.
100,000$
83 Water Plant And Gsr Gate
Replacement
Replace the (3) water plant site gates and the (3) GSR gates
(Rochester, Emerald, and Sycamore).
100,000$
84 Process Flow Meter And Valve
Replacements
Replace (14) flow meters within the treatment plant and wells.
Replace process valves coincident to the flow meters and
filters.
1,200,000$
85 Water Plant And Peninsula Well
Field Fiber Optic Cable
Install fiber optic communication cable to all wells and remove
existing radio telemetry.
1,000,000$
7 - Stormwater
86 Carson Lake Regional Storm
Water
Construction of a regional storm water management facility
on the middle branch of Willow Creek immediately west of
Highway 218. This facility will serve development west of
Highway 218 and south of Rohret Road.
$1,160,000
87 Riverfront Crossings Storm Sewer Storm sewer improvements in the Central Crossings Sub-
District.
$1,375,000
88 Iowa Avenue Culvert Repairs This project will repair a box culvert that carries Ralston
Creek under Iowa Avenue.
$348,000
649
Project Name Description Unfunded Amt
City of Iowa City
Capital Improvement Program
Unfunded Projects
89 N. Branch Basin Excavation Aerial mapping done for the update to the flood plain maps
revealed that sedimentation has consumed a portion of the
capacity of the facility. This basin is located in Hickory Hill
Park.
$135,000
90 Olympic Court Storm Water Storm sewer retrofit to relieve localized flooding from storm
water runoff.
$464,000
91 Sunset Street Storm Sewer The area just north and south of Kineton Green, east of
Sunset, has experienced back yard flooding and drainage
problems.
$440,000
92 Riverside Drive & Arts Campus
Storm Sewer
This will be a joint project with the University of Iowa to
upgrade the Riverside Drive / Arts Campus storm sewer and
lift station to perform better during future floods.
$1,000,000
8 - Parks & Recreation
93 Recreation / Aquatic Center As recommended in the Parks and Recreation Master Plan,
construct a major new Recreation & Aquatic Center, probably
in the western part of Iowa City.
$16,000,000
94 Mercer Park Pool Improvements This project would include the replacement of the two pool
bulkheads, deck tile, dive stands, and the renovation of the
women's locker room from a shared shower space to two
separate shower spaces.
$500,000
94 Waterworks Park Boat Ramp This project is to add a boat ramp to access the Iowa River in
the northeast corner of Waterworks Park. Improvements
include a boat ramp, boat trailer parking, a boat dock, and an
access road.
$250,000
95 Riverfront Crossings Park - Phase
4
Phase 4 of the Riverfront Crossings Park master plan adds a
new river access, an amphitheater, a kayak launch, and new
river trails.
$1,353,000
96 Riverfront Crossings Park
Restroom & Bridge
Construction of second restroom/shelter by Nature Play and
second bridge to 2nd Street; also includes removing an
abandoned trunk sewer line.
$910,000
97 Gilbert Street/Park Maint Shop
Boat Ramp
Addition of an accessible boat access to the Iowa River from
the parking lot at the Park Maintenance Shop.
$245,000
98 Iowa River Trail, Benton To
Highway 6
This project will extend the Iowa River Trail from Benton St to
Highway 6, on the west side of the Iowa River. Future
phases of the trail could extend to Sturgis Ferry Park and on
top of the west side levee to McCollister Blvd.
$1,700,000
99 Ralston Creek Trail Under Iowa
Interstate Railroad
The project would involve constructing a trail connection
under the Iowa Interstate Railroad that connects the existing
trail along the west side of Ralston Creek, north of the Iowa
Interstate Railroad, to the proposed trail that will be
constructed along the west side of Ralston Creek as part of a
development located south of the Iowa Interstate Railroad.
$1,700,000
100 Sand Prairie Enhancement Take steps to clear, re-seed and perform low impact
development on the 38 acre sand prairie and adjacent
McCollister property acquired in 2004/05.
$273,000
101 Mercer Park Ball Diamond #4
Renovation
This project would reconfigure ball diamond #4 at Mercer
Park to realign the field to a NW orientation. This would
include the removal of the existing field, fencing, and
$374,000
102 Kicker's Park Playground
Replacement
Replace playground #1 at Kickers Athletic Complex as it is
reaching the end of projected serviceable life. Project also
adds ADA compliant paths.
$185,000
650
Project Name Description Unfunded Amt
City of Iowa City
Capital Improvement Program
Unfunded Projects
103 Calder Park Playground
Replacement
Replace the playground at Calder Park. Site constraints keep
this as a smaller piece of equipment.
$135,000
104 Second Parking Lot At Ashton
House
Provides for additional parking on the north side of the Ashton
House to support larger events at the facility.
$300,000
105 Lower City Park Master Plan
Improvements
Implement changes to make the park more resilient to
flooding. Follows from the 2015 master plan.
$23,268,522
106 East Side Sports Complex
Improvements
Build out of a new 73 acre park on the City’s east side. The
park includes expansion of various field sports as well as
serves as a neighborhood amenity. Follows from the 2015
master plan.
$14,034,794
107 Terry Trueblood Recreation Area
Parking Expansion
Expansion of the parking areas with addition of 100 parking
spaces at the Terry Trueblood Recreation Area lodge and
lake.
$225,000
108 Wetherby Park Entrance And
Parking Lot Improvements
Connect Broadway sidewalks to the trail system in Wetherby
Park. Resurface the parking lot and basketball court adjacent
to parking lot. A trail extension will also be made to the
Community Garden area in order to provide ADA access.
$100,000
9 - Other Projects
109 Burlington Street Median Construct the Burlington Street median from Gilbert Street to
Madison Street. Project includes relocation of water and
sewer utilities. This project will require a traffic signal
preemption system. (Part of the Riverfront Crossings
amendment to City-University URA).
$1,973,000
110 Cemetery Columbarium Construction of a columbarium. $405,000
111 City Hall Relocation Relocate and expand / modernize City Hall and City Council
Chambers.
$12,000,000
112 Police Evidence Storage Facility Construction of a permanent evidence storage facility. $929,000
113 Central Police Station Relocation Relocate and expand / modernize Central Police Station. $19,000,000
114 Fire Station #1 Relocation Relocate and expand / modernize Central Fire Station #1. $11,593,000
115 Fire Station #5 Construction of Fire Station #5 in the South Planning District. $2,898,000
116 Fire Station #6 Construction of Fire Station #6 in the Southwest Planning
District.
$2,898,000
117 Flood Buyouts This project will provide funds for the purchase of houses in
designated flood hazard buyout areas after FEMA and CDBG
buyout programs have ended.
$530,000
118 Riverside Drive Redevelopment This project includes methane abatement, excavation, and fill
at the 7 acre site owned by the City at Riverside Dr. and Hwy
6. This site preparation would allow for marketing of this
property for commercial development.
$2,527,000
119 Airport Equipment Shelter Snow removal equipment was previously stored in United
Hangar. Equipment Shelter would provide enclosed storage
for equipment.
$337,500
120 Airport Perimeter Road Construction perimeter road for maintenance and fueling
vehicles to travel to south development area.
$267,700
121 South Airport Site Development South General Aviation area site development with access
roadway and utilities.
$2,125,100
122 Hangar A Door Replacement Hangar A door replacement; hangar A has 10 doors to be
replaced.
$200,000
123 Summit Street Historic Plan Streetscape and intersection elements through Summit Street
Historic District.
$302,000
651
Project Name Description Unfunded Amt
City of Iowa City
Capital Improvement Program
Unfunded Projects
124 Traffic Signal Pre-Emption System This project will install a city-wide Geographic Information
System based traffic signal pre-emption system for
emergency vehicles. This system is necessary if the
Burlington St Median Project is constructed between Madison
St and Gilbert St.
$1,221,000
125 Iowa Interstate Railroad Quiet
Zones
The Quiet Zones project would be for design and
implementation of required upgraded warning devices and
physical infrastructure (medians and gates) for four at-grade
street crossings. The upgrades would improve safety at each
crossing and reduce the need for trains to sound their horns.
$1,000,000
126 Burlington Street Dam Modification of the Burlington Street Dam to address public
safety concerns, improve riverbank stability, improve fish
habitat, and create recreational opportunities.
$6,435,000
Total - Unfunded Projects 336,362,466$
652